Tribunals and CommissionsSingle Bench(2024) 03 RERA CK 4268

M/s SLG Estates Pvt. Ltd. vs M/s Purearth Infrastructure Ltd. & Anr.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 27 March 2024

HON’BLE JUDGES
Anand Kumar, Chairperson
CASE NUMBER
Comp. no. 89/2021
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

17 paragraphs · 342 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

Adv. Nidhi Jain appeared on behalf of the Complainant.

2.

Adv. Venket Rao along with Adv. Pankaj Chadda appeared on behalf of the Respondents and stated the following chronology events;

i.

The project was conceived by M/s DCM, KNA and Ansals in the year 1986.

ii.

Due to differences between the partners the project was taken over by DCM with new partner company M/s Purearth Infrastructure Ltd.

iii.

The complainant Ms. Vinay Abroal made an application for allotment of 400 sq. ft. in the year 1996.

iv.

Complainant filed the application for transfer of name in Complainant’s Company’s name in the year 2006.

v.

Hon’ble High Court of Delhi allowed re-construction of the project in the year 2004.

vi.

The Monitoring Committee set up by Hon’ble Supreme Court sealed the project in the year 2011. Which continued till 2022.

vii.

On 30.05.2012 the building got desealed.

viii.

In 2013, Hon’ble Supreme Court put a ban on construction on all those properties which were under the purview of Monitoring Committee and hence since 2013-22 no construction took place.

3.

Ld. Counsel placed on record a copy of approved sanctioned plan dated 07.11.1996 for development of flattened factory.

4.

When asked, Ld. Counsel for Complainant informed that her client had not made application for refund before coming to this Authority.

5.

Ld. Counsel for Respondents further argued that the present Complainant became an allottee on 17.12.2008 upon allotment of unit and thereafter they paid certain payments taking total amount to Rs. 7,66,000/-.

6.

Ld. Counsel for Respondents further submitted that the project does not require registration with this Authority as it aimed at development of flattened factories.

7.

Ld. Counsel for Respondents requested that this Authority may pass an order that this project is not in the purview of RERA as per submissions made by them.

8.

The Authority asked Ld. Counsel to make it clear as to what their client wants to do with the project since large numbers of allottees are concerned.

9.

Case is posted on 30.04.2024 at 2:30 pm.