High CourtsSingle Bench(2009) 11 KAR CK 0084

M. Gangadhar vs The State of Karnataka, Department of Urban Development and The Director of Municipal Administration

Karnataka High Court · Decided on 17 November 2009 · Citation: (2010) ILR (Kar) 119

HON’BLE JUDGES
Ram Mohan Reddy, J
RESULT
Dismissed
CASE NUMBER
Writ Petition No. 28505 of 2009

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

4 paragraphs · 407 words

Ram Mohan Reddy, J.—The petitioner on being appointed as a Junior Engineer in the respondent City Municipal Council in the year 1987, was eligible for promotion to the post of Assistant Executive Engineer, but for the pendency of a departmental proceeding over alleged charges of misconduct initiated on 01.06.2006. The City Municipal Council having promoted the petitioner to the post of Assistant Executive Engineer by order dated 09.06.2009, Annexure-A recalled the same by Order dated 08.09.2009 Annexure-B on the premise of pendency of disciplinary proceedings. Hence, this Writ Petition grounded on violation of principles of natural justice.

2.

The fact that the petitioner had the special knowledge over the initiation of disciplinary proceedings as on 01.06.2006 while a Junior Engineer in the respondent City Municipal Council is not in dispute. The further fact that but for the disciplinary proceeding yet to be completed/concluded, there was no impediment for the respondent City Municipal Council to promote the petitioner to the post of Assistant Executive Engineer on the basis of seniority-cum-merit is also not in dispute. Therefore, the answer to the question as to whether the petitioner was meritorious enough to secure a promotion apparently lies in the decision of the disciplinary authority after the conclusion of the disciplinary proceeding. The City Municipal Council having not referred to the pendency of disciplinary proceeding on the date the petitioner was promoted to the post of Assistant Executive Engineer, the subsequent order Annexure-B, impugned herein, recalling the order of promotion, without notice to the petitioner, cannot be said to be in violation of the principles of natural justice. I say so because, the question of failure to observe natural justice does not at all matter if the observance of natural justice would have made any difference in the admitted or indisputable facts speaking for themselves, since courts do not issue futile writs as observed by the Apex Court in the case of S.L. Kapoor Vs. Jagmohan and Others, .

3.

Indisputably, if the petitioner is absolved of the material allegations in the disciplinary proceeding initiated by the respondent City Municipal Council, it is needless to state that the petitioner would be entitled to all the benefits, both monetary and service, including promotion.

In the result, the petition is without merit and is accordingly rejected. The respondent City Municipal Council is directed to conclude the enquiry proceedings as expeditiously as possible, in any event, within a period of six months from today.