High CourtsSingle Bench(2018) 07 J&K CK 0052

Inhabitants Of Village Anji @APPELLANT@Hash State Of Jammu & Kashmir And Ors.

Jammu And Kashmir High Court · Decided on 12 July 2018

HON’BLE JUDGES
Janak Raj Kotwal, J
RESULT
Disposed Off
CASE NUMBER
Other Writ Petition No.1310 Of 2018, Miscellaneous Petition No.01 Of 2018

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

27 paragraphs · 534 words
1.

Through the instant writ petition, petitioners seek the following reliefs:Â

“(a) Commanding the respondents not to carry on the process of muck dumping of yard no. 4 of tunnel T-2 on Katra Reasi Section of USBRL

project beyond the 55 kanals of land falling ulnder Khasra no. 97 situated at village Anji Tehsil & District Reasi which has been acquired by the

respondent No. 3, upon the land of the petitioners, grave yards and natural water spring as the same will cause great prejudice to the right of the

petitioners.Â

(b) Commanding the respondent No. 5 to provide police protection to the petitioners so that the respondent No. 4 will not carried on the muck dumping

on the land of the petitioners.Â

(c) Commanding the respondents to dump the waste material of yard no. 4 of Tunnel T-2 on Katra Reasi section of USBRL project on the land

already acquired by the respondent no. 3 measuring 55 kanals falling under Khasra No. 97 situated at village Anji Tehsil & District Reasi.â€​

2.

The case of the petitioners is that pursuant to Notification dated 09.10.2017, issued by respondent No. 3 under Section 9 and 9A of the Land

Acquisition Act, 1990, land measuring 55 Kanals comprising under Khasra No. 97 situated at Village Anji, Tehsil & District Reasi was acquired by

the respondents for public purpose (Muck Dumping) Yard No. 4 of Tunnel T-2 in Kilometer 33.212 to Kilometer 38.375 on the Katra Reasi Section of

USBRL project. It is stated that respondents instead of dumping the waste material upon the aforesaid land acquired by them, have started dumping

the waste material upon the land of the petitioners and upon the water springs, thereby depriving the inhabitants of the Village Anji from getting

water. It is stated that respondents are damaging the agricultural land of the petitioners on which they are earning their livelihood as they have no

any other source of income except the land on which the respondents are dumping the waste material.

3.

Learned counsel for the petitioners states that petitioners also approached respondent No. 3-Collector Land Acquisition (Addl. Deputy

Commissioner) Reasi by way of representation to redress their grievances, but the same has not been accorded consideration.

4.

During the course of the arguments, learned counsel for the petitioners states that the petitioners would be satisfied, if respondent No. 3- Collector

Land Acquisition (Addl. Deputy Commissioner) Reasi is directed to accord consideration to the representation of the petitioners within some time

frame. There is no legal impediment in granting such relief.

5.

In view of the aforesaid submissions made by learned counsel for the petitioners and in the facts of the case, the instant writ petition is disposed of

by giving liberty to the petitioner to make a fresh representation before respondent no. 3-Collector Land Acquisition (Addl. Deputy Commissioner)

Reasi. On such representation being filed, respondent No. 3-Collector Land Acquisition (Addl. Deputy Commissioner) Reasi shall consider the same

and dispose of the same expeditiously, preferably within a period of two weeks from the date of receipt of certified copy of this order alongwith the

representation.Â

6.

With the aforementioned observations, the writ petition is disposed of along with connected MP.