Judgment
Adv. Neeraj Matta along with Sh. Shiv Kumar (AR), Sh. Arun Gupta, Company Associate appeared on behalf of the Complainant.
Adv. Ray Vikram Nath along with Adv. Akshat Chaudhary, Adv. Harshvardhan Jha and Sh. Amar Kumar Sahu, Legal Assistant appeared on behalf of the Respondents.
Adv. Nazia Parveen along with Sh. Rahul Verma, AE(B) appeared on behalf of MCD.
Ld. Counsel for Complainant submitted that no conveyance deed has been executed till date by M/s NBCC Ltd. for the subject property and due to non-execution of conveyance deed they have incurred heavy commercial loss. He also submitted that M/s NBCC Ltd. is charging unreasonable maintenance charges from them that too without maintaining building. They claimed that as per RTI it appears that M/s NBCC Ltd. is incurring only half of the maintenance charges collected from allottee, as expenditure on maintenance of the building. This document dated 28.03.2023 is taken on record.
Ld. Counsel for M/s NBCC Ltd. submitted that they are not in a position to execute the conveyance deed as they have yet to execute the lease deed with the L & DO who has not yet agreed to execute the lease deed.
He also submitted that initially they submitted original building plan in 2006 and completed building as per plan and got the partial occupancy certificate from MCD on 29.03.2011. Since, they obtained occupancy certificate before the enactment of this Act, this complaint does not come under the purview of RERA.
Representatives of MCD clarified that MCD had issued occupancy certificate on 29.03.2011 considering the completion of building as per building plans sanctioned in 2006 for which 100 FAR was used. They further informed that M/s NBCC Ltd. submitted another building plan in August 2014 for seeking sanction for utilization of additional FAR allowed as per 2021 MPD. However, before it could be sanctioned it was discovered that M/s NBCC Ltd. had started construction of two additional basements. Considering illegal construction done the building plans for utilizing additional FAR were not released and illegal constructions were sealed. Since then no progress has been made.
Ld. Counsel for Respondents further clarified that since the proposed additional construction remains sealed, the L & DO is not executing the lease deed. He further requested that he may be allowed to make further submissions considering the rejoinder filed by the Complainants.
Request allowed. He may make written submissions by 31.07.2023.
We direct office to issue fresh notice to L & DO for appearing before this Authority in person and submit a status report on project on the next date of hearing along with full details of the case.
Case is posted for further hearing on 23.08.2023 at 2:30 pm.