Judgment
Shri Pradeep Kumar Aggarwal, Director along with Shri Abhishek Pandey, Authorized Representative appeared before the Authority and submitted that they have made an application dated 28.06.2022 for giving them registration pending environment and pollution clearance as the project is being developed in an area where other projects have been cleared from these angles.
He further submitted that he has made a detailed submission in this regard to the Authority in his application.
He categorically stated that they undertake to mention in the 'Booking Form' and 'Agreement of Sale' the following clauses.
"The necessary Environment Clearance & Pollution Clearance in respect of this project SAWASDEE NSP is yet to be received from the Ministry of Environment & Delhi Pollution Control Committee, for which the applications have been made on 01.04.2022 and 19.05.2022 respectively. In case the Environment Clearance and or Pollution Clearance is not received by 1st OCT 2022, the persons booking the Shops/Units/Commercial space in the project shall be given refund on demand within 15 days of their making such request in writing with 9% interest (MCLR + 2%)".
He further stated that he is making this request for early registration of the project with the Authority as he has taken Rs. 65 crore loan from DMI finance for the projects SWASDEE NSP and SWASDEE GEMS and there is a heavy burden on him for repayment of this loan. In case Authority allows registration of this project he can seek booking as per RE (RD) Act, 2016 and reduce his financial burden which they have taken for two different projects namely SWASDEE NSP and SWASDEE GEMS. As far as Delhi Jal Bord and Sewerage clearance from DJB is concerned they drew attention of the Authority to letter dated 10.06.2022 issued by DDA.
The case is reserved for orders.