High CourtsSingle Bench(2007) 04 MAD CK 0270

L. Puniakodi vs The Executive Officer, Pammal Municipality

Madras High Court · Decided on 16 April 2007

HON’BLE JUDGES
A. Kulasekaran, J
CASE NUMBER
Writ Petition No. 13762 of 2007 and M.P. No. 1 of 2007

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

13 paragraphs · 613 words

A. Kulasekaran, J.—By consent of the learned Counsel on either side, this Writ Petition is taken up for final disposal. The learned Government Advocate takes notice for the Respondent. Heard both sides.

2.

The learned Counsel for the Petitioner has submitted that the Respondent has issued the impugned communication dated 12.4.2007, directing the Petitioner to remove the culvert, which is constructed for the use and purpose of hoisting their party flag, without affording opportunity to the Petitioner and that the said communication is not in accordance with the provisions of Section 339 of the Tamil Nadu District Municipalities Act, 1920 (hereinafter referred to as the Act) and prayed for quashing of the impugned order.

3.

On the above said contentions, this Court heard the learned Government Advocate for the Respondent.

4.

No where in the impugned communication, any reference is made that any notice was issued prior to passing of the impugned communication.

5.

Section 339(1) of the said Act contemplates. Time for complying with order and power to enforce in default : "(1) Whenever by any notice, requisition, or order under this Act, or under any rule, by-law or regulation made under it, any person is required to execute any work or to take any measures or do anything a reasonable time shall be named in such notice, requisition or order within which the work shall be executed, the measures taken, or the thing done."

6.

Section 339(2) of the said Act contemplates, "If such notice, requisition or order is not complied with within the time so named the executive authority may cause such work to be executed or may take any measures or do anything which may, in his opinion, be necessary for giving due effect to the notice, requisition or order as aforesaid."

7.

Section 339(3) of the said Act contemplates, "If no penalty has been specially provided in this Act for failure to comply with such notice, the said person shall be liable on conviction before a magistrate to a fine not exceeding fifty rupees for every such offence."

8.

Section 199 of the said Act contemplates, "Prohibition against commencement of work without permission : The construction or reconstruction of a building shall not be begun unless and until the executive authority has granted permission for the execution of the work."

9.

Section 363 of the said Act contemplates, "Prohibition against unauthorised dealings with public place or materials : No person shall without authority in that behalf remove earth, sand or other material or deposit any matter or make any encroachment from, in or on any land vested in the municipal council, or river, estuary, canal, backwater or water course (not being private property) or in any way obstruct the same."

10.

It is clear from the Section 339 of the Act, a notice is required prior to passing any order. It is also not in dispute that u/s 199 and 362 of the Act, no work can be carried out without permission from the concerned authorities. In any event, before exercising power, the Respondent ought to have granted an opportunity to the Petitioner, but in this case, the same was not afforded to the Petitioner. Hence, considering facts and circumstances of the case, the impugned communication is kept in abeyance, subject to the conditions mentioned below:

1.

The Petitioner shall sent his explanation within a period of seven days from today.

2.

On receipt of such explanation, the Respondent is directed to give opportunity to the Petitioner and pass orders, on merits and in accordance with law.

3.

The Petitioner in the mean time shall not proceed with further construction. Accordingly, this Writ Petition is ordered. No costs.