High CourtsDivision Bench(2025) 12 SHI CK 1818

Madan Gopal vs State Of H.P. & Others

High Court Of Himachal Pradesh · Decided on 10 December 2025

HON’BLE JUDGES
Vivek Singh Thakur, J · Romesh Verma, J
RESULT
Disposed Of
CASE NUMBER
Civil Writ Petition No 19317 Of 2025

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

9 paragraphs · 362 words

Vivek Singh Thakur, J

1.

Notice. Mr. Sushant Keprate, learned Additional Advocate General and Mr. Jia Lal, Advocate under instructions of learned original counsel Mr. Rohan Tomar, Advocate, appear and waive service of notice on behalf of respondents No.1 and 2 as well as respondentCWPNo.19317 ofNo20253 respectively.

2.

Petitioner is aggrieved by induction of limitation period of 6 months in Rule 285 of the Himachal Pradesh Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Rules, 2008 vide Notification dated 24.5.2025, for submission of claims by beneficiaries from the happening/c mpletion of instance.

3.

Prayer has been made o quash the limitation period introduced by aforesaid Notification.

4.

In response, respondents-State through Secretary Labour Employment & Overseas Placement, to the Government of Himachal Pradesh has placed on record instructions dated 2nd December, 2025, whereby it as been informed that to redress the grievance of the petitioners, appropriate instruction has been issued by the respondents v de communications dated 17.10.2025 and 2.12.2025, whereby it has been clarified that all the claims of workers which have accrued before date of amendment notification i.e. 24.5.2025 shall not be considered time barred and further that the cause of action/incident of all the petitioners in these cases/CWP’s accrued to workers before notification dated 24.5.2025 and the claims, submitted by them after this notification dated 24.5.2025, shall not be considered time barred by the Labour

Welfare Officers and will be entertained for disbursementCWPNoof.19317benefitsof2025 subject to completion of all codal formalities.

5.

It has been further communicated that as the claim of the petitioners in respect of those events that occurred prior to 24.5.2025 will be considered for disbursement by the Labour Welfare Officer even if these have been raised by them after the date of noti ication 24.5.2025.

6.

Copies of communications dated 17.10.2025 and 2.12.2025 sent to Labour Welfare Office s Himachal Pradesh Building and Other Construction Workers Welfare Boa d, have been placed on record.

7.

In view of above, nothing survives to be adjudicated in present petitions and acc rdingly all these petitions are disposed of in terms of instructions imparted by the respondents, placed on record alongwith pending applications, if any.