AI Structured Summary
Not yet generated for this judgment
Judgment
Adv. Nidhi Jain appeared on behalf of the Complainant.
Adv. Siddharth Sharma, Proxy Counsel for the main Counsel Adv. Neha Jain along with Sh. Dheeraj, AR appeared on behalf of the Respondents.
Both parties made joint submission that they are trying to settle the matter amicably and sought sometime to do so.
Request allowed.
The parties may reach a settlement by the next date of hearing.
We note that Respondents have not obtained completion certificate in respect of Plaza-4, “Techno Business Park” Central Square, 20, Manohar Lal Khurana Marg, Bara Hindu Rao, Delhi as yet and therefore it should have registered as on-going project as per Section 3 of RE(RD) Act, 2016.
Since, prima facie, there is a violation of section 3 of RE(RD) Act, 2016 as above, we direct the Respondents to explain as to why action should not be taken against them for violation of Section 3 of RE(RD) Act, 2016 by 31.01.2023.
Case is posted for further hearing on 16.02.2023(Thursday) at 2:30 pm.