[Per; Justice Rakesh Kumar Jain (JM)]: (ORAL)
The challenge in this Appeal is to the Order dated 12.01.2023, passed by the Adjudicating Authority (National Company Law Tribunal, Division Bench-II, Chennai), by which, an Application filed by the Appellants bearing IA(IBC)/785(CHE)/2022 in IBA/1423/2019, for directing the Resolution Professional (‘RP’) of the Corporate Debtor (‘M/s. Landmark Housing Projects Chennai Pvt. Ltd.’) to accept their Claim and further direct him to reconstitute the Committee of Creditors (‘CoC’) by including their names and their Claim, has been dismissed.
The brief facts of the case are that the Appellant booked a Flat with the Corporate Debtor and were allotted Flat No.103 in the Project called ‘EVANIA’, situated at Ramappa Nagar, Perungudi, Chennai, having one covered car park with total apartment area of 1558 Sq. ft. along with UDS of 711 Sq. Ft. for a total Sale Consideration of Rs.1,09,78,037.10/-. The Appellants stated to have paid part of the Sale Consideration to the tune of Rs.70,96,581/- on various dates between 09.03.2015 to 15.10.2015. The Appellants received an email on 21.08.2017 from the Corporate Debtor to choose another apartment constructed by it instead of the one booked by them. The Appellants gave their consent vide email dated 31.08.2017 and confirmed the booking of Flat No. A-404 in the Corporate Debtor’s Project ‘TIVOLI’ at Mogappair.
It is alleged that the possession of the said Flat was never handed over and in the meanwhile, they came to know about the initiation of CIRP Proceedings by the Adjudicating Authority vide its Order dated 29.04.2021 against the Corporate Debtor.
Although, it has come in the Reply of the Respondent No.1 that the Appellant submitted their Claim for an amount of Rs.1,27,94,038/- but it was admitted to the tune of Rs.70,96,581/- as per the Books of Accounts of the Corporate Debtor.
It has come in the Order that the Resolution Plan accepted by the CoC was approved by the Tribunal vide its Order passed in IA(IBC)/417(CHE)/2022 on 27.06.2022 and on the same day, the Appellants filed the Application in question physically before the Tribunal on 27.06.2022. The said Application has been dismissed by the Ld. Tribunal vide its Impugned Order dated 12.01.2023 on the ground that it had become infructuous.
The Prayer made in the Application by the Appellants is for directing Respondent No.1 to accept their Claim and then to reconstitute the CoC by including the name of the Appellants and their Claim. It is pertinent to mention that the Appellant had already filed their Claim and an amount of Rs.70,96,581/-, was admitted, therefore, at the fag end when the Application for approval of the Resolution Plan was allowed on 27.06.2022, the Appellant came with the present Application on the same day for considering their Claim and reconstitution of the CoC which is apparently not justified and hence, the Application has been rightly dismissed by the Ld. Tribunal as having become infructuous.
We do not find any error in the Impugned Order and therefore, the present Appeal is found to be without any merit and the same is hereby dismissed though without any order as to cost.