Tribunals and CommissionsFull Bench(2020) 12 RERA CK 1060

M/s. Purearth Infrastructure Ltd.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 3 December 2020

RESULT
Allowed
CASE NUMBER
F.1/ 12/PR/2017

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

9 paragraphs · 1,034 words

M/s. Purearth Infrastructure Ltd. (the Applicant Promoter) has submitted two successive applications on 18 November 2019 and 16 March 2020 seeking extension of time for completion of their project “The Amaryllis Phase-I” in Karol Bagh (registered as an on-going project on 5 March 2018 vide Registration Certificate No. DLRERA/2018/P0004), beyond 31 January 2020, the date by which the project was scheduled to be completed as per the Registration Certificate.

2.

The Promoter has requested for these extensions on the plea that the delays were caused due to stoppage of work owing to the orders issued by Hon’ble Supreme Court and other Government Authorities including the Environmental Protection (Prevention and Control) Authority (EPCA), and that as such delays were caused by circumstances beyond the control of the Promoters and are accordingly covered under ‘force majeure’ clause.

3.

The documents submitted by the Applicant were scrutinized and a hearing notice was issued to the applicant to appear before the Authority on 5 August, 2020, on which date of hearing the Promoter was directed to reassess the situation to include any delays that were since caused due to Covid-19 Pandemic and to furnish a consolidated picture regarding the expected completion of the project taking into account the series of disruptions and the time period lost because of each such episode. The Applicant/ Promoter was also directed to furnish copies of information provided to the allottees of the project and the matter was listed for hearing on 8 September 2020. Mr. Harsh V. Bansal appeared on behalf of the Applicant Promoter and submitted that he has filed a detailed reply to the notice dated 15 July 2020 stating various grounds including grounds of Force Majeure and the case was listed for a further hearing on 30 September 2020.

4.

The various delays of about 20 months (~600 days) claimed by the Promoter to have been caused by circumstances beyond their control includes 75 days (on six different occasions date-wise) when a complete stoppage of work was ordered by Hon’ble Supreme Court on account of environmental issues; 36 days when partial stoppage of construction was ordered (on two different occasions for a total of 72 days) by EPCA; 46 days on account of ban on Diesel Generator sets by the Delhi Pollution Control Committee (DPCC) owing to environmental issues (10% impact claimed for disruptions caused on three occasions for total of 458 days); three months (90 days) on account of amendment of Unified Building Bye-laws for Delhi; 0.75 months (23 days) on account of extreme weather conditions and four months (~120 days) on account of stoppage of work by contractors owing to disruptions and/or situations such as demonetization and introduction of GST regime. In addition to the above, the Promoter has sought an extension of nine months on account of disruption caused by Covid-19 pandemic.

5.

The various claims made by the Promoter for delay in completion of the project on account of ‘force majeure’ have been considered by the Authority. Seeking an extension of the period of registration on the plea of ‘force majeure’ for the delays caused by stoppage of construction ordered by the Hon’ble Supreme Court and other authorities on environmental issues (75 days + 36 days) appear justified. Further, the delay of 46 days claimed on account of environmental issues leading to a ban on Diesel Generator sets (claimed as 10% of partial disruptions caused on 458 days on three occasions) also appears reasonable. In addition, a period of 9 months as allowed by the appropriate Government i.e., Ministry of Housing and Urban Affairs vide its order No. O-17028/230/2018/Housing-UD/EFS-9056405 dated 13 May 2020 due to delays/ disruptions caused by Covid-19 pandemic needs to be included in the total period of extension for completion of the project despite the admission of the Applicant during the hearing held on 30 September 2020 that construction work on the project was possible to be started partially in July 2020.

6.

The claims made by Promoter for seeking extension owing to delays caused by extreme weather conditions; differences and disputes between contractors; and events such as demonetization, introduction of GST regime are not considered justified for inclusion in the ‘force majeure’ clause as such situations are normally expected to be factored by the promoters/ developers in the usual course of project implementation. Further, the extension claimed on account of any possible delays caused by the need to make alterations in view of the changes in the Unified Building Bye-laws are not considered justified as the promoter Applicant has itself stated that such changes were notified by the Delhi Development Authority on 5 April 2017 i.e. a good 6 weeks before the approval to the sanction plans of the project by NDMC on 17 May 2017. Taking into account that a period of almost four months was available to the Promoter Applicant before it made an application for registration of project was made, it is fair to assume that the promoter would have factored in the time period required by it to make the necessary alterations as required by the modification of the Unified Building Bye-Laws, in the original date of completion of project sought by it in its application.

7.

In view of the above, we are of considered opinion that a total extension of 157 days may be considered for completion of the project, in addition to the nine months (beginning 25 March 2020) of delay and disruptions caused due to Covid-19 pandemic as allowed by the order of the Appropriate Government i.e. the Ministry of Housing and Urban Affairs vide its order No. O-17028/230/2018/ Housing-UD/ EFS-9056405 dated 13 May 2020. Accordingly, an extension of completion of the project is granted for a total of 432 days beyond 31 January 2020. The revised date of completion of the project may accordingly be fixed as 7 April 2021. It is made clear that no further opportunity will be given to the Applicant/ Registrant for an extension of date for completion of the project beyond 7 April 2021 and that the said project must be completed in all respects by that date.

8.

Ordered accordingly.

9.

A Certificate for extension of registration of the project may issue in Form ‘F’ accordingly.