The instant writ petition has been filed with the following prayers:
1)quash and set aside the impugned notice dated 10.04.2026 (Annex.-7) issued by Respondent No. 3;
2)quash and set aside the arbitrary action of the resoondents in closing / obstructing / disabling / rendering non-functional the petitioner's e-ravana / e-transit / dispatch facility and all consequential proceedings and action pursuant to the notice dated 10.04.2026 (Annex.-7}.
3)quash and set aside the Notice dated 30.06.2026 and survey dated 03.06.2026 (Annex.-9) alongwith all all consequential proceedings pursuant thereof.
4)declare that the respondents cannot proceed to raise any coercive demand, levy, penalty, recovery or adverse regulatory action against the petitioner on the basis of the impugned survey unless and until a corrected and lawfully sustainable survey is carried out after associating the petitioner and after supplying complete material relied upon;
5)direct the respondents to forthwith restore and keep functional the petitioner's e-ravana / e-transit facility so as to enable lawful dispatch, transit generation and business operations;
6)restrain the respondents from taking any coercive action or raising any arbitrary demand against the petitioner pursuant to the impugned notice dated 30.06.2026 or the proposed hearing dated 10.07.2026 without first granting due hearing and passing a reasoned order in accordance with law;
The facts, briefly stated, are that the petitioner is a registered partnership firm engaged in mining of Garnet (Abrasive & Gem) under Mining Lease No. 02/1993 since 2007. Pursuant to a spot inspection conducted on 06.04.2026, the respondents prepared an inspection report alleging discrepancy between the estimated production and the quantity covered by e-Rawanas, whereupon a show cause notice dated 10.04.2026 was issued and the petitioner's e-Rawana/e-Transit facility was simultaneously deactivated. The petitioner submitted its reply disputing the inspection report on the ground that it was based on rough estimations and inaccurate measurements. Subsequently, another notice dated 30.06.2026 was issued on the basis of a drone survey conducted on 03.06.2026, which the petitioner alleges to be defective owing to incorrect mapping and non-supply of the survey data and methodology. Contending that no speaking order has been passed, that the deactivation of the e-Rawana facility is arbitrary, and that the opportunity of hearing was illusory, the petitioner has approached this Court.
It has been submitted by the petitioner that the inspection dated 06.04.2026 was carried out in a casual manner, without proper scientific measurement or use of measuring instruments. It is specifically pointed out that one of the pits, which had accumulated rainwater, was not measured but merely assessed by visual estimation, and was recorded as having a depth of approximately 10 metres, whereas the actual depth is of more than 16 metres. It is submitted that this erroneous assessment has materially inflated the estimated excavation quantity attributed to the petitioner, and that the inspecting team did not undertake any effort to ascertain the correct depth despite the same being verifiable.
It is submitted that garnet, being embedded in rock/slab, is recoverable only to the extent of 10% to 15% of the excavated material, and that this percentage varies from lease to lease and even pit to pit, and is never a fixed or flat figure. It is contended that the respondents, while preparing the inspection report, proceeded on the assumption of a flat 10% recovery rate and, on that basis, estimated the petitioner's production at approximately 24,272 Metric Tons, as against 26,497.71 Metric Tons covered by e-Rawanas issued by the petitioner, treating the difference as indicative of misuse of e-Rawanas. Further, it was contended that the drone inspection done was not proper.
It is further submitted by the petitioner that before taking any action under Rule 45(7) and 45(7)(a) of the Mineral Conservation and Development Rules, 2017 (‘MCDR, 2017’), the procedure provided under Rule 11 of the MCDR, 2017, has to be followed. Rule 11 prescribes a specific procedure before mining operations can be suspended for non-compliance with the approved mining plan. It is pointed out that under Rule 11(2), the lessee is first required to be informed in writing of the alleged violation; if the violation is not rectified within 45 days, a show cause notice is to be issued calling for reasons why the operations should not be suspended; and only if no satisfactory reply is received within a further period of 30 days may suspension follow. It is contended that, in the present case, this graded procedure was bypassed in its entirety, the deactivation of the E-Rawana facility was effected simultaneously with, and by, the very notice dated 10.04.2026, without any prior intimation of violation, without the 45-day period to rectify, and without any reasoned order preceding the suspension.
It is further submitted by the counsel for the petitioner that, till date, the respondent remains unaware whether the petitioner has committed any wrong whatsoever, if any, allegedly committed by the petitioner. He submits that despite this complete uncertainty as to the very existence of a violation, the petitioner's e-Rawana facility stands deactivated.
Per Contra, learned Counsel for the respondents, at the outset, raises a preliminary objection to the maintainability of the present writ petition and submits that the petitioner cannot invoke the writ jurisdiction of this Court for the purpose of challenging a mere show cause notice, inasmuch as it is well settled that a show cause notice does not, by itself, give rise to any cause of action or infringe any right of the noticee, unless the same is shown to be wholly without jurisdiction. He further submits that the deactivation of the petitioner's e-Rawana facility is purely an interim and precautionary measure, and not a final order, inasmuch as it has been resorted to only to prevent any further mismatch between the mineral excavated and the quantity sought to be dispatched, pending final determination of the show cause proceedings.
Moreover, it is submitted by the learned counsel for the respondents that the action proposed in the notice dated 10.04.2026 (Annex.7) is under Section 21 (5) of the MMDR Act, 1957 for initiating recovery against the petitioner, so also under the applicable Rules for termination of the mining lease and no action whatsoever has been proposed for suspending the mining lease, therefore, petitioner’s reliance upon Rule 11 (2) and Rule 45 (7) of MCDR, 2017, is misplaced.
Further, the learned counsel for the respondents places reliance on Entry 5 of the Schedule to the Notification dated February 2002 (S.O. 342) issued by the Mines (Gr. II) Department, whereby the power to enter and inspect any mine, inter alia, for enforcement of an order of the Government to suspend or close mining operations, and for stopping and checking illegal movement of minerals, stands delegated, under Section 24(1) of the Mines and Minerals (Development and Regulation) Act, 1957, to the Additional Director (Mines)/Superintending Mining Engineers/Superintending Mining Engineer (Vigilance)/Mining Engineer (Vigilance), within their respective jurisdiction. Thus, respondents were duly authorized and competent to stop and check the movement of mineral, and to enforce suspension of mining operations, in exercise of the said statutorily delegated power, and that the impugned action was accordingly within the lawful competence of the respondent.
Moreover, it is highlighted by the learned counsel for the respondents that the respondents are duly empowered to deactivate the e-Rawana facility of a mining lease-holder, such power being conferred under Clause 1 of the Office Order dated 27.02.2020 (Memo No. DMG/DMGOMS/TP-R Active-Deactive/357-386), issued by the Director, Mines and Geology, Government of Rajasthan. Further, reliance is placed on Clause 4 of the said office order, which contemplates that where an E-Rawannas is deactivated on account of irregularities described in Clauses 1 to 3, it is open to the stakeholder to submit a representation for reactivation, which would then be examined by the Superintending Mining Engineer (Circle) concerned, who, upon the irregularity being found to be rectified or the explanation found satisfactory, and after deposit of the requisite penalty/dues, shall accept or reject the representation and pass a Speaking Order accordingly.
It is further submitted by the learned counsel for the respondent that the said remedy of representation, was available to the petitioner, but that the petitioner has not, till date, availed of or invoked the said procedure by submitting any such representation before the competent authority.
Further, the learned counsel for the respondents, places reliance on the order dated 28.07.2026 passed by the Hon’ble Division Bench in case of State of Rajasthan Vs Dhaka Construction Company, (D.B. Civil Writ No. 857/2026), wherein, it was held that the during the pendency of proceeding, the activation of E-ravannas may give rise to removal of excess excavation, and thus, it would become difficult to monitor and verify the stock.
I have heard learned counsel for the parties and have carefully perused the material available on record.
At the outset, it is necessary to identify the precise scope of the controversy before this Court. The petitioner has raised substantial objections to the factual and technical basis of the proceedings, including the correctness of the measurements recorded during the inspection dated 06.04.2026, the manner in which the depth of the water-filled pit was assessed, the percentage of recovery of Garnet, the estimated quantity of excavation, the comparison between excavation and dispatch, and the methodology and mapping adopted during the drone survey dated 03.06.2026.
These objections cannot be characterized as frivolous. At the same time, their determination would necessarily require examination of technical material, mine plans, survey records, measurements, geological characteristics, production and dispatch records, e-Rawanna data, and the methodology adopted for computing excavation and recoverable mineral. Such an exercise is essentially fact-finding in nature and falls, in the first instance, within the domain of the competent mining authorities. This Court, while exercising jurisdiction under Article 226, does not ordinarily undertake an original technical adjudication merely because the correctness of a departmental inspection or survey is disputed.
The Court is conscious that judicial review is available where there is patent lack of jurisdiction, violation of statutory procedure, breach of principles of natural justice, mala fides, or manifest arbitrariness. However, the existence of disputed technical questions does not, by itself, furnish a ground for the constitutional court to substitute its own assessment for that of the specialised statutory authority at the stage when the proceedings are yet to culminate in a final order.
The notices issued to the petitioner refer, inter alia, to alleged contraventions of Section 4(1) and Section 4(1A) of the MMDR Act, Rule 45(7) of the MCDR, 2017, Rule 11 of the MCDR, 2017 and the Minerals (Other than Atomic and Hydro Carbons Energy Minerals) Concession Rules, 2016 (hereinafter, "MCR, 2016"). The notices further contemplate action including recovery under Section 21(5) of the MMDR Act and termination of the mining lease under the applicable rules.
Section 21(5) of the MMDR Act deals with recovery where a person raises mineral without lawful authority. It enables the State Government, subject to the statutory requirements, to recover the mineral so raised or, where it has already been disposed of, the price thereof, and also the applicable rent, royalty or tax. The provision is therefore concerned with a substantive consequence flowing from an established case of unauthorised raising of mineral; it does not, by itself, prescribe the procedural mechanism governing every form of departmental adjudication preceding such recovery. The same has been reproduced below:
“21. Penalties.―1
[(1) Whoever contravenes the provisions of sub-section (1) or sub-section (1A) of section 4 shall be punishable with imprisonment for a term which may extend to five years and with fine which may extend to five lakh rupees per hectare of the area.
(2)Any rule made under any provision of this Act may provide that any contravention thereof shall be punishable with imprisonment for a term which may extend to two years or with fine which may extend to five lakh rupees, or with both, and in the case of a continuing contravention, with additional fine which may extend to fifty thousand rupees for every day during which such contravention continues after conviction for the first such contravention.]
(3)Where any person trespasses into any land in contravention of the provisions of sub-section (1) of section 4, such trespasser may be served with an order of eviction by the State Government or any authority authorised in this behalf by that Government and the State Government or such authorised authority may, if necessary, obtain the help of the police to evict the trespasser from the land.
[(4) Whenever any person raises, transports or causes to be raised or transported, without any lawful authority, any mineral from any land, and, for that purpose, uses any tool, equipment, vehicle or any other thing, such mineral tool, equipment, vehicle or any other thing shall be liable to be seized by an officer or
authority specially empowered in this behalf. (4A) Any mineral, tool, equipment, vehicle or any other thing seized under sub-section (4), shall be liable to be confiscated by an order of the court competent to take cognizance of the offence under sub-section (1) and shall be disposed of in accordance with the directions of such court.]
(5)Whenever any person raises, without any lawful authority, any mineral from any land, the State Government may recover from such person the mineral so raised, or, where such mineral has already been disposed of, the price thereof, and may also recover from such person, rent, royalty or tax, as the case may be, for the period during which the land was occupied by such person without any lawful authority.”
The petitioner's reliance upon Rule 11(2) of the MCDR, 2017 also requires careful consideration. Rule 11(2) of the MCDR, 2017 applies where mining operations are not carried out in accordance with the approved or certified mining plan, or where information contained in the mining plan is found to be incorrect, misleading or non-compliant with applicable law. The power contemplated by the substantive part of Rule 11(2) of the MCDR, 2017 is a power to suspend all or any of the mining operations, subject to the conditions and safeguards contained in the proviso thereto. The relevant portion of the rule is reproduced below:
"11.Mining operations under mining lease.– (1) No holder of a mining lease shall commence or carry out mining operations in any area except in accordance with the mining plan approved, modified or reviewed by the Indian Bureau of Mines or prepared and certified in accordance with the system established by the State Government pursuant to the proviso to clause (b) of sub-section (2) of section 5 or approved by the competent authority of the Atomic Minerals Directorate for Exploration and Research, in respect of minerals specified in Part B of the First Schedule to the Act where the grade of such atomic minerals is equal to or above the threshold value limits declared under Schedule-A of the Atomic Minerals Concession Rules, 2016.
(2)If the mining operations are not carried out in accordance with the approved or certified mining plan or any information contained in the mining plan is found to be incorrect, misleading or non-compliant with applicable laws including these rules, the competent authority may by order, suspend all or any of the mining operations and permit continuance of only such operations as are required to restore the conditions in the mine as envisaged under the approved or certified mining plan or modified mining plan, for the purpose of restoration to the extent possible:
Provided that the lessee shall be informed in writing about the violation and if the violation is not rectified within a period of forty-five days, a show cause notice shall be 7 issued asking reasons why the mining operations should not be suspended and, further, if no satisfactory reply is received within a period of thirty days, the mining operations shall be suspended:
Provided further that the competent authority may revoke the suspension after compliance by rectifying the violation pointed out in this regard."
The proviso to Rule 11(2) of the MCDR, 2017 prescribes a graded procedure: the lessee is to be informed in writing of the violation; if the violation is not rectified within forty-five days, a show-cause notice is to be issued as to why mining operations should not be suspended; and if no satisfactory reply is received within a further period of thirty days, suspension may follow. The procedure is therefore directly linked to the exercise of the power of suspension contemplated by Rule 11(2) of the MCDR, 2017.
In the present case, however, the notices under challenge does not propose for action to suspend mining operations under Rule 11(2) of the MCDR, 2017. The action contemplated in the notices includes recovery under Section 21(5) of the MMDR Act and termination of the mining lease under the applicable concession rules. The mere fact that Rule 11 or Rule 45 is referred to among the alleged violations does not, without more, transform the entire proceeding into one under Rule 11(2) of the MCDR, 2017 for suspension of mining operations.
At the same time, it would not be correct to hold that Rule 45(7) is wholly irrelevant to the proceedings. Rule 45(7) specifically deals with cases where a holder of a mining lease has submitted incomplete, wrong or false information in daily, monthly or annual returns, or has failed to submit a return within the prescribed time. In the case of a mining lease, Rule 45(7)(a) contemplates, inter alia, suspension of mining operations, prosecution, and recommendation for termination of the mining lease where the suppression or misrepresentation indicates abetment or connivance of illegal mining. The said rule is hereunder reproduced:
"45.Monthly and annual returns.- (7) If it is found that the holder of a mining lease or the person or company engaged in trading or storage or end-use or export of minerals, as the case may be, has submitted incomplete or wrong or false information in daily or monthly or annual returns or fails to submit a return within the date specified; then,–
(a)in the case of mining of minerals by the holder of a mining lease, the Regional Controller of Mines may advise the State Government to,-
(i)order suspension of all mining operations in the mine and to revoke the order of suspension only after ensuring proper compliance;
(ii)take action to initiate prosecution under these rules;
(iii)recommend termination of the mining lease, in case such suppression or misrepresentation of information indicates abetment or connivance of illegal mining;"
Consequently, the applicability and precise consequences of Rule 45(7) would depend upon the nature of the allegation ultimately established and the statutory consequence sought to be imposed. The Court, at this interlocutory stage, is not required to determine whether the alleged discrepancy actually constitutes a false or incorrect return within the meaning of Rule 45(7), nor whether the factual material is sufficient to attract the more serious consequence contemplated under Rule 45(7)(a)(iii). Those questions are matters for the competent authority in the pending proceedings.
In the present matter, however, the notices are still at the stage of calling upon the petitioner to explain the alleged discrepancies. No final order determining the petitioner's liability has yet been passed. The petitioner has, in fact, already submitted its reply to the first notice and has an opportunity to place its objections regarding the subsequent drone survey and other material before the competent authority.
The Court therefore finds no justification, at this stage, to undertake an adjudication of the petitioner's technical objections. Whether the depth of the pit was correctly measured; whether the estimated excavation was scientifically arrived at; whether a flat recovery percentage was impermissibly applied; what proportion of Garnet was actually recoverable; whether the drone survey was correctly mapped; and whether the alleged difference between excavation and dispatch establishes any unlawful raising or misrepresentation are questions which require determination upon technical material and evidence.
The next issue concerns deactivation of the petitioner's e-Rawanna facility. The respondents have produced and relied upon the Notification dated 2nd February, 2002, wherein, the State Government in exercise of powers conferred by sub-section (2) of Section 26 of the Mines and Minerals (Development and Regulation) Act, 1957 (Central Act 67 of 1957), has directed that powers exercised by it under the said Act and Mineral Concession Rules, 1960 in relation to the matters mentioned in column No.2 of the Schedule given therein shall be exercised by the officers or authorities of the Mines & Geology Department, shown against each in column No.4 of the Schedule in addition to the officers/authorities to whom such powers were delegated by previous notification issued from time to time and against Serial No.5 of the said notification for the purpose of entering and inspection of any mines for the purpose of collection of royalty & rent/Survey/prevention of illegal extraction of mineral(s) enforcement of the order of the Government to suspend or close mining operations/stopping and checking of illegal movement of mineral(s)/examination of all type of records relating to mines and minerals movement under Section 24 (1), the officers or authority, who can exercise the said power has been mentioned. The existence and scope of such delegated authority materially distinguishes the present case from one where an action is taken by an officer having no statutory authority whatsoever. The Notification dated 02.02.2002 is taken on record. The relevant part of the Notification is reproduced hereinbelow:
| Sr. No | Matters in relation to which powers may be exercised | Relevant Provisions | Officers or authority by whom to be exercised |
|---|---|---|---|
| 5. | To enter and inspection of any mines for the purposes of collection of royalty & rent/Survey/prevention of illegal extraction of mineral(s), enforcement of the order of the Govt. to suspend or close mining operations/stopping & checking of illegal movement of mineral(s)/ examination of all type of records relating to Mines and minerals movement | Section 24(1) | Additional Director (Mines)/ Sudptg. Mining Engineers/ Supdtg. Mining Engineer (Vigilance)/ Mining Engineer (Vigilance) within their respective jurisdiction. |
For ready reference, Section 24(1) of the MMDR Act, 1957, is reproduced hereunder:
“24.Power of entry and inspection.―(1) For the purpose of ascertaining the position of the working, actual or prospective, of any mine or abandoned mine or for any other purpose connected with this Act or the rules made thereunder, any person authorised by the 1 [Central Government or a State Government] in this behalf, by general 2 *** order, may―
(a)enter and inspect any mine;
(b)survey and take measurements in any such mine;
(c)weigh, measure or take measurements of the stocks of minerals lying at any mine;
(d)examine any document, book, register, or record in the possession or power of any person having the control of, or connected with, any mine and place marks of identification thereon, and take extracts from or make copies of such document, book, register or record;
(e)order the production of any such document, book, register, record, as is referred to in clause (d); and
(f)examine any person having the control of, or connected with, any mine.
(2)xxxxxx”
Thus, the respondents while invoking the powers entrusted under the said notification have stopped the movement of the mineral temporarily by deactivating the E-Rawanna facility.
The respondents have further relied upon the Office Order dated 27.02.2020 governing activation and deactivation of the e-Rawanna facility. The said Office Order has not been challenged by the petitioner in the present proceedings. Clause 4 thereof, as relied upon by the respondents, also contemplates a mechanism for seeking reactivation by submitting a representation before the competent authority and the petitioner has not challenged the said office order dated 27.02.2020.
In the facts of the present case, the respondents have explained that the deactivation has been resorted to during the pendency of proceedings concerning an alleged discrepancy between excavation/production and dispatch, with the object of preventing further dispatch from rendering subsequent verification of stock difficult. The measure has not resulted in termination of the mining lease itself or initiation of recovery, nor has the petitioner been subjected to a final finding of illegal mining. The restriction is presently confined to the e-Rawanna mechanism for dispatch.
Such a temporary regulatory measure, when adopted for the limited purpose of preserving the subject matter of an ongoing inquiry and preventing further dispatch pending verification, cannot, merely because it causes commercial inconvenience, be equated at this stage with a final punitive order. The proportionality of the measure, however, is necessarily linked to the duration of the pending proceedings. An interim measure cannot be permitted to acquire the character of an indefinite penalty merely by reason of administrative delay.
This Court takes into consideration the decision of the Division Bench in State of Rajasthan v. Dhaka Construction Company (supra), wherein, in the factual context before that Court, concern was expressed that activation of e-Rawannas during pendency of proceedings concerning alleged excess excavation could facilitate further removal of mineral and thereby make effective monitoring and verification of stock difficult. The underlying rationale is one of preservation of the subject matter of the inquiry and protection of public revenue pending final determination. The relevant part of the judgment is reproduced below:
“Without prejudicing the case of either party before the Hon'ble Single Judge, and having regard to the submissions advanced by the learned Additional Advocate General, this Court is of the view that, in the given factual matrix, activation of the e-Ravannas at this stage may give rise to removal of excess excavation during the pendency of the proceedings, thereby making effective monitoring and verification of the stock difficult”
The reliance placed by the respondents upon the aforesaid decision, however, cannot be understood as laying down an absolute proposition that an e-Rawanna facility must invariably remain deactivated in every case merely because proceedings are pending. The question has to be examined in the factual and statutory context of each case.
The contention of the petitioner that the writ petition is maintainable because the inspection report and drone survey are allegedly erroneous also cannot, by itself, justify interference at this stage. The petitioner is not remediless. It has an opportunity to place the relevant survey material, measurements, mining plans, geological data, production records, dispatch records and other technical material before the competent authority and to demonstrate why the departmental computation is incorrect.
The legal position concerning interference against a show-cause notice is also well settled. In Union of India v. Kunisetty Satyanarayana, (2006) 12 SCC 28, the Hon’ble Supreme Court reiterated that a writ petition against a mere show-cause notice is ordinarily premature, since the notice by itself does not ordinarily determine any right or liability and the authority may ultimately drop the proceedings after considering the explanation. The relevant paragraph is reproduced below:
“13.It is well settled by a series of decisions of this Court that ordinarily no writ lies against a charge-sheet or show-cause notice vide Executive Engineer, Bihar State Housing Board v. Ramesh Kumar Singh, Special Director v. Mohd. Ghulam Ghouse, Ulagappa v. Divisional Commr., Mysore, State of U.P. v. Brahm Datt Sharma, etc.
14.The reason why ordinarily a writ petition should not be entertained against a mere show-cause notice or charge-sheet is that at that stage the writ petition may be held to be premature. A mere charge-sheet or show-cause notice does not give rise to any cause of action, because it does not amount to an adverse order which affects the rights of any party unless the same has been issued by a person having no jurisdiction to do so. It is quite possible that after considering the reply to the show-cause notice or after holding an enquiry the authority concerned may drop the proceedings and/or hold that the charges are not established. It is well settled that a writ petition lies when some right of any party is infringed. A mere show-cause notice or charge-sheet does not infringe the right of anyone. It is only when a final order imposing some punishment or otherwise adversely affecting a party is passed, that the said party can be said to have any grievance. Writ jurisdiction is discretionary jurisdiction and hence such discretion under Article 226 should not ordinarily be exercised by quashing a show-cause notice or charge-sheet.
15.Writ jurisdiction is discretionary jurisdiction and hence such discretion under Article 226 should not ordinarily be exercised by quashing a show-cause notice or charge-sheet.”
Likewise, in Special Director v. Mohd. Ghulam Ghouse, (2004) 3 SCC 440, the Hon’ble Supreme Court deprecated routine interference by the High Courts at the stage of a show-cause notice, while recognizing that judicial review may nevertheless be exercised in exceptional cases, particularly where the notice is wholly without jurisdiction or otherwise suffers from a fundamental legal defect. The relevant paragraph is reproduced below:
“5.This Court in a large number of cases has deprecated the practice of the High Courts entertaining writ petitions questioning legality of the show-cause notices stalling enquiries as proposed and retarding investigative process to find actual facts with the participation and in the presence of the parties. Unless the High Court is satisfied that the show-cause notice was totally non est in the eye of the law for absolute want of jurisdiction of the authority to even investigate into facts, writ petitions should not be entertained for the mere asking and as a matter of routine, and the writ petitioner should invariably be directed to respond to the show-cause notice and take all stands highlighted in the writ petition. Whether the show-cause notice was founded on any legal premises, is a jurisdictional issue which can even be urged by the recipient of the notice and such issues also can be adjudicated by the authority issuing the very notice initially, before the aggrieved could approach the court. Further, when the court passes an interim order it should be careful to see that the statutory functionaries specially and specifically constituted for the purpose are not denuded of powers and authority to initially decide the matter and ensure that ultimate relief which may or may not be finally granted in the writ petition is not accorded to the writ petitioner even at the threshold by the interim protection granted.”
The principle emerging from these decisions is not that a show-cause notice can never be examined under Article 226. Rather, the Court must determine whether there is a compelling jurisdictional or procedural defect warranting intervention before the statutory authority completes the adjudicatory process. The Court must also avoid granting, at the threshold, the very substantive relief which would effectively pre-empt the statutory proceedings.
Tested on the aforesaid principles, this Court is not persuaded that the present case falls within the exceptional category warranting quashing of the pending notices. The respondents have disclosed the statutory provisions alleged to have been violated, the factual basis of the allegations has been indicated, and the petitioner has been called upon to furnish an explanation. The precise correctness of those allegations remains to be determined by the competent authority.
Equally, this Court is not expressing any opinion on the merits of the inspection report dated 06.04.2026 or the drone survey dated 03.06.2026. Nothing contained in this order shall be construed as an approval of the measurements, estimated excavation, recovery percentage, mapping methodology or the alleged discrepancy between production and dispatch relied upon by the respondents.
For the reasons recorded hereinabove, this Court declines to interfere with the pending show-cause proceedings or the interim deactivation of the e-Rawanna facility at this stage. The writ petition is, accordingly, dismissed.
The writ petition is accordingly dismissed with the aforesaid directions. There shall be no order as to costs.