High CourtsSingle Bench(2017) 09 DEL CK 0055

International Trenching Pvt. Ltd. vs Power Grid Corporation Of India Ltd

Delhi High Court · Decided on 27 September 2017

HON’BLE JUDGES
Sanjeev Sachdeva, J
RESULT
Allowed
CASE NUMBER
Original Miscellaneous Petition (MISC.)(COMM.) No. 32 Of 2017

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

21 paragraphs · 317 words

Sanjeev Sachdeva, J

IA No.11524/2017 (exemption)

Exemption is allowed subject to all just exceptions.

O.M.P.(MISC.)(COMM.) 32/2017

1.

This is a petition under Section 29A of the Arbitration & Conciliation Act seeking extension of time for making the arbitral award.

2.

In the arbitral proceedings, Mr. Justice (Retd.) S.K. Mahajan was appointed as the Presiding Arbitrator. The Reference was entered into by the

Tribunal on 18.04.2016. The Presiding Arbitrator expired on 23.09.2016 and thereafter the present Arbitral Tribunal was constituted on 05.12.2016.

3.

The statutory period calculated from the date of initially entering into the Reference expired on 18.04.2017. With the consent of the parties, the time

for making the award was extended for a period of six months.

4.

The Arbitral Tribunal has noticed that the dispute arises out of an engineering contract and the documents, referred to by the parties, spread over

several volumes.

5.

It is contended by the learned counsel for the parties that the proceedings could not be concluded within the statutory period on account of demise

of the Presiding Arbitrator and the delay that occurred in reconstituting the Tribunal and secondly, on account of the very nature of the disputes

between the parties, which are technical and involves several volumes of documents.

6.

Learned counsel for the parties submit that the delay has not occurred on account of any reason attributable to the Arbitral Tribunal and the parties

have also been diligently prosecuting their respective cases.

7.

Learned counsel for the parties further submit that a further period of six months would be required for the conclusion of the proceedings and for

making the award.

8.

In view of the peculiar facts, as noted above, the time for making the award is extended by a further period of six months. The Tribunal is

requested to make the award within the extended period.

9.

The petition is, accordingly, allowed in the above terms.