JUDGMENT (PER BHARATI DANGRE J):-
The four Writ Petitions before us involve the issue of grant of amenity TDR and the Petitions raise a challenge to the orders refusing the same to the Petitioner and the common ground raised is, that they were conferred with the benefit of the Floor Space Index (FSI) and Transferrable Development Rights (TDR) upon handing over their land to the Planning Authority i.e. the Municipal Corporation of Greater Mumbai (MCGM) along with the amenities as per the prevailing policy but they have been denied the benefit of Amenity TDR as per Regulation 34 read with Appendix VII of the Development Control Regulations, 1991 (DCR).
Though we would deal with the facts involved in each Petition as we have heard the respective Senior Counsels representing the rival parties, before we proceed to do so we would like to briefly refer to the statutory provisions governing the field and also briefly refer to the declaration of law by the Apex Court on the said subject, as well as this Court interpreting the statutory provisions.
A) THE PREFACE
The Petitions involve the doctrine of ‘Eminent Domain’, as the claim staked by the Petitioners is for grant of adequate compensation, being conscious of the principle underlying the legal doctrine that empowers the Government authority to acquire private property for public use, provided that ‘just compensation’ is offered to the affected property owners. The legal doctrine of Eminent Domain strikes a delicate balance between promoting social welfare, such as through infrastructure development and urban planning and safeguarding individual property rights. Article 300A of the Constitution, ensures that no one shall be deprived of his/her property except in accordance with law. It is, however, essential that the Government demonstrate genuine public purpose in its acquisition and compensate the property owners fairly, to mitigate the risk associated with this formidable power.
The said principle deserve synchronization with the law prescribing for acquisition of land with award of appropriate compensation which was initially governed by the Land Acquisition Act, 1894 which permitted compulsory acquisition, asserting State’s Authority over individual property rights. The said enactment is now replaced by the Right to Fair Compensation to Land Acquisition, Rehabilitation and Resettlement Act, 2013 and the new legislation aim to enhance transparency and ensure fair compensation based on current market value, and also incorporating provisions for rehabilitation of displaced individuals and communities.
The principle of Eminent domain in India is synonymous with ‘Compulsory Acquisition’ . The current legal structure for exercise of this right by the State Government must strike a chord with the Act of 2013, which has tuned the acquisition of properties with the principle of social justice, so that actual or potential loser receive fair compensation in a fair, speedy and transparent manner. The Act of 2013 has also broadly defined ‘Public purpose’ which has enabled the Government to acquire lands for projects like infrastructure development, urban expansion and public utilities and it is this broad definition that enables the justification for exercise of Eminent domain.
Keeping in tune with the aforesaid principle, the MRTP Act, 1966 contain provisions for compulsory acquisition of the land for ‘Public Purpose’ and since the claim of the Petitioners before us revolve around the statutory scheme contained in the statute as well as the Regulations formulated thereunder, we deem it appropriate to reproduce the provisions highlighting the scheme of acquisition of land and payment of compensation upon such compulsory acquisition.
B) THE STATUTORY SCHEME
The Maharashtra Regional and Town Planning (MRTP) Act 1966, is a statute making provisions for planning the development and use of lands and contain provisions for the preparation of Development Plans with a view to ensure that the town planning schemes are executed effectively. It also contain provisions for compulsory acquisition of land required for public purpose in respect of the said plans and Section 125 prescribe that any land required, reserved or designated in the Regional plan, Development plan or Town planning scheme for a public purpose or purposes including plans for any area of comprehensive development or for any new town shall be deemed to be land needed for a public purpose within the meaning of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2014.
The Maharashtra Regional and Town Planning Act, 1966 in the form of Section 125 contain the provision reflecting the principle of Eminent domain, which permit the State Government to acquire any land needed for public purpose and section 126 provide for acquisition of land required for the said purposes, as specified in the Plans.
The provision existing prior to 25/03/1991 contemplated two modes of acquisition viz. either by Agreement or by making Application to the State Government for acquiring such land under the Land Acquisition Act, 1894. However, in 1991, Section 126 of the MRTP Act, 1966, underwent a substantial change and now it made available one other mode of acquisition in form of clause (b), which entitled the Owner or Lessee to avail, in lieu of any such amount, equivalent to the value of Lessor’s interest, to be determined by any of the Authorities concerned under the Land Acquisition Act, 2013, Floor Space Index (FSI) or Transferable Development Rights (TDR) against the area of land surrendered free of cost and free from all encumbrances and in addition to the above, further additional FSI or TDR against the development or construction of amenity on the surrendered land at its cost, as per the Final Development Regulations prepared in this behalf provided.
At this stage, we deem it appropriate to reproduce Section 126(1), as we are concerned with the said provision as the claim of the Petitioners is for the additional FSI or TDR against the development/ construction of the amenity on the surrendered land. Section 126(1) reads thus :-
“126. Acquisition of land required for public purposes specified in plans
(1)When after the publication of a draft Regional Plan, Structure plan) a Development or any other plan or town planning scheme, any land is required or reserved for any of the public purposes specified in any plan Authority, or as the case may be, any Appropriate Authority may, except or scheme under this Act at any time the Planning Authority, Development as otherwise provided in section 113A acquire the land,-
(a)by agreement by paying an amount agreed to, or
(b)in lieu of any such amount, by granting the land-owner or the lessee, subject, however, to the lessee paying the lessor or depositing with the Planning Authority, Development Authority or Appropriate Authority, as the case may be, for payment to the lessor, an amount equivalent to the value of the lessor's interest to be determined by any of the said Authorities concerned on the basis of the principles laid down in the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, Floor Space Index (FSI) or Transferable Development Rights (TDR) against the area of land surrendered free of cost and free from all encumbrances, and also further additional Floor Space Index or Transferable Development Rights against the development or construction of the amenity on the surrendered land at his cost, as the Final Development Control Regulations prepared in this behalf provide, or
(c)by making in application to the State Government for acquiring such land under the provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, and the land (together with the amenity, if any, so developed or constructed) so acquired by agreement or by grant of Floor Space Index or additional Floor Space Index or Transferable Development Rights under this sections or under the provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, as the case may be, shall vest absolutely free from all encumbrances in the Planning Authority. Development Authority, or as the case may be, any Appropriate Authority.”
The above provision has thus recognised yet another mode of acquisition of land by so prescribing in clause (b) and the petitions before us involve this provision, when the land is acquired by granting the land owner or the lessee, the Floor Space Index (FSI) or Transferable Developmental Rights (TDR) against the area of lands surrendered free of costs and free of encumbrances in lieu of the amount receivable. The said provision also contemplate grant of further additional FSI or TDR, which is available against the development or construction of the amenity on the surrendered land at the cost of the land owner or the lessee, as the final Development Control Regulation (DCR) prepared in that behalf provide.
Upon the land being acquired in the aforesaid manner, as the case may be, it vest absolutely free from encumbrances in the Planning authority and Development authority or as the case may be in appropriate authority.
It is this provision which is the focal point for all the four writ petitions filed before us as the individual Petitioners claim the benefit under the second part of clause (b) in Section 126 in form of additional FSI or TDR against the development/ construction of the amenity on the surrendered plot and upon the said benefit being not granted, the Petitioners have approached this Court and we will be referring to the facts of each petition at the relevant stage.
The MRTP Act has defined ‘Amenity’ in Section 2(2) as below:-
(2)“amenity” means roads, streets, open space, parks, recreational grounds, play grounds, sports complex, parade grounds, gardens, markets, parking lots, primary and secondary school and colleges and polytechnics, clinics, dispensaries and hospitals, water supply, electricity supply, street lighting, sewerage, drainage, public works and includes other utilities, services and conveniences;”
Similarly, ‘Development right’ is defined in Section 2(9A) to the following effect:-
(9A) “Development right” means right to carry out development or to develop the land or building or both and shall include the transferable development right in the form of right to utilise the Floor Space Index of land utilisable either on the remainder of the land partially reserved for a public purpose or elsewhere, as the final Development Control Regulations in this behalf provide;”
The existing provision in the earlier section 126 found its way in harmony with existing Development Control Regulations of 1967 when the owner of the land (including a Lessee) was only entitled to the benefit of Floor Space Index (FSI) which was permitted to be used only on the balance land. The said provision in DCR 1967 read thus :-
II. Development Control Regulation 1967 :
10(2) With the previous approval of Government the Floor Space Indices specified above, may be permitted to be exceeded in respect of buildings of Educational and Medical Relief Institutions and Government and Semi-Government Offices and luxury hotels and in respect of any building on the top of which any revolving structure is to be constructed at a place of Public entertainment or amusement.
“The Municipal Commissioner shall permit additional floor-space index on 100% of the area required for read-widening or for constructing new roads proposed under the Development Plan, or those proposed under any provision of the Bombay Municipal Corporation Act, if the owner (including a lessee) of such land is prepared to release such area for road widening or for constructing new roads without claiming any compensation thereof. Such 100% of the area going under such road-widening or road construction shall be limited to 40% of the area of the plot remaining after release of the land required for such road widening or road construction. This concession would also be available in Industrial Zones.”
In consonance with the aforesaid amendment being introduced in Section 126, DCR, 1991 in force comprised of two Regulations i.e. Regulation 33 in connection with FSI /additional FSI alongwith Regulation 34 regulating transfer of development rights. The said provision read thus :-
DCR 1991, Reg. 33(1)
“33. Additional Floor Space Index which may be allowed to certain categories :-
(1)Road widening and Construction of new Roads:- The Commissioner may permit additional floor space index on 100 per cent of the area required for road widening or for construction of new roads proposed under the development plan or those proposed under the Mumbai Municipal Corporation Act, 1888, excluding areas of internal means of access, if the owner (including the lessee) of such land surrenders such land for road widening or new road construction without claiming any compensation in lieu thereof and hands over the same to the Corporation free of encumbrances to the satisfaction of the Commissioner. Such 100 per cent of the F.S.I. on land so surrendered to the Corporation will be utilisable on the remainder of the land upto a limit of [40 per cent] [40 per cent in respect of plot situated in Mumbai City and 80 per cent in respect of plots situated in the suburbs and extended suburbs] of the area of the plot remaining after such surrender and the balance F.S.I. remaining thereafter shall be allowed to be utilised as a Development Right in accordance with regulations governing Transfer of Development Rights (TDRs) in Appendix VII, or the full FSI on the land is surrendered to the Corporation may be allowed to be used as a Development Right in accordance with the Regulations governing Transfer of Development Rights (TDRs) in Appendix VII. Thereafter the road land shall be transferred in the city survey records in the name of the Corporation and shall vest it in becoming part of a public street as defined in sub-section (3) of section 288 of the Mumbai Municipal Corporation Act, 1888.”
Similarly, Regulation 34 in relation to the Transfer of Development Rights provided as below:-
‘In certain circumstances, the development potential of a plot of land may be separated from the land itself and may be made available to the owner of the land in form of Transferable Development Rights (TDR). These Rights may be available and be subject to the Regulations in Appendix VII.’
Appendix VII under the caption ‘Regulations for the grant of TDR to owners/developers and conditions for grant of such rights contemplated the following:-
“1.The owner (or lessee) of a plot of land which is reserved for a public purpose in the development plan and for additional amenities deemed to be reservations provided in accordance with these Regulations, excepting in the case of an existing or retention user or any required compulsory or recreational open space, shall be eligible for the award of Transferable Development Rights (TDRs) in the form of Floor Space Index (FSI) to the extent and on the conditions set out below. Such award will entitle the owner of the land to FSI in the form of a Development Rights Certificate (DRC) which he may use himself or transfer to any other person. ……
5.The built-up area for the purpose of FSI credit in the form of a DRC shall be equal to the gross area of the reserved plot to be surrendered and will proportionately increase or decrease according to the permissible FSI of the zone where from the TDR has originated:
[provided that in specific cases considering the merits, where Development Plan Roads/ Reservations are proposed in No Development Zone, the Commissioner with prior approval of the Government shall grant FSI for such road land/reserved land equivalent to that of the adjoining zone]
6.When an owner or lessee also develops or constructs the amenity on the surrendered plot at his cost subject to such stipulations as may be prescribed by the Commissioner or the appropriate authority, as the case may be and to their satisfaction and hands over the said developed/constructed amenity to the Commissioner/appropriate authority, free of cost, he may be granted by the Commissioner a further DR in the form of FSI equivalent to the area of the construction development done by him, utilisation of which etc. will be subject to the Regulations contained in this Appendix. ...
15.DRs will be granted and DRCs issued only after the reserved land is surrendered to the Corporation where it is Appropriate Authority, otherwise to the State Government, as the case may be, free of cost and free of encumbrances after the owner or lessee has leveled the land to the surrounding ground level and after he has constructed a 1.5 m. high compound wall (or at a height stipulated by the Commissioner) with a gate at the cost of the owner, and to the satisfaction of the Commissioner, or the State Government (where the Corporation is not the appropriate authority). The cost of any transaction involved shall be borne by the owner or lessee.
[Provided that in case of encumbered plots which are required for implementation of public project on very urgent basis following policy guidelines shall be applicable:-
(1)In case of land which are /were fully encumbered and where encumbrances had/have to be removed and rehabilitated elsewhere by the project implementing authority, the owner of such lands shall be considered eligible for claim of TDR to the extent of 25% of the plot area.
(2)In case of land which are partly encumbered and where encumbrances are/were removed and rehabilitated elsewhere by the Project implementing authority, then the owner of such land will be considered eligible for claim to TDR as under:-
(a)For the portion of land which is was vacant: 100% of the vacant area of land.
(b)For the portion of land which is/was encumbered: 25% of the area of the land under encumbrances.
Project implementing authority shall separately certify the area of land which was vacant and the area of land under encumbrances alongwith details as per the joint measurement survey carried out in this respect with City Survey Officer. The area of vacant land and land under encumbrances shall be clearly distinguished and demarcated, otherwise the land under part encumbrances shall be treated as fully encumbered land.
(3)The owner/claimant has to follow the procedure laid down by the Municipal Corporation of Greater Mumbai for granting the Development Right Certificate.
Provided further that TDR admissible under this Regulation shall also be available in respect of properties owned by Central Government, the State Government and their statutory agencies.]”
For the effective implementation of the provisions of the Act, the State Government is empowered to make Rules by publishing the same in the official gazette. Similarly, the Planning Authority, and in the present case, the Municipal Corporation of Greater Mumbai (MCGM) which is the Planning Authority for jurisdiction of Greater Mumbai, has framed Regulations in exercise of the power conferred under Section 35(1) r/w Section 22M of the MRTP Act, which received sanctions from the State Government.
The first development plan prepared by the Corporation was sanctioned in the year 1964-1967 and which was revised and sanctioned by the State Government in the year 1991-94. On 14/12/1989 the Urban Development Department published Draft Development Control Rules for Greater Bombay, as the MCGM by declaration issued under sub-section (1) of Section 23 read with Section 38 of the MRTP Act gave notice of its intention to prepare a revised development plan for Greater Bombay, which was published in the Maharashtra Government Gazette, Bombay Divisional Supplement on 13/01/1977.
On following the legal formalities stipulated in the MRTP Act, and upon receipt of the recommendations of the advisory committee appointed by the State Government to examine the draft development plan, in exercise of powers conferred by sub-section (1) of section 31 and all other powers enabling in that behalf, the Government of Maharashtra published a notice inviting suggestions and objections in respect of the draft DCR in form of Development Control Rules for Greater Bombay, 1989 covering the building activity and development work in the areas under the jurisdiction of Municipal Corporation of Greater Bombay.
The said rules were accompanied with Appendix VII in form of Rules for the grant of TDR to owners/developers and conditions for grant of such rights and it permitted the owner of the plot of land which is developed or reserved for public purpose in the development plan to be eligible for the award of TDR in form of FSI to the extent and on the condition set out therein and the owner of the land was entitled to the FSI in form of Development Rights Certificate (DRC) which he was entitled to use himself or transfer to any other person.
The DRC as per Appendix VII is to be issued by Commissioner and it shall state the FSI credit in square meters of the built-up area to which the owner of the allocated/designated/reserved plot is entitled as well as the place and the user zone in which the Development Right is earned and the areas in which the credit may be utilized.
The draft also contained a provision to the effect that the built-up area for the FSI credit in form of a DRC shall be equal to 2/3rd of the gross area of the reserved plot provided that in a case where the owner also develop or construct at his cost a public amenity on the reserved plot and surrender the same to the appropriate authority of the State Government, free of cost, the Commissioner, with previous approval of the State Government, may allow him FSI credit higher than 2/3rd of the gross area of the plot in form of DRC.
The DCR 1991 for Greater Bombay came into effect from 25/03/1991 and replaced the existing DCR and it continue to govern building activity and development work in areas under entire jurisdiction of Municipal Corporation of Greater Bombay.
The DCR of 1991 for Greater Bombay defined several terms and amenity was defined as below:-
2(7) “Amenity” means roads, streets, open spaces, parks, recreational grounds, play grounds , gardens, water supply, electric supply, street lighting, sewerage, drainage, public works and other utilities, services and conveniences.
The DCR also assign specific meaning to “Drain” to mean the system or line of pipes, with their fittings and accessories, and it included an open channel for conveying surface water or a system for removal of liquid. Since the Petitions before us has the involvement of DCR of 1991, we would only focus upon Regulation 33 and Regulation 34 thereof along with Appendix VII.
It is in light of the aforesaid statutory scheme in form of the Act of 1966 and the Regulations framed thereunder, we have to examine the rival contentions placed before us for consideration in the four different Petitions. However, it is not that the provision in the DCR of 1991 is receiving consideration from us for the first time as even in the past and to be precise from early 90s, it was subjected to consideration in various proceedings before this Court as well as the Hon’ble Apex Court.
C) SERIES OF LITIGATION
While the DCR, 1991 was in force, the Chief Engineer (Development Plan) issued a circular on 09/04/1996 on the subject of grant of TDR in lieu of construction of amenity as per provision of Regulation 34 read with clause (6) of Appendix VII and the said circular prescribed percentage of FSI which would be made available in terms of clause (6) for different type of amenities in the surrendered plot. It provided for 100% FSI in case of built-up area and amenities like General Hospital and Fire Station etc, but in case of open space amenities like garden, playground, Recreation Ground (R.G.), parking, open spaces, and burial ground and in case of construction of D.P. road, widening of existing roads etc, the FSI which could be availed was restricted to the extent of maximum 15% of the area of amenities and was made subject to the conditions enumerated in the circular.
Yet by another circular, the percentage was increased to 25% from 15%.
These circulars were subject matter of multiple Writ Petitions filed before this Court, lead Petition being filed by Godrej and Boyce Manufacturing Company Ltd., and the competency of the Commissioner in issuing the said circular was questioned, as it restricted the availability of FSI to 15/25 % as against 100% FSI for amenities like buildings, hospital etc. Another question raised was, whether the restriction of percentage regarding the availability of FSI in relation to the development or construction of amenity in a surrendered plot would apply to such development, which was completed or carried out pursuant to the permission granted prior to the issuance of the circular.
The Division Bench of this Court, considered the submission on behalf of the State in the backdrop of the Regulations and in particular Regulation 34 which authorized the commissioner to interpret its provision whenever there was any doubt and in exercise of this power, the authority to whom the power was delegated by the Commissioner prescribe FSI equivalent to the area of construction or development depending upon the value of the construction or development, it could not be said to be an exercise which is arbitrary or unreasonable or mandatory or in contravention of the statutory provision. It was urged that there was no vested rights for availing further TDR in form of FSI in relation to construction and handing over of the amenity in the surrendered plot, though if the owner/developer had carried out construction of amenity according to the terms and conditions approved by the competent authority he can be awarded with additional FSI under clause (6) of Appendix VII.
Factually in all the four cases, it was noted that the availability of FSI was to be made subsequent to the enforcement of the circular though there were some cases, where the approval for construction of amenity was prior to the date of the circular.
The Division Bench in the facts and circumstances, observed that merely because the approval for the construction or development of amenity was granted prior to issuance of circular, would not create any vested right to claim a particular percentage of FSI or even the FSI itself, on account of approval of the amenity but it would depend upon the provisions of law in that regard on the day, on which the FSI is to be granted. It also held that there is neither any retrospective implementation of the circular nor any right created in favour of the Petitioner to demand FSI contrary to the said circular, merely because the construction or development of amenity was approved prior to its issuance and the Court dismissed the writ petitions.
The said decision was subjected to challenge before the Hon’ble Apex Court and came to be decided in case of Godrej and Boyce Manufacturing Company Limited vs. State of Maharashtra1 referred to as Godrej and Boyce (I), when the judgment delivered by the High Court was found to be unsustainable and the stand of the municipal authority was held to be contrary to the law.
The judgment delivered on 06/02/2009 in the backdrop of the concept of ‘amenity’ considered the scheme of the MRTP Act 1966 including Section 126 laying down three modes of acquisition of land required for public purposes specified in the plans.
It also refer to Regulation 34 and Appendix VII, a part of the said Regulation, and determined the principle contention, whether executive instruction could override or supersede the provisions of the Regulations, having statutory force. The argument canvassed on behalf of the State that the law provided for grant of additional development right proportionate to the value of amenity constructed by the owner at his own cost and the circular by the Municipal Commissioner only quantified the exchange value of different kind of amenity in percentage term depending upon the cost of construction or other relevant consideration, did not find favour with the Apex Court.
The reasoning which deserves to be highlighted is the observations in para 51, 52 and 58, of the law report, which is reproduced as below:-
“51.Section 126(1)(b) of the Act uses the word “against”: it speaks of granting FSI or TDR “against the area of land surrendered” and further additional FSI or TDR “against the development or construction of amenities on the surrendered land”. Now, one of the meanings of the word “against: is given as “in return of something” e.g. the exchange rate against Franc” (Chambers 21 Century Dictionary, 1st published in India 1997, reprinted 1999). Webster’s Third New International Dictionary gives the meaning of the word “against” as “in exchange for: in return for”. Concise Oxford English Dictionary gives one of the meanings of the word as “in exchange for, in return for; as an equivalent or set-off for; in lieu of, instead of”.
52.Thus, on the basis of the language used in Section 126(1)(b) it could be legitimately argued that what is contemplated is to recompense the landowner proportionate to the value of the development or construction of the amenity on the surrendered land. But the matter does not stop there. As seen above in Appendix VII to the Regulations Para 5 uses the words “equal to the gross area of reserved plot”. Therefore, insofar as the bare land is concerned there is no difficulty. Para 6 of the appendix, however, uses the words “equivalent to the area of the construction/development” and much argument is made on the meaning of the word equivalent. ….
58.We may here make it clear that we fully appreciate the rationale behind trying to make value of the development/construction rather than its area as the basis to recompense the landowner and for granting the additional FSI or TDR. The submissions of Mr Naphade in that regard are not without substance but that is not the law as it stands and the value of the development/construction can only be made the basis for granting additional FSI or TDR by making suitable amendments in the law and not by an executive circular.”
Recording that if the submission advanced on behalf of the Municipal Authority is accepted it would result into palpably unjust and inequitable results, it was held that the land is designated in the development plan as reserved for any of the purposes or for any of the amenities as defined in Section 2(2) or Regulation 2(7) the owner, is not left with many options and he does not have the same bargaining position as the municipal authority and therefore it was held that the surrender of land in terms of clause (b) of Section 126 (1) cannot be subjected to any further condition than those already provided in the statutory provision. However, it was also observed that it was open for the legislature to add to the conditions prescribed for in the statute but certainly it could not have been done at the hands of the executive.
In light of the aforesaid, the Appeals and the Writ Petitions were allowed and the judgment of the Bombay High Court dated 18/10/2005 was set aside.
As a consequence of the aforesaid ruling, Regulation 33 was promptly amended on 17/06/2010 and the same thereafter read thus:-
"33. Additional Floor Space Index which may be allowed to certain categories:-
(1)Road widening and Construction of new Roads- The Commissioner may permit additional FSI on 100 per cent of the area required for road widening or for construction of new roads proposed under the development plan or those proposed under the Mumbai Municipal Corporation Act, 1888, excluding areas of internal means of access, if the owner (including the lessee) of such land surrenders such land for road widening or new road construction without claiming any compensation in lieu thereof and hands over the same to the Corporation free of encumbrances and after the owner or lessee has levelled the land to the surrounding ground level and after he has constructed 1.5 mt. high compound wall leaving the setback area (or at a height stipulated Commissioner.
When an owner or lessee or Power of Attorney holder/Authority holder also develops or constructs the road on the surrendered land at his cost subject to such stipulations as may be prescribed by the Commissioner to his satisfaction, and hands over the said developed/constructed road to the Commissioner free of cost, he may be granted by the Commissioner additional FSI equal to 25% of the area of this construction/development done by him (This modification will not apply in cases where road FSI is utilized and also full occupation certificate is granted).
Such 100 per cent F.S.I. on land so surrendered to the Corporation and/or FSI towards road area constructed, will be utilizable on the reminder of the land up to a limit of 40 per cent in respect of plot situation in Mumbal City and 80 per cent in respect of plots situated in the suburbs and extended suburbs of the area of the plot remaining after such surrender and the balance F.S.I. remaining thereafter shall be allowed to be utilized as a Development Right in accordance with regulations governing Transfer of Development Rights (TDRs) in Appendix VII, or the full FSI of land surrendered to the Corporation may be allowed to be used as a Development Right in accordance with the Regulations governing Transfer of Development Rights (TDRs) in Appendix VII. Thereafter the road land shall be transferred in the City survey records in the name of the Corporation and shall vest it in becoming part of a public street as defined in sub-section (3) of section 288 of the Mumbai Municipal Corporation Act, 1888.”
Upon the Regulations being amended to the aforesaid effect, Godrej and Boyce Manufacturing Limited, in the capacity of owners of piece and parcel of land situated in S ward of village Ghatkopar, Taluka Kurla, which were reserved in Development Plant for public amenity namely Recreation Ground (R.G.), claimed its eligibility for award of TDR in form of FSI.
According to the Petitioners they surrendered their land covered by RG reservation to the Corporation and was allotted TDR in the year 1996 equal to the area of the said land in accordance with clause (5) of Appendix VII of Regulation 34. As per the Petitioners, it developed the land by incurring expenditure and handed over the amenity/ RG in accordance with the plans/layouts sanctioned by the Corporation and requested for equivalent TDR/FSI under clause (6) of Appendix VII. However, the Corporation refused to oblige by relying on its policy circular that additional TDR would be given only to the extend of 15-25% for roads development/construction and would not be admissible for Recreational Grounds developed.
The Petitioners urged that they had surrendered the land free of costs in due compliance with the provisions of the Regulations and opted to avail TDR in view thereof and the possession of the lands being taken along with the structure on 09/12/1995 and two separate possession receipts were passed on but the Corporation issued DRC restricted only to the FSI of the reserved land as per clause (5) of Appendix VII.
According to the petitioners, they opted to construct and develop the Amenity i.e. the Recreational Ground as per the specifications of the Respondent, with legitimate expectation of obtaining additional TDR in lieu of such construction and development in accordance with clause (6) of Appendix VII of Regulation 34.
Apart from this, the maintenance of the amenity was also undertaken by the petitioners through one firm and when the demand was raised by the petitioners for grant of additional TDR, it was informed that the owners of the surrendered land were not entitled to any TDR in lieu of construction/development of RG.
Therefore, the petitioners approached the Court by filing the writ petition on 28/09/2010, praying for direction for allotment of DRC of total area 31057.30 sq.mts.for construction and development of amenity.
The claim in the petition was strongly opposed on the ground that the amenity was never developed by the petitioner for availing TDR and whatever work was carried out like cutting, filling, etc. it was towards the condition precedent for obtaining the TDR in lieu of surrender of land under reservation as per clause (15) of Appendix VII. The respondents adopted a very specific stand that the petitioner is entitled for basic 100% DRC and after due scrutiny, two separate DRCs were issued in lieu of surrender of land and while accepting the DRC, the issue of additional TDR for construction/development was never raised by the petitioners and the same was handed over by only carrying out the required work as per clause (15) of Appendix VII.
An exhaustive reference is made to the correspondence to establish the fact that the petitioners had undertaken the development of construction of the amenity in terms of clause (6) of Appendix VII and Regulation 34 with approval of the authorities of the Corporation and they are entitled to additional TDR in form of FSI.
On appreciating the rival claims, the Division Bench observed that the petitioners had never submitted any proposal before availing of the additional TDR in terms of clause (6) of Appendix VII of Regulation 34, as in terms of clause (6), the owner or the lessee, who intend to develop or construct the amenity on the surrendered plot at his cost, had to approach either the Commissioner or the appropriate authority with the proposal, which after due scrutiny and subject to such stipulations, as may be prescribed, the owner or the lessee has to carry out the construction. In short, it was noted that there was no claim staked by the petitioners under clause (6), but the claim was only under clause (5) of Appendix VII Regulation 34. It was also noted that the petitioners had not filled in the printed form, as was done earlier while claiming TDR as per clause (5).
In conclusion, the Division Bench held that the request made by the petitioners through two applications for claiming additional TDR against the said lands in terms of clause (6) of Appendix VII was turned down on 27/11/1998, but the petition is instituted on 28/09/2010 i.e. almost after lapse of twelve years and, therefore, inference could be drawn that the petitioners had abandoned their claim for additional TDR in terms of clause (6) of Appendix VII.
The petition was, therefore, dismissed by the Division Bench vide its judgment dated 08/08/2018.
Being aggrieved by the aforesaid decision, Godrej And Boyce Manufacturing Company once again knocked the doors of the Apex Court and the issue is put to rest in case of Godrej And Boyce Manufacturing Company Limited & Anr. Vs. Municipal Corporation of Greater Mumbai & Ors.2 referred to as Godrej and Boyce (II) but only recently i.e. vide judgment dated 08/05/2023.
In the meantime, several writ petitions were filed before this Court, claiming advantage of the ruling in Godrej and Boyce (I) and by a common judgment delivered by the Division Bench on 18/12/2018, a group of petitions were disposed of. The Judgment delivered in Apurva Natwar Parikh and Company Pvt Ltd vs. The State of Maharashtra and Ors3 along with several other writ petitions, revolved around the interpretation and implementation of the decision of the Apex Court in case of Godrej and Boyce (I), which in turn read with Regulation 34 read with clause (6) of Appendix VII of DCR of Greater Bombay.
The Petitioners made grievance about refusal by the Corporation to grant additional TDR equivalent to the area of amenity developed and this claim was based on the decision of the Apex Court and it even raised a challenge to the notification dated 16/11/2016, when the DCR was amended by the State Government exercising the power under clause (c) of sub-section 1(AA) of Section 37 of the MRTP Act. Clause 4.2 of the schedule now provided for grant of TDR against construction of amenity and that brought a major change to the provisions of clause (6) of Appendix VII and infact Appendix VII was obliterated from DCR.
The group of 11 Petitions also included a petition filed by Kukreja Construction Company and though the Division Bench of Justice Oak and Justice R.C. Chagla rejected the challenge to the notification dated 16/11/2016 and held it legal and valid but it was clarified that it will not have a retrospective or retroactive application to a land reserved under the development plan which is surrendered and amenity is developed on the said land by the owner or lessee at his own cost prior to 16/11/2016. It was declared that such cases shall be governed by Regulation 33(1) and clause (5) and (6) of Appendix VII. In case of land reserved for road either in development plan under the MRTP Act or under the provisions of the said Act of 1888 and surrender is made and road is developed on or after 17/06/2010 but before 16/11/2016, the FSI or TDR in lieu of amenity was directed to be governed by Regulation 33 (1) as amended on 17/06/2010.
On analysis of factual aspect in each case, however, it is to be found that the claim was rejected on the ground of delay and laches as it was found that the claim for the TDR for additional amenity to the extent of 100% was made after much lapse of time and therefore, all petitions which received rejection were rejected on the ground that they suffered from delay and laches. Only one petition i.e. WP No. 203 of 2014 was allowed and WP No .1860 of 2017 was partly allowed. However, it is pertinent to note that as far as the petition filed by Kukreja Construction Company, after the decision in case of Godrej and Boyce (II), the petition filed by Kukreja Construction Company was allowed by the Apex Court and we will come to this aspect a little later.
The decision of the Division Bench in Godrej received in depth consideration from the Hon’ble Apex Court when it analysed the Judgment of the High Court in the backdrop of the rival contentions and formulated two issued for consideration as below :-
“(i)Whether the High Court was right in concluding that there was abandonment of claim by the appellants?; and (ii) Whether the finding of fact arrived at by the High Court that the appellants, did not and could not have developed the amenity, calls for any interference, especially in the light of the statutory provisions and the facts that unfold from the correspondence exchanged between the parties?” As far as the first claim is concerned, the Apex Court observed thus :-
“40.In other words, during the period from 1996 to 2009, the right to claim additional TDR was in suspended animation. Therefore, the appellants had to necessarily wait till the cloud over their right got cleared. To say that the wait of the appellants during the period of this cloudy weather, tantamounts to abandonment, is clearly unjustified and unacceptable. Therefore, the finding recorded by the High Court on Question 1 is not in tune with the law or the facts of the present case and hence Question 1 has to be answered in favour of the appellants herein.”
As far as the second issue is concerned, on analysing the statutory scheme, it was noted that the question, whether the appellants did develop amenity or not lies in the correspondence and on a detailed analysis of the correspondence exchanged between the parties, commencing with a letter of 14/07/1994 sent by the architect of Godrej to the Chief Engineer and ending with handing over possession of the land on 09/12/1995 to the Corporation and the Corporation issuing DRC on 02/01/1996 granting TDR for the surrendered land, being covered by the first time zone. The second time zone, according to the Apex Court commenced on 20/11/1996 with Mayfair Housing seeking permission of the Corporation to develop and maintain the Recreation Ground, to be followed by the request for additional TDR dated 17/04/1998 being rejected by the order dated 27/11/1998.
On scrutinizing the correspondence in these two time zones, it is observed that, what was applied by the Architects in first time zone i.e. on 14/11/1994 was only a DRC for the surrender of the land and there was no indication in the said letter that the appellant was interested in developing an amenity for the purpose of claiming additional TDR and that is why, while filling up the printed form, at point No.17, “Whether the reservation is proposed to be built upon as per the plans approved by the Authority concerned as per clause (6) of Appendix VII, if so, details thereof”, the response is, “does not arise as the reservation is for RG.”
This was found to be in contrast with the answer to the very same question, which was accompanied with the letter dated 17/04/1998 in the second phase, when the response was, “...Recreation Ground already developed as per Municipal specifications and various requirements.”
With these peculiar facts, emerging from the correspondence placed on record, it was noted that only when the Developer i.e. appellant No.2, entered into the scene, the claim for additional TDR cropped up i.e. in November 1996, when the developer sought permission to develop and got a power of attorney executed in his favour on 24/12/1996 and till the entry of the developer, only the architects were in picture.
The aforesaid observation lead to a specific conclusion being drawn, that the correspondence shows that the work of cutting, filling, levelling and terracing was completed only to enable the Corporation to accept the surrender of land and grant of TDR i.e. Stage I TDR. It is only in the letter of 28/09/1995 sent by the architect, Worthy Enterprises, there is a mention of “additional amenity” for the first time and actually all the activities undertaken were for the purpose of accepting the land and grant of TDR. By relying upon the possession receipt of 09/12/1995, it is concluded that, the possession receipt make a note of compound wall with a gate being provided and that the DP Road with Storm Water Drain is also constructed and the possession of the land is taken subject to the owner agreeing to rectify the defects in the work and it was clear that whatever works were undertaken by the appellants and their architects, were part of the conditions fulfilled to make the Corporation accept the surrender of land and issue a DRC towards TDR.
It is in the wake of the aforesaid, it was concluded that no Amenity was developed as required by law, by appellant No.1 so as to be entitled for additional TDR and the following specific observation from the Apex Court sealed its fate;
“68.But unfortunately for the appellants, whatever they had done through their Architects up to the date of handing over possession and getting the DRC, was not projected by them as the development of amenity. If all those activities up to the date of handing over possession constituted development of amenity, there was no necessity for Appellant 1 to give PoA to Appellant 2 to undertake the activity of development of amenity and to seek Additional TDR. If the work of development of amenity and the lodging of a claim for additional TDR had been undertaken only after Mayfair Housing entered into the picture, then the appellants became bound by the condition laid down by the Corporation that Appellant 2 will not be entitled to Additional TDR.
69.Therefore, we are of the view that the High Court was right in recording a finding of fact that the appellants did not develop the amenity so as to be entitled to additional TDR. Once the finding of fact made by the High Court in this regard is upheld, the appeal should automatically meet with the fate that it deserves. Accordingly, the appeal is dismissed. There will be no order as to costs.”
D) CONTENTIONS ON BEHALF OF THE PETITIONERS
It is in the wake of the aforesaid pronouncements from the Apex Court, we are called upon to adjudicate the grievance of the Petitioners raised through the four Writ Petitions and before we deal with the facts of each petition and the counter submissions advanced we would consider the broad submissions on which the reliefs is sought by the Petitioner and as to how it is contested.
Learned Senior Counsel, Mr. Nankani, has marked his appearance for the Petitioner in Writ Petition No. 1185 of 2017, whereas learned Senior Counsel, Mr. Samdhani, has represented Petitioners in other three writ petitions. Broadly, it is the contention of the respective senior counsels that once the decision of this Court in Godrej and Boyce is set aside by the Honble Apex Court, delay and laches would not defeat the claim of the Petitioners, and it is imperative for this court to consider the merits of each case. Heavy reliance is placed upon decision of the Apex Court in case of Kukreja Construction Company & Ors. Vs. State of Maharashtra & Ors.4 decided on 13/09/2024 and it is brought to our notice that the decision of the Division Bench and a finding rendered therein that for six years or more no claim was made for 100% TDR on account of construction of amenity but additional Amenity TDR equivalent to 100% of area is sought only after the decision of the Apex Court in case of Godrej and Boyce (I) and our attention is invited to the following conclusion:-
“In all these cases, we find that the writ petitioners/appellants herein had surrendered the reserved land and had also been granted 25% TDR and a representation for additional TDR was made after the judgment of this Court in Godrej & Boyce I and in some cases, the representation was made early but in other cases, the representations were made after some time. It is also noted in Civil Appeal No. 1748 of 2015, in the case of Natwar Parikh, this Court had stated that the decision in Godrej & Boyce I could not be revisited inasmuch as the Mumbai Municipal Corporation could not seek to reargue the matter. Also, the facts in each case on the questions of delay was to be considered as observed by this Court. The issue of abandonment of claim has also been considered and negatived in the judgment of this Court in Godrej & Boyce II. We have referred to the decisions of this Court where the question of delay and laches would not arise in matters such as the present cases. When relief in the nature of compensation is sought, as in the instant case, once the compensation is determined in the form of FSI/TDR, the same is payable even in the absence of there being any representation or request being made. In fact, a duty is cast on the State to pay compensation to the land losers as otherwise there would be a breach of Article 300-A of the Constitution. As rightly contended by the learned senior counsel for the writ petitioners/appellants herein, the respondent-Mumbai Municipal Corporation has not established that owing to a short delay even if it has occurred in any of these cases owing to uncertainty in law, the Corporation has been prejudiced by the same or that the third -party rights had been created which could not be disturbed owing to delay or laches. The calculation of period of delay in the table submitted by learned senior counsel for the Mumbai Municipal Corporation is not acceptable in view of our discussion above. The decisions referred to by us above would clearly indicate that neither the doctrine of delay and laches nor the principle of abandonment of claim or waiver would apply in these cases. Rather the delay has occurred on the part of the Mumbai Municipal Corporation in complying third with the Regulations insofar as these appellants are concerned.
18.1.In view of the aforesaid discussion, we hold that the Bombay High Court was not right in dismissing the writ petitions on the ground of delay and laches. Hence, those portions of the impugned order of the High Court are set aside.
19.We also do not find any merit in the three appeals filed by the Mumbai Municipal Corporation. Having regard to the earlier judgments of this Court, we find that the reasoning of the High Court on merits in the three impugned decisions discussed above is just and proper which would not call for any interference by this Court.
20.Consequently, the civil appeals filed by the writ petitioners/appellants herein are allowed as under:
(i)Those portions of the impugned order dated 18.12.2018 by which the writ petitions were dismissed on the ground of delay and laches are set aside and the respondent Mumbai Municipal Corporation is directed to consider the case of those writ petitioners/appellants herein in light of the judgments of this Court in Godrej & Boyce I and release the balance FSI/IDR to the appellants.
(ii)However, in the case or appellant-Kukreja Construction company and others, the Mumbai Municipal Corporation is directed to consider the nature of the amenities constructed and thereafter to consider their case for additional FSI/TDR.
(iii)The said exercise shall be carried out as expeditiously as possible and within a period of three months from today.”
Mr. Nankani would also place reliance upon the decision of the Apex Court in Brihanmumbai Municipal Corporation and Ors vs. Vijay Nagar Apartments and Ors5 which placed reliance on the decision in Kukreja Construction (Supra).
It is the specific contention of Mr. Nankani that the decision in case of Kukreja Construction (supra) ought to be read as a whole and the ratio flowing therefrom has to be read in the context of the facts of the Petitions considered by the Supreme Court, which are largely similar as the facts in this case. According to him, the Apex Court considered the Petitions, wherein the Petitioners had belatedly claimed the benefits of FSI and additional TDR and allowed the same owing to the rights accruing under Article 300A of the Constitution.
According to Mr. Nankani, in the following decisions, the Apex Court granted the benefit despite the claim being staked after considerable lapse of time:-
“1.1.Jitendra Amritlal Sheth V/s. State of Maharashtra, wherein the Petitioner claimed 100% FSI after 3 years and 11 months and did not claim additional TDR.
1.2.Oberoi Reality Limited and Anr. V/s. MCGM & Anr., wherein the Appellant claimed the rights after 8 years from handing over the amenity.
1.3.Jameel A. Hussain V/s. State of Maharashtra, wherein the Petitioner made an application after the gap of 8 years from handing over of the amenity and after 3 years after the decision in Godrej and Boyce.
1.4.Byramjee Jeejeebhoy Private Limited V/s. Municipal Corporation of Greater Mumbai, wherein the Petitioner applied for grant of 100% additional TDR within 2 years of surrender, however, did not take any action thereafter of 6 and 12 years.
1.5.Girdharlal D. Rughani Alia Thakkar H.U.F. V/s. State of Maharashtra, wherein the Petitioner applied for grant of additional 100% TDR after 10 years from developing the amenity.
1.6.Nanbhoy Jeejeebhoy Private Limited V/s. State of Maharashtra, wherein the Petitioner applied for grant of additional TDR after 8 to 13 years without any explanation.”
Contending that since the Apex Court has allowed the aforesaid Writ Petitions, he would submit that the ratio laid down in Kukreja Constructions (supra) ought to be read in the context of the aforesaid cases. It is also his submission that the stand adopted by the Respondents in their reply affidavit that the Petitioners application was not in proper form and it ought not to be entertained is also hollow as according to him, it is settled law that form of notice or application contained in the Rules cannot be elevated to a mandate that the notice/application ought to convey in substance what ought to be conveyed. He would invoke the principle of law laid down by the Apex Court in Life Insurance Corporation of India vs. Escorts Ltd & Ors6.
Mr. Samdani, the learned senior counsel appearing for the Petitioners in the three Petitions, namely, WP/359/10, WP/2132/15 and WP/2018/19, has asseverated before us that as per Section 126 of the MRTP Act, when the land is acquired for a public purpose, since it is so reserved in any plan or scheme and the mode adopted is the one prescribed in clause (b) of sub-section (1) of Section 126, then the land owner or the lessee is entitled for FSI or TDR against the area of land surrendered free of cost and free from all encumbrances. According to him, the very said provision contemplate additional FSI/TDR against the “development or construction of the amenity” on the surrendered land at his cost, as per the Development Control Regulations in this behalf provide. He would submit that it is only upon the requirements contemplated in sub-section (1) being complied with by the Planning Authority, Development Authority or any other Appropriate Authority, the land shall vest free from all encumbrances in it and, therefore, according to him, it is the statutory obligation of the Authority to ensure that the land owner or the lessee is compensated.
Inviting our attention to Regulation 33, which is a provision of additional FSI and clause (1) thereof, providing for the FSI to be allowed in road widening and construction of new roads, he would submit that the same deal with the first phase of surrender of land as covered under clause (b) of sub-section (1) of Section 126 of MRTP Act. This, in turn, result in grant of additional FSI on 100% of the area required for road widening or construction of new roads, being handed over by the owner, without claiming any compensation free of encumbrances.
However, as far as the second part of sub-clause(b) which exist in form of additional Amenity, is to be found in Regulation 34, which is to be read alongwith Appendix VII, and according to Mr.Samdani, clause (5) of Appendix VII deal with the land component and, the same has to be read alongwith clause (15), which contemplates that DR will be granted and DRC issued only when the reserved land is surrendered to the Corporation or otherwise to the State Government after complying with three stipulations, namely, the land is levelled to the surrounding ground level, construction of 1.5 meter high compound wall and construction of a gate, all at the cost of the owner, to the satisfaction of the Commissioner or the State Government and upon such compliance, a DRC equal to the gross of the reserved plot to be surrendered shall be granted.
However, as per Mr.Samdani, clause (6) pertains to the handing over of amenity, when the owner or the lessee, develop or construct the amenity on the surrendered plot and in the manner prescribed by the Commissioner and when he hand over the developed/constructed amenity free of cost, he is entitled for a further DR in form of FSI equivalent to the area of construction development done by him, utilization of which shall be subject to the Regulations contained in the Appendix. However, after the decision in case of Godrej And Boyce (I), Regulation 33 was amended and as far as the Road is concerned, it continued to remain 100% of the area required, but the proviso inserted, covered the development or construction of the road and the entitlement was curbed to 25% of the area of the construction/development done. However, this clause came with a clarification that this modification will not apply in cases where road FSI is already utilized and full occupation certificate is granted.
It is the submission of Mr.Samdani that the clause in the amended Regulation 33 related to a road amenity and for this purpose, there is no need to take recourse to Regulation 34 and for construction of a Road amenity, from 17/06/2010, an owner or lessee is entitled for additional FSI equal to 25% of the area of the construction. However, this capping of 25% will not apply in cases where road FSI is already utilized and full occupation certificate is granted.
Learned Senior Counsel, Mr. Samdhani, has focused his attention on the statutory scheme and it is his categorical submission that the whole idea involved acquisition of land for public purpose and though initially, it was thought to award compensation in kind and therefore FSI was allotted and a particular percentage of which was to be utilized in development of the land on the same plot, subsequently with the provision of Section 126 being modified in lieu of the compensation provision for FSI/TDR was introduced. According to him, when the provision of acquiring land by either of the modes and in particular clause (b) is concerned, which now allowed additional FSI/TDR for construction/development of amenity, it involves two components; (i) surrender of land which is the first phase and (ii) development and construction of the amenity which is the second phase.
He would invite our attention to the definition of the term ‘Amenity’ under the MRTP Act, as well as the DCR and drawing a distinction, he would submit that roads/streets are to be laid but an amenity like RG will have to be constructed. According to him, every word used in the said definition of the term ‘amenity’ as well as in the agreement will have to take colour from the context in which it is used. He would also place reliance upon the latest decision of the Apex Court in case of Brihanmumbai Municipal Corporation vs. Vijay Nagar Apartments (Supra). He would specifically invoke the observations to the following effect:-
“50.This Court in Kukreja Construction (supra) has placed reliance on its earlier judgment in Kazi Moinuddin Kazi Bashiroddin v. Maharashtra Tourism Development Corporation, where this Court held that in matters relating to payment of amount of compensation to land losers, if at all two views are possible, the view that advances the cause of justice is always to be preferred rather than the other view, which may draw its strength only from technicalities. 62. In matters which relate to payment of fair compensation against acquisition of land, the State is obligated to fairly compensate the owner of the land since it is a curtailment of his legal right to enjoyment of such land. It is an intrinsic aspect of Article 300A. Upon such acquisition, a duty is cast on the State to make good-the compensation as determined under the relevant statute, in this case, MRTP Act and the regulations framed thereunder. circumstances, we see no reason to differ from the view taken by this Court in Kukreja Construction (supra) in respect of effect of delay and laches in the claim for conferment of additional TDR against construction of amenity under Section 126(1)(b) of the MRTP Act.”
Another judgment, he would rely upon is of T Bhimjyani Realty Pvt Ltd vs. State of Maharashtra and Ors7. It is specific contention of Mr. Samdhani that though the 2013 Act, to have a fair compensation award is introduced, the mindset of the respondent authorities has remained unchanged, it being that they are discharging their obligation by offering TDR/FSI in lieu of the compensation.
One matter of concern, which is expressed by Mr. Samdani is that when TDR of 2011 is granted in 2024, it do not come with interest and infact the owner was not allowed to use his land as it was acquired but he has been kept out of the benefit for considerable point of time but there is no scheme to compensate. According to Mr. Samdani, the Planning Authority must not behave as if they are obliging the land owner by awarding some compensation which is not fair.
E) CONTENTIONS ON BEHALF OF CORPORATION
The arguments advanced by the respective senior counsels received strong opposition from the Corporation through the affidavits in reply filed contesting the claim in the petition and also through the submissions advanced by the respective senior counsels representing the Corporation. Senior Counsel Mr. G.S. Godbole, has marked his appearance for Corporation in WP No.359 of 2010, and in WP No. 2018 of 2019, whereas Dr. Birendra Saraf, learned Senior Counsel has marked his appearance in WP No. 2132 of 2015. Mr. Aspi Chinoy, learned Senior Counsel has represented the Corporation in WP No. 1185 of 2017 and all of them unequivocally opposed the arguments raised by on behalf of the Petitioners.
The decisions relied upon by the respective counsels for the Petitioners are distinguished by the counsel representing the Corporation and it is their specific contention that the ratio flowing from the said decision has to be read in the facts of the case.
Mr. Chinoy, opposing the writ petition filed by East and West Builders in WP No. 1185 of 2017, apart from advancing his submission in the factual context has assertively submitted before us that unless and until the work done by the claimant was intended to be the construction/development of the ‘amenity’, he is not entitled to claim or receive the additional amenity /additional amenity TDR under Appendix VII. He would submit that if the work has been carried out only for handing over the land, which is phase one and if the Corporation has accepted the surrender of the road, and has granted FSI of 100%, upon the owner satisfying the condition of the layout. But, according to him something more is required to be done to avail the amenity TDR under Appendix VII, as this should be undertaken with an intention to develop / construct an amenity.
According to him, merely because the land owner might have develop a DP garden or construct a DP road in order to make the MCGM accept the surrender of the land (Garden/Road Plot) against grant of FSI/TDR for the area surrender, would not entitle him to claim that he has constructed ‘amenity’ under Appendix VII or to claim additional/amenity TDR under Appendix VII clause (6).
Heavy reliance is placed by Mr. Chinoy upon the judgment of the Apex Court in Godrej and Boyce (II) and according to him, on careful examination of the facts involved would reveal that the Petitioners had developed a garden by levelling and landscaping, planting trees, providing a fountain as per approval of the Superintendent of Gardens and Municipal Commissioner and then surrender it to the MCGM on 14/12/1995. Accordingly, it received land TDR under Appendix VII, clause (5) without staking any claim for additional/amenity TDR under clause (6) of Appendix VII. However, a subsequent claim for amenity TDR for the work of developing the garden plot was rejected by recording that whatever work was carried out by the Petitioner was for the purpose of convincing the Corporation to accept the surrender of the land and to grant TDR. However, the subsequent correspondence reflected that the work of cutting, filling, levelling and terracing was completed only to enable the Corporation to accept the surrender of land and grant TDR. In particular, the observation of the Apex Court to the effect that from the letter dated 20/07/1995, issued by the Chief Engineer laying down certain conditions, including construction of storm water drains, was only for the purpose of grant of DRC, even for surrender of the land and according to Mr. Chinoy, the Apex Court specifically distinguished between the work undertaken as a part of effort to make the Corporation to accept the surrender of land, and to grant TDR and the actual development of amenity for claiming additional TDR.
Learned Senior Counsel Mr. Godbole representing the Corporation in two petitions would also factually contest the case of the Petitioners and he would also place heavy reliance upon the pertinent observations of the Apex Court in Godrej and Boyce (II), when a distinction is made between the work that is carried out for handing over of the land as per the layout and construction/development of the amenity and according to him, in both the cases in which he represent the Corporation, no case is made out for grant of the additional FSI/TDR.
Dr. Saraf, the learned Senior counsel representing the Corporation in WP No. 2132 of 2015 also insist on the aspect that the claimant must express intention to develop the amenity and it must be in specific and cannot be presumed. According to him, whatsoever activity is undertaken by the Petitioner was towards a layout condition as per the prevailing regime. But, after 1991 the Petitioner approached the State Government without mentioning anything about DP Road which was already constructed and FSI utilized.
He therefore, wrote to the Corporation as, it was not accepting the DP Road, stating that he was maintaining the said road but according to Dr. Saraf, the construction was not for availing the TDR and reliance is once again placed in the observation of the Apex Court in Godrej and Boyce (II). According to the learned Senior Counsel, when the Corporation asked the Petitioner to hand over, he chose to construct but in no way the regime of amenity TDR was available when the road was constructed.
In short, the contention advanced through the respective senior counsel on behalf of the Corporation is based on factual aspect though the legal proposition flowing from the authoritative pronouncement is not in question. The respective counsel for the Corporation, do not harp on the point of delay but have specifically urged before us that let the facts in each case be examined to ascertain whether the Petitioners deserve conferment of 100% additional FSI/ TDR in light of the pronouncements of the Apex Court.
F) ANALYSIS OF RIVAL SUBMISSIONS
There can be no doubt about the applicability of the principle of Eminent domain and this principle is found to be implemented through Section 125 of the MRTP Act, 1966 as it contemplate compulsory acquisition of land needed for purposes of Regional plan, Development plan, or Town planning scheme and any land required, reserved or designated in a Regional plan, Structural plan, Development plan or Town planning scheme for public purpose or purposes including plans for any area of comprehensive development or for any new town is deemed to be land needed for a public purpose within the meaning of the Act of 2013.
Section 126 translates the principle contained in Section 125 which permit the Planning Authority, Development Authority or as the case may be any Appropriate Authority, to acquire the land, after publication of a draft Regional plan, a Development plan or any other plan or Town planning scheme if the land is required or reserved for any public purpose specified in any plan or scheme under the Act. Admittedly, prior to 1991, there were only two modes of acquisition that is either by agreement, or by making an application to the State Government for acquiring such land under the Land Acquisition Act, 1894. Therefore, at the relevant time, in this regime, even the Development Control Regulations, made the owner entitled for the FSI and that too in respect of buildings of specific type i.e. Educational and Medical Relief Institutions and Government/Semi Government Offices, and in such cases, when the owner was entitled to release such area for road widening or constructing new roads, without claiming compensation, 100% of the area going under road-widening was directed to be limited to 40% of the area of the plot remaining after release of the land required for such road-widening or construction.
Post 1991, when the provision of Section 126 as it stands today was introduced, though acquisition by agreement by paying an amount was accepted as the first mode of acquisition, but place, a provision was introduced by granting the land owner or the lessee, an amount equivalent to the value of its interest to be determined by any of the authorities on the basis of the principles laid down in the Act of 2013, Floor Space Index (FSI) or Transferable Development Rights (TDR) against the area of land surrendered free of costs and free of all encumbrances. In addition to this, the owner or lessees were also held entitled to further FSI or TDR against the development or construction of the amenity on the surrendered land at his cost, which shall be as per the final DCR prepared in this behalf. The third method of requesting the State Government for acquiring such land continued to remain as one of the mode of acquisition by retaining it in Section 126(1) clause (c).
All the Writ Petitions before us has the involvement of MCGM, and we are concerned with the Development Control and Promotion Regulations for Greater Mumbai 1991 (DCR) formulated by exercising power under the Act of 1966.
Regulation 33 of the said DCR provide for additional floor space index, which was allowed in certain categories, and we are concerned with the category of ‘Road Widening and Construction of New Roads’ .
The aforesaid provision empowered the Commissioner to permit additional floor space index and on 100% of the area required for road-widening or construction of new roads proposed under the DP or roads proposed under the Mumbai Municipal Corporation Act 1888, excluding the areas of internal means of access, provided the owner (including the lessee) surrendered the land for road-widening or for construction of new road, without claiming any compensation in lieu thereof and handover the same to the Corporation free of encumbrances. The 100% of FSI available against the surrender of such land by virtue of the said provision was permitted to be utilisable on the reminder of the land upto a limit of 40%, if the plot is situated in Mumbai city and 80% if the plot is situated in suburbs after such of the area of plot remaining after surrender and the balance FSI was allowed to be utilised as development right in accordance with the Regulations governing Transfer of Development Rights (TDRs) in Appendix VII or the full FSI and the land is surrendered to the Corporation may be allowed to be used by grant of DRC.
The said provision categorically provided that thereafter the road shall be transferred in the city survey record in the name of the Corporation and shall vest in it by becoming a part of ‘public street’ within the meaning of Act of 1988.
As against this, Regulation 34 provided for transfer of development rights where a development potential of a land may be separated from the land itself and is made available to the owner in form of TDR which is subjected to regulation in Appendix VII.
Regulation VII govern the grant of TDR which enable the owner of a plot, which is reserved for a public purpose in the development plan and for additional amenity by treating it as reservation provided in accordance with the Regulations subject to the exception stipulated therein like maintaining open space etc and this enabled the owner to be eligible for the award of TDR in the form of floor space index to the extent and condition set out in the regulation. This FSI is to be allotted in form of a DRC, which was permitted to be used by himself or was allowed to be transferred to some other person.
By virtue of the the said Regulation, where the plot of land is reserved for any purpose contemplated in Section 22 of the MRTP Act, the owner is held eligible for Development Rights (DR) as stipulated in clause (5) and (6), after the land is surrendered free of cost as stipulated in clause (5) and after completion of the development or construction as stipulated in clause (6), if he has undertaken the same.
For our purposes, therefore two clauses are relevant namely clause (5) and clause (6) of Appendix VII of Regulation 34.
Clause (5) deals with phase (1) where, the area of the reserved plot is surrendered by the owner (lessee) and in such a situation, he is entitled for FSI credit in form of DRC, which is equal to the gross area of the reserved plot, which is liable for a proportional increase or decrease according to the permissible FSI of the zone from where the TDR has originated. This provision is however subject to an exception that in specific cases considering the merits where the development plan roads/reservation are proposed in no development zone, then the Commissioner will lead the approval of the government grant FSI for such road land/reserved land equivalent to that of adjoining zone.
Clause (6) deals with the second phase viz, when an owner or lessee also develops or construct the amenity on the surrendered plot at his cost, which is in accordance with the stipulations as prescribed by the Commissioner or the Appropriate authority and thereafter handover the developed/constructed amenity, free of cost. It is in this scenario, he is entitled for grant of a further DR in the form of FSI equivalent to the area of construction/development done by him, utilization of which shall be subject to regulations contained in the Appendix.
Clause (6) therefore clearly deal with availing of the DR for construction/development done by the owner but it is necessary that such an act must be done according to the stipulations prescribed by the Commissioner or the appropriate authority and is upto their satisfaction and a DRC is to be issued only on the satisfactory compliance of the condition prescribed in the Appendix.
The Regulations also prescribed as to how the DRC may be utilised but we are not concerned, with all the other clauses. One important clause of Appendix VII is clause (15) which clearly provide that Development Rights will be granted and DRC shall be issued only after the reserved land is surrendered to the Corporation/ the Appropriate Authority/the State Government, free of cost and free of encumbrances but after the following things being undertaken by the owner; (a) the land of the plot is levelled to the surrounding ground level (b) one construction of 1.5 mtr high compound wall (c) a gate to be erected at the cost of the owner and to the satisfaction of the authority. The cost of any of the aforesaid shall be borne by the owner or the lessee.
The said Regulation also make a provision for lands which are encumbered and it require removal and rehabilitation of the encroachers and in such a case, the owner of such land is held eligible for claiming of TDR to the extent of 25% of the plot area.
However, it is worth to note that, the existing DCR permitted 100% of the FSI on the land so surrendered to the authority, to be utilised in the proportion prescribed. However, in light of the circular issued by Chief Engineer (Development Plan) of the MCGM (BMC), in regards to the availability of the FSI under clause (6) of Appendix VII of the DCR, restricting the entitlement from equivalent to 15 to 25 % as against the one provided in clause (6) that is DR in form of FSI equivalent to the area of construction/development, when the Bombay High Court in Godrej and Boyce (I) upheld the said circular, the Hon’ble Apex Court in Godrej and Boyce (I), held the circular to be unsustainable and it was specifically observed that the surrender of land in terms of clause (b) of Section 126(1) of the Act, cannot be subjected to any further conditions than those already provided by way of statutory conditions. It is apparent that the State Government realizing that if a small work is undertaken like construction of a road passing through a layout being used as a DP Road, grant of DR in form of FSI equivalent to the area of construction/development would create huge burden on the Corporation and therefore, it ventured out to issue a circular and while the Apex Court struck it down, it however, observed that the change can only be effected by amending the Regulations and not by any executive circular issued by the Municipal Authority as the area of construction/development having been fixed by the Regulations as a major of equivalence, land owner was held entitled to determination of equivalence in accordance therewith and not any other basis such as value of the amenity constructed/developed on the surrendered land.
The aforesaid decision of the Apex Court resulted in an amendment in the DCR in the year 2010 and the Road widening and construction of new roads as contemplated in Regulation 33 (1) underwent a change.
By virtue of the said amendment, Regulation 33 relating to the award of additional floor space index for road widening and construction of new roads, entitled the owner to avail additional FSI on 100% of the area required for road widening or for construction upon the owner surrendering such land without claiming any compensation in lieu thereof and handing over the same free of encumbrances to the Corporation and after the owner or lessee has levelled the land to the surrounding ground level, and he has constructed 1.5 mtr high compound wall leaving the setback area with a gate at his cost and to the satisfaction of the Commissioner.
The provision which was added by the amendment, however restricted the FSI benefit to 25% of the area of the construction/development, where the owner or lessee developed or constructed the road on the surrendered land at his cost in terms of the stipulations prescribed by the Commissioner and to his satisfaction and hand over the constructed road to the Commissioner free of cost. However, the provision which was only applicable to the amenity in form of a road, specified that the modification that is the FSI being restricted to 25% of the area of construction/development shall not apply, where the FSI is utilised and full occupation certificate is granted. In short, the capping of the FSI to 25% was not to be made applicable, where the FSI was already utilised and full occupation certificate was granted.
Therefore, as far as the road amenity is concerned, a special provision was made under Regulation 33 itself and though the first component of surrender of the land permitted the owner to avail FSI of 100%, as far as development/construction of the Road on the surrendered land, after the amendment, it was restricted to 25% of the area of the construction/development.
It is pertinent to note that pursuant to the notification of 16/11/2016, Regulation 34 stood substituted by the Schedule and even Appendix VII stood deleted. Clause 3(i) of the schedule made it clear that the same was not applicable in case of earlier land acquisition or development for which compensation was already paid partly or fully and for such surrender no TDR will be available in terms of the schedule. Clause 4.2 of the schedule therefore contain a provision for TDR against construction of amenity and this govern the case of an owner or lessee, who with prior approval of Municipal Commissioner develop or construct the amenity on the surrendered plot or on the land which is already vested in the Planning Authority, at his own cost subject to the stipulation as prescribed and to the satisfaction of the Municipal Commissioner and handed over the said amenity free of cost, then he may be entitle for a TDR in form of FSI as per the formula stipulated as below:-Construction Amenity TDR in square meter = A/B * 1.25
However, this notification being subjected to challenge before the Division Bench, in case of Apurva Natvar Parikh & Co. Private Limited, it was declared that the aforesaid clause will be applicable only with effect from 16/11/2016 and from this date clause (6) of Appendix VII will not apply to the lands with amenity surrendered after that date. With a clear ruling that it do not have a retrospective or retroactive application, we do not think that we have to focus more on the said notification as that is not the issue before us.
After the decision in case of Godrej and Boyce (I) on 06/02/2009 and between the decision of the Apex Court in Godrej and Boyce (II) on 08/05/2023, several writ petitions came to be filed before the High Court, which involved the issue of interpretation and implementation of the decision of Godrej and Boyce (I) dealing with Regulation 34 clause (6) of Appendix VII of DCR of 1991.
A group of petitions was adjudicated by the Division Bench and the judgment delivered on 18/12/2018 included individual cases, where the Petitioners staked claim for grant of 100% DRC by pleading the specific facts peculiar to each of them. This included Writ Petition No. 1898 of 2009 filed by Kukreja Construction Company and Ors vs. State of Maharashtra as well as the case of Nanabhoy Jeejeebhoy Pvt. Ltd. And anr vs. The State of Maharashtra and Ors (WP No. 541 of 2017).
The Petitioners adopted a stand that in cases where they have handed over the constructed DP Road to the Corporation and had received 25% of TDR for construction of D.P. Road, when on 17/06/2010, the DCR 33(1) was amended and restricted the additional FSI to 25% and in Godrej and Boyce, it was held that there was entitlement of receipt of an FSI equivalent to the land surrendered. It was urged that clause (b) of sub-section (1) of Section 126 of MRTP Act provided for grant of compensation in form of FSI/TDR for construction of amenity as provided by the relevant DCR, and the DCR by particular Regulation 34 r/w Appendix VII provided for a complete code for grant of TDR, and if a private land is reserved in a development plan for construction of amenity like a road, the same would be otherwise acquired but by compulsory acquisition and the owner had a choice to refuse to surrender the reserved land without compulsory acquisition if he is not allowed to construct the amenity and claim 100% TDR on account of construction.
To the Contrary, the Advocate General adopted a stand that the State Government had issued a notification on 16/11/2016 and this operated retroactively, and it was intended to apply to the cases which were under consideration of the Planning Authority as well as this Court and if the application for TDR was pending, the same will be considered as per the said notification. It was also argued that the said notification only offered to clarify that the owner will be compensated for constructing amenity on the basis of its value rather than the area thereof and attention was invited to clause 4.2 introduced by the amendment and it was urged that the amendment is declaratory as it declared what was the intention of the legislature.
The decision in case of Godrej and Boyce (I) was invoked to submit that the Apex Court had appreciated the rationale in trying to assess value of the development/construction rather than its area as the basis to compensate the land owner by granting additional FSI or TDR, but it also observed that, that was not the law as it stood then and the value of the development/construction can be made the basis of the grant of additional FSI or TDR by making suitable amendments in the law and not by issuing circular. It was thus urged that the impugned notification introduced the amendment exactly in terms of the observation.
MCGM, however, adopted a stand that the decision of the Apex Court in Godrej and Boyce is per incuriam as it had ignored the effect of Regulation 33 of the DCR. Though the Corporation also adopted a stand that the notification dated 16/11/2016 removed the very basis of the decision in Godrej and Boyce and it also prohibited issuance of TDR in favour of the persons who have already been compensated, it also adopted a stand that there is no vested right for availing TDR in form of DRC.
It is in light of the arguments so canvassed, the Division Bench once again referred to the statutory provisions along with the Regulation 33 (1) which permitted availing of FSI of 100% of area required for road widening or for construction of DP roads, new roads or roads proposed under the Mumbai Municipal Corporation Act, 1888, provided the owner surrenders the land.
However, as far as Regulation 34, which was for grant of TDR, it was noted that the concept of TDR is, that the FSI available in respect of one plot of land can be permitted to be used on another plot and it was governed by Appendix VII.
In light of the statutory scheme, the Division Bench specifically observed under clause (b) of Section 126(1), FSI or TDR against the surrender of land free of cost which is reserved for public purpose on being made available, the land vest in the Planning Authority. In addition, if the owner develops or construct the amenity on the surrendered plot at his own cost, additional FSI or TDR will be granted as per the provisions of DCR.
The Bench therefore held thus “Therefore, when a reserved land is surrendered free of cost to a Planning Authority after developing an amenity thereon at the cost of owner or lessee, there is a provision for grant of additional TDR or FSI against the development or construction of amenity which will be in addition to FSI or TDR in lieu of surrender of the land. Thus, a right accrues to the owner to get FSI or TDR against development of amenity on the surrendered reserved land. Thus, he is entitled to FSI or TDR in respect of development or construction of amenity as per the prevailing DCR on the date of surrender of the land with amenity in addition to the FSI or TDR against the area of land surrendered. The right to get compensation accrues on the date of surrender as on surrender of the land and amenity thereon, it vests in the said Corporation. It is a mode of acquiring a reserved land.”
Drawing a comparison between Regulation 33(1) and Regulation 34 to be read with Appendix VII, the amendment in Regulation 33(1), applicable to reservation of Road from 17/06/2010 was taken note of, as from that date the Additional FSI as provided in clause (b) of Subsection (1) of Section 126 was declared to be 25% of the area of the construction of road and as a result of which for such Amenity, in terms of clause (6) of Appendix VII, the owner or lessee was not entitled to get TDR equivalent to the entire area of road construction but it remained confined to 25%. It was noted that Regulation 33(1) as amended on 17/06/2010 is not modified by the notification of 16/11/2016.
On construing the said notification in the light of the authoritative pronouncements it was noted that none of the counsel had pointed out any provision of MRTP Act, which authorises or permitted the amendment to be carried out which shall have retrospective effect or retrospective operation and none of the rule making provisions provide for enacting DCR with retrospective operation and therefore a declaration was issued that the notification dated 16/11/2016 will not have retrospective application to land reserved under the development plan which is surrendered and amenity is developed by the owner or the lessee prior to 16/11/2016 and such cases were directed to be governed by Regulation 33(1) and clause (5) and (6) of Appendix VII with a further declaration that in case of a land reserved for a road, either in the development plan or under MRTP Act or under the provisions of the Act of 1888 and surrender is made and road is developed on or after 17/06/2010 but before 16/11/2016, the FSI or TDR in lieu of amenity will be governed by the Regulation 33(1) as amended on 17/06/2010.
The argument that the decision of the Apex Court is per incuriam was rejected but, the Petitions were decided on facts of the case and only Writ Petition No.203 of 2014, which formed part of the group, where the DRC was granted by the Corporation on 11/05/2007 on account of surrender of land and when within three years of his surrender i.e. on 2/02/2010, the Petitioner requested for issuance of 100% TDR in respect of the amenity but on 10/12/2010, DRC of 25% of the amenity was granted, by applying the decision in case of Godrej and Boyce (I), it was held that the conduct of the Petitioner cannot be said to be the one, which will prevent the writ court from granting relief in terms of the decision in case of Godrej and Boyce and the Petition was allowed.
Writ Petition No.1898 of 2009, filed by Kukreja was dismissed in the wake of the fact placed before the Court that the Petitioners constructed DP road and a completion certificate was issued on 19/08/1994 and the completion certificate was granted on 17/03/2003, whereas the TDR in respect of the land was issued on 16/03/1994 and 5/04/2003. Noting that the grant of additional TDR was claimed only on 21/07/2003 and the application shows that only 25% TDR was claimed in respect of amenity of DP road, noting that the Petitioner had not thereafter followed the application and no claim was made for six or more years for 100% TDR but only on 28th August, 2009 the additional TDR for the amenity equivalent to 100% of the area was applied for. Recording that the application was made only after the decision in case of Godrej and Boyce and the Petition was filed on 15/09/2009, the claim of 100% TDR was rejected.
All the other Writ Petitions were dismissed baring Writ Petition No. 203 of 2014 and Writ Petition No. 2262 of 2010 which pertains to recreation grounds and a garden and the Corporation issued DRC on 19/04/2007, and it was on 11/02/2010 the petitioner applied for additional 100% TDR on the basis of the decision of the Apex Court, the said Writ Petition was allowed.
The Petition filed by Kukreja Construction Company, which was dismissed by the Bombay High Court was subject matter of a Civil Appeal before the Apex Court along with other Appeals arising out of judgment dated 18/12/2018 as well as the judgment dated 20/10/2022, where Writ Petition No. 411 of 2013 was allowed and the MCGM filed the Appeal.
On a detail analysis of the contention advanced in the backdrop of the statutory schemes and the decision in case of Godrej and Boyce (I) and the Godrej and Boyce (II), the decision of the Bombay High Court in different Writ Petitions was considered and it was noted that the Writ Petitioners/Appellants have surrendered the reserved lands and were granted 25% TDR and a representation for additional TDR was made after the judgment in case of Godrej and Boyce (I) and in some cases representation was made early and in other cases it was made on lapse of considerable time.
Since Godrej and Boyce had directed the question of delay to be considered in each and every case and the abandonment of the claim was negated, it was expressed that the question of delay and laches will not arise in the present cases and the reason for the same was thus recorded:-
“When relief in the nature of compensation is sought, as in the instant case, once the compensation is determined in the form of FSI/TDR, the same is payable even in the absence of there being any representation or request being made. In fact, a duty is cast on the State to pay compensation to the land losers as otherwise there would be a breach of Article 300-A of the Constitution. As rightly contended by the learned senior counsel for the writ petitioners/ appellants herein, the respondent-Mumbai Municipal Corporation has not established that owing to a short delay even if it has occurred in any of these cases owing to uncertainty in law, the Corporation has been prejudiced by the same or that the third party rights had been created which would not be disturbed owing to delay or laches. The calculation of period of delay in the table submitted by learned senior counsel for the Mumbai Municipal Corporation is not acceptable in view of above discussion. Rather delay has occurred on part of the Mumbai Municipal Corporation in complying with the Regulations insofar as the appellants are concerned.”
In light of this, it was held that the Bombay high Court was not right in dismissing the writ petitions on the ground of delay and laches and the portion of the impugned orders to that extent were set aside. Though the Appeals filed by the Corporation were found to be without any merit, and the same were dismissed, the appeal filed by Kukreja was allowed in the following terms:-
“20.Consequently, the civil appeals filed by the writ petitioners/appellants herein are allowed as under:
(i)Those portions of the impugned order dated 18.12.2018 by which the writ petitions were dismissed on the ground of delay and laches are set aside and the respondent Mumbai Municipal Corporation is directed to consider the case of those writ petitioners/appellants herein in light of the judgments of this Court in Godrej & Boyce I and release the balance FSI/TDR to the appellants.
(ii)However, in the case of appellant-Kukreja Construction Company and others, the Mumbai Municipal Corporation is directed to consider the nature of the amenities constructed and thereafter to consider their case for additional FSI/TDR.
(iii)The said exercise shall be carried out as expeditiously as possible and within a period of three months from today.”
One more decision cited before us is in case of Vijay Nagar Apartments and Anr Vs. State of Maharashtra and Ors (supra) decided on 03/04/2024, when the petition was allowed by the Division Bench, which prayed for quashing and setting aside of the impugned communication and sought appropriate writ/directions to the respondents to grant additional amenity TDR for construction and development of garden as per reservation and this petition rejected the ground of delay though it was canvassed that the claim is belated and that the application for TDR was made only after DCPR 2034 came into force. Referring to the decision in case of Godrej and Boyce and in the backdrop of the fact that the garden was being maintained by the Petitioners, the Division Bench concluded thus:-
“51.All that this clause therefore means is that the claim for Amenity TDR would stand suspended or deferred so long as the garden was being maintained by the Petitioners at their costs. Otherwise, there was a complete failure to pay compensation and a result confiscation or expropriation of rights and an executive action directly contrary to the mandate of the statute and to Article 300A of the Constitution of India.
52.On the question of whether it is the later DCPR 2034 or the DCR 1991 that will apply, in our view, there is no question of applying DCPR 2034. The entire development, the LOI, the undertaking and the concept of this form of TDR was predicated on the applicability of DCR 1991. There was no question of anybody being subjected to the discipline of Regulation 32 (4.2) of DCPR 2034. Indeed, to read it like this would require a complete rewriting of the LOI and of the undertaking because the words used in DCPR 2034 (against ‘construction’ of such amenity) are not to be found in the LOI or the undertaking and they are also not to be found in this limited fashion in 126(1)(b) which speaks of TDR against the development or construction of the amenity (not just built up area).”
This decision being challenged before the Apex Court, has resulted into its dismissal and the said judgment in case of Brihanmumbai Municipal Corporation and Ors vs. Vijay Nagar Apartments and Ors (supra), is also placed before us but since it involve an amenity in form of a garden, we would be relying upon the relevant observations only qua the grant of amenity as we in none of the cases we have before us that is the involvement of ‘garden’ as an amenity.
G) INDIVIDUAL WRIT PETITIONS
With this above ratio flowing from the aforesaid authorities, we must now turn our attention to individual writ petitions to ascertain and apply the principle laid down, to the facts in each case.
(I) WRIT PETITION NO. 2132 OF 2015
The petition of M/s. Thakur Sons is slightly different from the other three petitions and as learned senior counsel Dr. Saraf has described the petition as an over-ambitious petition, we must note the factual background before we appreciate the reliefs sought in the petition, directing the MCGM to grant TDR equivalent to the area of DP Road constructed at the cost of the petitioner.
The petition involves DCR 1967 which as per Regulation 10(2) provided for grant of additional Floor Space Index (FSI) on 100% area of the land surrendered for road widening.
The MCGM evinced its intention to prepare a revised Development Plan for Greater Bombay on 13/01/1977, and accordingly, on 30/04/1985, revised draft Building Bye-laws and Development Control Rules were submitted.
As far as the petitioner is concerned, who was seized and possessed the property bearing no.741, 755/A1 and 780/1 admeasuring 12,834.80 sq.m at village Poisar, Taluka Borivali which was affected by 13.40 m and 18.30 m wide DP road under the sanctioned development plan of ‘R’ ward and ear-marked as amenity plot under the provisions of DCR.
When the layout was sanctioned on 30/10/1984, a condition was imposed that the petitioner shall construct the DP Road and hand over the same to the Corporation. On 02/11/1984 the petitioners gave an registered undertaking to the following:-
“3.That the land within the proposed 44'/60’ Development plan road in the owner's holding shall be kept and unbuilt upon and will have to be constructed according to the Municipal Specification, including providing lights, drains etc. and shall be handed over to the Corporation free of cost after construction, whenever required by Corporation. For the portion of the land within the Development plan road, 100% Floor Space Index advantages can be given, if the additional Floor Space is restricted to 40% of the Floor Space Index of the remaining land provided the land in the road portion is handed over to the Corporation without claiming any compensation thereof. In case full Floor Space Index cannot be consumed, due to the restriction, compensation for unused area of land under Development Plan Road will be paid."
According to the petitioner, it constructed the DP road at its own expenses and was granted TDR in lieu of the area surrendered but the amenity TDR is not granted and for this purpose, the petitioner for the first time in 2014, forwarded its request for grant of additional TDR but since the said request was not considered, the petitioner has approached this Court.
It is the case of the petitioner that on construction of the road, the land and reservation was transferred in the name of MCGM and it was mutated in the year 1985 itself, but this was subject to the claim of the petitioner for grant of FSI against the land component. As per the requirement of the Corporation, on the DP Road being constructed, it was also imperative to have street lights on the DP road and the petitioner made necessary payment towards the light charges which was followed by an IOD being issued on 10/02/1987, stipulating conditions for development.
On 11/05/1987, completion certificate was issued by MCGM. This was followed by the publication of revised DCR (Draft DCR 1989) which included the provision for amenity TDR. It is on 20/02/1991, DCR 1991 was notified, which came into force on 25/03/1991 and on 2/05/1991, the petitioner addressed a communication to the Secretary, Housing and Special Assistance Department offering to develop the DP Road on condition of availing construction potential to be used on their balance holding. This was followed by a communication from respondent no.1 to the petitioner on 7/6/1991, stating as below :-
“(a)The Completion Certificate for the DP road was accepted. (b) The responsibility of maintaining DP road in good condition, till such time, the DP road is handed over. (c) Necessary deposit payment receipt for street light poles and part completion certificate for storm water drains submitted by the petitioner was acknowledged.”
According to the petition, on 21/06/1991, the Secretary, Housing and Special Assistance Department, responded to the petitioner’s letter clarifying that the petitioner would be at liberty to claim the benefit of TDR in accordance with the revised DCR for developing the DP Road. The petitioner thereafter, continued to maintain the DP road incurring huge cost for its maintenance and on 30/01/1996, made a request to the Corporation for taking over of the DP road, and it is only on 24/5/1996, the possession of the constructed DP Road was taken from the petitioner and its receipt was passed.
On 06/02/2009, the Apex Court delivered the judgment in Godrej and Boyce (I), declaring that the owner is entitled to additional TDR equivalent to development of unit and the petitioner realising that it had developed the road to the extent of 12,652.80 sq.m, he is entitled to additional TDR in the equivalent figure. It is in 2014 the petitioner made a request for the first time for grant of additional TDR and continued to reiterate its request which was not considered, which constrained the petitioner to approach this Court on 11/06/2015.
The Petition, being argued before us through the learned Senior Counsel Mr. Samdani, who has urged that the construction of amenity, the DP Road, though commenced in 1985-86, it attained completion and was handed over only in the year 1996. Thus, according to him, the vesting of the land along with the amenity in the Corporation took place in the year 1996, but the compensation and right to receive compensation for development of the amenity accrued to and vested in the petitioner in the year 1996 itself and therefore petitioner is entitled for compensation prevailing in terms of DCR 1991 for the development of amenity.
He would submit that under DCR 1967 there was only a provision for grant of FSI and the said provision did not permit the Corporation to add any conditions with respect to the development/construction of road, sewage line, electric poles, drainage line, etc. However, according to the learned Senior Counsel the authorities were conscious of the development plan being revised as the intention was clear in 1977 itself when the process of circulating the draft development plan had already commenced.
According to Mr. Samdani, the petitioner was also aware of the DCR and the provisions of TDR being introduced for development of the amenity and therefore it sought confirmation of its entitlement from the Government in May 1991 and received confirmation of the entitlement. It is not disputed by Mr. Samdani that the surrender of the road duly constructed was in the year 1996, but it is his specific contention that the Corporation cannot deny the rights accrued and vested in the petitioner in view of the confirmation by the State and vesting of Road in BMC only in 1996. It is his specific contention that on the date of handing over of the possession, the right to receive the benefit accrued to the petitioners in terms of the DCR which was in force on that day.
The pleadings in the Petition has received response through an affidavit-in-reply filed by the Executive Engineer (Development Plan) P & R Ward, wherein the following specific defence is adopted in opposing the claim in the Petition;
“a)I say that as per sanctioned Development plan 1967 of R Ward the land bearing CTS No 741, 755A/1 & 780/1 of village Poisar is affected by 44’ feet & 60’ feet wide proposed DP road. Further as per SRDP 1993 of R Ward, the land u/r is affected by 13.40 mtrs & 18.30 mtrs wide proposed DP road. As per Sanctioned DP 2034, the land u/r is affected by existing road.
b)I say that on going through the Record Register maintained by the office of these Respondents it appears that the proposal of handing over of the land bearing CTS No.755, 756, 757, 758, 771, 774 & 775/1 of Poisar Village at Kandivali (East) affected by 44ft.and 60 ft. wide D.P. Road and their junction has been initiated as long as back in the year 1985-86 under No.ACQ/WS/FSI-274. Hereto annexed and marked Exhibit-I is the copy of the said proposal as per Record Register.
d)I say that from the records it appears that the possession of the land bearing CTS No.741 (part), 755/A1 (Part) and 780/1 of village Poisar admeasuring 12652.80 sq. mts. has been taken over by MCGM vide possession receipt under No.ACQ/S/FSI-274 dt.24.05.1996 and title of the said land has been also transferred in the name of MCGM. Hereto annexed and marked Exhibit-II is the copy of Possession Receipt and Property Card Extract. From the entry in the PR card, it is seen that the land u/r has been transferred in the name of MCGM on 18.07.1985 i.e. prior to coming into force DCR 1991. As such the applicant is not liable for any additional TDR for construction of road.
e)I say that it also appears that the Applicant M/s.Thakur & sons had handed over the land under reference affected by D.P. Roads by availing FSI benefit in the layout approved under No.CHE/630/LOR, which was initially approved on 30.10.1984 and amended from time to time. The terms & conditions of layout approved u/no CE/630/LOR in the year 1984 in respect of DP road are as below.
Sr. No 1) That all the access roads shall be constructed and lighted to Municipal Specifications and shall be properly maintained jointly by all subdivided plot holders.
Sr. No 3) That the land within the proposed 44'/60' Development plan road in the owner's holding shall be kept open and unbuilt upon and is to be and will have to be constructed according to the Municipal Specifications, including providing lights, drains etc and shall be handed over to the corporation free of cost after construction, whenever required by the Corporation. For the portion of the land within the Development plan road, 100% Floor Space Index advantage can be given if the additional Floor Space is restricted to 40% of the Floor Space Index of the remaining land provided the land in the road portion is handed over to the Corporation without claiming any compensation thereof. In case, full Floor Space Index cannot be consumed, due to the restriction, compensation for the unused area of land under Development plan road will be paid.”
Referring to the revised guidelines for grant of additional TDR as per clause (6) of Appendix VII in respect of DP Road, handed over in lieu of TDR, after construction of the roads as per layout terms and conditions, it is stated that the guidelines were issued in respect of grant of additional 25% TDR, but it is clearly mentioned that the additional TDR is not applicable to cases, where the DRC for road/set back land had already been issued and the owner had constructed the roads/set back as per layout conditions, but had not claimed additional TDR at the time of application for land TDR. In the following specific words, the Petition is opposed:
“20.I say that in light of the above legal position and the amended provisions of the DCR, the case of the Petitioners would not be a fit case for the grant of additional 100% TDR in the form of TDR for the area equal to the area of the construction / development of each of the D.P. Roads i.e. for an area totally admeasuring 12,652.80 sq.mtrs (i.e. 12834.80 - 182.00) since admittedly compensation has already been paid by way of granting 100% FSI for the area of roads proposed under the development plan in accordance with the Regulation 33(1) and the land has already been handed over to the Respondent No.2.
21... .. ..
22.I say that Govt. of Maharashtra In UDD has sanctioned the revised development plan for Mumbai City on 08.05.2018 excluding the Schedule B which is in EP (Excluded Part). I further say that alongwith DP 2034 the DCPR 2034 has also been sanctioned and came into effect from 13.11.2018. As per the provision of Development Control and Promotion Regulations (DCPR) 2034 the construction amenity TDR is admissible for the Built up area of the amenity on the basis of rate of construction mentioned in the Annual Statement of Rate (ASR) prepared by the Inspector General of Registration for the year in which construction of amenity is commenced and land rate per Square on as per Annual Statement of Rate (ASR) prepared by Inspector General of Registration for the year in which construction of amenity is constructed. There is no provision for granting additional TDR towards the construction of road carried out by the owner.”
The relief in the petition is opposed by Dr. Saraf by clearly submitting that this is a petition of old regime when DCR 1967 was in force and which only made the owner entitled for additional FSI of 100% of the area required for road widening or for constructing new roads proposed, if the owner is prepared to release such area without claiming any compensation. Clause 10(2) further provided that such 100% of the area going under such road widening with road construction shall be limited to 40% of the area of the plot remaining after release of the land required for such widening or road construction.
It is in this regime the petitioner submitted a layout scheme which included construction of DP road and the layout was approved for the said property on 30/10/1984. The petitioner submitted a registered undertaking to the effect that it shall keep the proposed 44/56 ft DP road open and unbuilt upon and shall construct according to the Municipal specifications including making provision for lights, drains etc. and it shall hand over to the Corporation free of cost, whenever required by the Corporation.
It is worth to note that at the relevant time, when this undertaking was given, a new regime of additional amenity TDR/FSI was not in force, and therefore, the undertaking was only to ensure handing over of the road by constructing it as per the specification provided, but this admittedly, was with an intention to avail 100% FSI.
The Corporation approved layout scheme submitted by the petitioner and an IOD was issued on 13/2/1985. It is on 25/3/1985 the Architect of the petitioner requested the Corporation to take over the DP reservation by specifically mentioning that the petitioner had availed the FSI benefits of the DP road. Pursuant to this, the name of the MCGM was mutated in the property register card which is the portion of DP Road, and further for land CTS No.741, the name of the Corporation was mutated in the P.R. Card. The Completion Certificate was issued by MCGM on 11/5/1987. The petitioner’s Architect submitted a detailed report of compliance with all the terms and conditions to the Executive Engineer and informed that “44/60 DP roads are constructed, drained and handed over to MCGB”.
The original P.R card incorporating the name of MCGB are already submitted.
What is pertinent to note is the detailed report submitted by the petitioner was scrutinized and the Junior Engineer, AE-Building Proposal forwarded its report to the Executive Engineer – BPR by endorsing the following :
“Complied with, completion certificate is at page 681/683 All DP roads are handed over to MCGB pg 457, pg.475 and 477”
The FSI for the DP roads was also consumed, as the buildings in the layout was constructed and OC for the building was granted.
The DC Regulations 1991, sanctioned by the State of Maharashtra came into force on 25/03/1991. The petitioner was granted permissions and sanction under the Old DCR 1967 and whatever compliances the petitioner undertook to carry out for the purpose of handing over the land to MCGM was in compliance of the stipulations under the DCR 1967.
After coming into force of the new DCR, the petitioner addressed a letter to the State Government as regards reservations on other CTRs of village Poisar and Kandivali by submitting that they were public reservation such as secondary school, primary school P.G and open space and since BMC was unable to develop the reservation, the petitioner offered to develop them on the terms which could be mutually decided. This included CTS No. 755/A-1 and 780/1.
In response to the offer of the petitioner to develop public reservations, the State Government responded on 21/6/1991 stating that the petitioner would be entitled to claim TDR for the development of such reservation. It is after a gap of five years from this event and to be precise on 30/1/1996, the petitioner addressed a letter stating that they have completed the DP Road in 1985 and also made the payment for street lights but the Department did not take possession of the road and they were required to maintain the same.
Certain shortfalls in the constructed road were notified and ‘the petitioner’ rectified them and again handed over possession of the DP road on 24/05/1996. It is this possession receipt of 24/05/1996 which is relied upon by the petitioner to stake its claim for 100% construction TDR by relying upon Godrej and Boyce as well as Apurva Natwar (supra) and Kukreja Constructions (supra).
In the facts of the case, one factual aspect which emerges with clarity being that the petitioner constructed the road as per layout which was approved and as a condition of this layout, it was to carry out the construction as per municipal specification including making provision of lights, drains etc, and handing it over free of cost whenever required by the Corporation.
This was all done by the petitioner to avail 100% FSI and in fact, on 25/03/1985, when the Architect of the petitioner addressed a letter to the BMC requesting it to take over the land falling in the said reservation, as per condition (i), it clearly indicated that it’s client had availed FSI benefits of DP road and though it was indicated that they are also interested in availing FSI benefits of other reservation as and when Government start giving FSI for such reservation and therefore, the handing over of the reservation for DP road should be treated without prejudice to the owners rights to avail such FSI.
It is noted that the construction on the road by the petitioner was only for the purpose of availing FSI benefit as the condition of the layout itself warranted the petitioner to construct the roads as per municipal specifications and whenever it is required by the Corporation to hand it over to it. The condition clearly prescribed that for the portion of the land within the DP road, 100% advantage can be given if the additional Floor Space is restricted to 40% of the FSI of the remaining land provided the land in the road portion is handed over to the Corporation without claiming any compensation.
It is therefore, pertinent to note that when the petitioner handed over the road, there was no provision for grant of amenity TDR and in fact, all the while, the petitioner staked its claim for TDR in lieu of constructing and handing over the DP road.
The present petition was filed by the petitioner and it was directed to be tagged along with group of petitions and that is why, it continued to remain pending, but we agree with Dr. Saraf that this petition is an over-ambitious attempt of the petitioner to claim additional amenity, and therefore, what is submitted before us by Mr. Chinoy in contesting WP No.1185/2017 is also applicable in case of the petitioner, as we find that prior to 25/3/1991, there was no provision of amenity TDR and only two modes of acquisition were permissible i.e. by way of an agreement or by making an application to the State Government for acquiring such land. The DCR 1967 then only entitled the owner/lessee to the FSI, to be used on the balance land. It is only after 1991 the third mode became available for availing the benefit in lieu of acquisition of the land in form of FSI/TDR against the areas of land surrendered free of cost and free of encumbrances and also further additional FSI or TDR against the development/construction of the amenity on the surrendered land.
In light of the aforesaid and in light of the old regime prevailing when there was no provision for amenity TDR, in our view, the reliefs sought cannot be granted and the petition is liable to be dismissed, and it is accordingly dismissed.
(II) WRIT PETITION NO.2018 OF 2019
The Petition involves plot of land bearing CTS No.374 lying and situated at Village Eksar, Taluka Borivali, Mumbai Suburban District, which involve land admeasuring 274000 sq.mtrs. The Petitioner claims to be the absolute owner of the said plot. As per DCR 1991, about four portions of the land were falling in Recreational Garden i.e. RG-I, RG-II, RG-III, RG-IV and one portion as playground.
The MCGM approved the layout of CTS 374 and between 1995 to 2000, in accordance with the guidelines contained in Circular dated 07/10/1995 for grant of benefit of D.P. Reservation, the Petitioner initiated various steps and handed over possession of the duly constructed amenity and executed transfer documents, resulting into the name of the MCGM being reflected in the property card maintained by the City Survey Office.
In respect of RG-I, on 30/01/2019, the Petitioner made a request for issuance of balance TDR/FSI and additional FSI and the claim was based upon Regulation 34 read with Appendix VII of DC Regulation 1991, as it was stated that the owner of the property which is subjected to a reservation under the sanctioned Development Plan is entitled to TDR equivalent to two times of the area of land reserved, namely, first time in lieu of handing over of the land and second time, in lieu of handing over the constructed amenity to MCGM. Stating that only partial benefit in lieu of handing over of part land was granted and no FSI/TDR was granted for the constructed amenity, though the name of the MCGM is already inserted in the Revenue Record, a request was made for grant of balance TDR/FSI in lieu of handing over constructed amenity for 41,532 sq.mtrs.
Even in respect of RG-II and RG-III, similar requests were made for DRC, as permissible in lieu of handing over constructed amenity on 30/01/2019. A request was also made in respect of CTS No.374B/15 for balance TDR admeasuring about 643.50 sq.mtrs. and in lieu of handing over constructed amenity for 6862.10 sq.mtrs.
It is the claim of the Petitioner that the Respondents are bound to grant additional 100% TDR of Recreational Ground /Playground developed as declared under DCR 1991 and there arises no question on part of the Petitioner to approach the office of the Respondents, seeking permission for developing the amenities. It is specifically pleaded case of the Petitioner that Respondent Nos.2 and 3 have failed to consider that in all RG and PG, the Respondents have issued LOI stipulating various conditions, inter alia, of levelling, construction of compound wall, storm water drain, security cabin etc., and since the amenities are developed on the surrendered plot at the cost of the Petitioner by fulfilling and complying various terms set out in the LOI, the Petitioner’s request for grant of additional FSI in lieu of amenity shall be granted.
The Writ Petition raise a challenge to the refusal to grant Amenity TDR vide letter dated 12/04/2019, in respect of land surrendered by it to MCGM, being reserved for public amenities (Play Ground and Recreation Ground) in the development plan, though the Petitioner stake its claim on the basis of clause (6) of Appendix VII of DCR, on hearing the respective counsel and on perusal of the documents, which are annexed along with the Petition and brought on record on behalf of the Corporation, we find the claim to be unsustainable.
The Petitioner has raised a claim in respect of three parcels of land, but since Mr. Samdani made a statement that the Petitioner will be restricting its claim only in regards to RG-I, and has the involvement of CTS No. 374/B/6(Pt) of Village Eksar, Taluka Borivali and the area involved is admeasuring 41,532.28 sq. mtrs and the claim of the Petitioner is its entitlement to receive TDR of the equivalent area along with the additional TDR for the constructed amenity. Mr. Samdani, make a categorical statement that, his claim as regards RG-III and PG-1 is not pressed and though the liberty is reserved to stake the claim qua this reservation by adopting independent proceedings.
According to the Petitioner, it deposited a sum of Rs. 8,26,500/- to cover defect liability in respect of the construction/development of the amenity and the Petitioner also furnished a registered undertaking in favour of MCGM to rectify the defects. In the year 2009, the Petitioner handed over possession of RG for receiving the first component of TDR (land component) and thereafter, certain shortfalls were notified and the Petitioner also rectified the shortfalls and carried out the work to the satisfaction of the Respondents. According to Mr. Samdani, there is no response to the aforesaid aspect by the Corporation and he would submit that on rectifying all the shortfalls, the Petitioner executed registered declaration from indemnity for transfer of land in favour of MCGM in terms of Section 126(1)(b) and on 19/09/2017, the name of MCGM was duly noted in the PR card.
As a consideration of the aforesaid, the Petitioner received 75% of the land component TDR/FSI and therefore, it claims the balance 25% of it. The Petitioner also stake a claim of 100% of the additional Amenity TDR. The application preferred by the Petitioner for balance 75% TDR and 100% of the additional amenity TDR clearly depict that the Petitioner staked its demand for balance TDR/FSI in lieu of handing over constructed amenity and for granting two times TDR/FSI in respect of land, which is not handed over but possession of the constructed amenity on this area was also offered.
According to the Petitioner, on 07/06/1993, the Petitioner applied for DRC by clearly setting out that it was under Regulation 34 read with Appendix VII and an LOI was issued in favour of the Petitioner on 02/12/1995, granting the request for grant of “Development Right Certificate” in lieu of the aforesaid land subject to compliance of various stipulations:
“1)That you will level the land by filing or cutting as may be necessary to the formation level as may be decided by the Chief Engineer (Roads & Storm Water Drains), which shall not be less than 27.55 Mtrs, above the Mean Sea Level. Further, the surface drainage arrangement shall be provided as may be certified by the Chief Engineers (Roads & Storm Water Drains). The reduced level of the land thus, after filling will be communicated with reference to T.H.D;
2)that you will construct compound wall with adequate number of gates as per the design and as per the specifications prescribed by the City Engineer of this Municipal Corporation.
3)…….
4)That since the land under reference is not accessible from Municipal/Public Road, right of way for 18.30 mtr width will be provided duly constructed by way at your cost as indicated on the accompanying plan alongwith street lights and till 18.30 mtr wide D.P. Road is handed over to MCGB;
5)That you will submit a registered undertaking that you will be liable to rectify the defects in the works to be executed under this permission within the period of one year from the date of handing over and will pay a deposit of Rs. 1.75/- lacs for faithful compliance of the requirements mentioned in this letter;”
Our attention is invited to the internal noting on the file of the MCGM, and it is very important for us to take note of the same with regards to the subject- ‘Utilization of TDR advanced for Recreation Ground reservation’ and the noting record thus:-
“ The Owner has desired to utilize the TDR generated from this Recreation ground reservation admeasuring 47288.08 sq.mt. in the same layout in accordance with this office circular u/no. CHE/91/DP/TD/GEN OF 7/10/1995.
As per the guide lines mentioned in the said circular the owner is eligible for I.O.D. to utilize 100% TDR to the extent of 80% of the net plot area, after the title is cleared by the Legal Dept. Necessary sanction of Ch.E.(D.P.) is already obtained by this office and scrutiny fees for TDR utilization is also paid on 17/05/05.
E.E. (B.P) W.S.R. Ward is requested to issue 100% I.O.D. is 47288.08 sq. mtrs. to the Owner subject to the total TDR to be utilized on the plot out of road and reservation shall be restricted to 80% of net plot area, The copy of the sanction of Ch.E. (D.P) is forwarded herewith for ready reference.”
The Petition is opposed by filing an affidavit, with a preliminary objection being raised that in the wake of the rejection of the proposal for grant of amenity TDR vide impugned order dated 12/04/2019, there is a remedy of appeal available under Section 47 of the MRTP Act and there is no sufficient justification as to why bypassing the said remedy, the writ petition shall be entertained.
On merits, it is contended that the Petitioner had voluntarily handed over the land in terms of LOI and the Petitioner had not submitted any application to the Planning Authority to develop the reservation under the policy of developing an amenity, so as to avail additional TDR on that count.
On merits, it is contended that the DRCs were issued for various reservations in lieu of handing over of the reserved areas to BMC, but all the applications were filed by the Petitioner, claiming only basic TDR for the surrendered land and there was no proposal filed for grant of additional TDR for developing the amenity. The contention of the Petitioner that there was levelling of land, construction of compound wall and storm water drainage is of no consequence according to the affidavit, as for taking benefit of the additional TDR, a specific proposal has to be submitted to the Planning Authority and the same can be considered only if the authority intended the amenity to be developed by the land owner. On other hand, it is contended that the activity that has been carried out by the Petitioner over the property was for the purposes of taking possession of the land under reservation and it is admitted that upon taking possession, the lands were transferred in the name of Corporation.
What is specifically pleaded in the affidavit is that, the entire transaction of handing over plots to the BMC was completed between 2009 to July 2013 and the process was completed in all respects in 2013 and now the claims staked after more than 9 years, by making an application for grant of additional TDR, deserve to be rejected, as there is no development of the reservations carried by the Petitioner. The decision in case of Godrej And Boyce is distinguished on facts, by stating that when the Petitioner made a representation on 30/01/2019 for grant of balance TDR in lieu of handing over possession of the reserved land and additional TDR in lieu of alleged development of amenity in the reserved area, the same is rejected by holding that the Petitioner is only entitled to TDR in lieu of the handing over possession of the reserved area.
Learned senior counsel Mr. Godbole representing the Corporation would urge that, the claim in the Petition is founded on clause (6) of Appendix VII of DCR, providing for additional FSI/TDR on account of development of amenity.
As per the learned senior counsel, the Petitioner submitted all applications for grant of DRC under Regulation 34 read with Appendix VII, claiming the basic TDR for the surrendered land and no application/proposal was filed for grant of additional TDR on account of developing the amenity. It is also submitted that the Petitioner utilized the FSI in situ in the same project except one where DRC was availed for TDR and the Petitioner levelled the land, constructed the compound wall and made provision for storm water drainage and also constructed a security cabin, which are the requirement as per clause (15) of Appendix VII of DCR.
Reliance is placed by Mr.Godbole on the Circular of 09/04/1996 in respect of the grant of TDR in lieu of construction of amenity under Regulation 34, clause (6), Appendix VII which provide that additional FSI in lieu of construction of amenity spaces on the PG and RG does not include the work of levelling, construction of compound wall, compound gate, landscaping and drainage arrangements and these activities are to be carried out as a part of the LOI for availing 100% FSI.
Apart from this, it is also urged by Mr.Godbole that the entire transaction of transferring of title to the BMC in this was completed on various dates between January 2009 to July 2013 in terms of Section 126(1)(b) of the MRTP Act and almost after more than nine and half years i.e. on 30/01/2019, the application is preferred for grant of additional TDR and it has been rightly rejected. It is also urged that the development of the amenity would include several things like providing drainage, public conveniences like toilets, development of gardens, pathways, installation of recreational equipments etc. and as far as the playground is concerned, it would necessarily include creation of pitches, grounds etc. or construction of the swimming pools or sports amenity, but since none of these activities are done by the Petitioner, it is not entitled for the benefit of additional TDR.
Mr. Godbole would categorically deny that the Petitioner has ever constructed or developed an amenity on the surrendered plot and whatever preparatory work was carried out, was as a condition of the LOI and this was undertaken as a prerequisite for surrender and issuance of base TDR and this stipulation was duly complied with prior to 2009, following which, the Corporation took possession of the Playground and Recreation Ground lands. But no further development was carried on these plots by the Petitioner as they were handed over essentially as vacant, levelled open spaces enclosed by a compound wall, but there was no amenity structure or any facility beyond the minimal levelling and in no case, this preliminary work transformed the land into developed public amenity, as required by clause (6). It is also submitted that once the Petitioner handed over the possession in 2009 and the land vested in the Corporation, any subsequent development of playground/recreation ground would be undertaken by the Corporation or its contractors and the Petitioner relinquished the control over the site and never sought to retain the control in order to develop “the amenity”. It is, therefore, strenuously urged by Mr. Godbole that the Petitioner cannot claim that it has ‘developed’ the amenity, so as to earn additional FSI.
The learned senior counsel also insisted upon the point, which is pressed into service by the learned senior counsel Mr. Chinoy, that for availing the additional TDR, it was open for the Petitioner, at the outset, before the land is vested, to obtain approval to execute the Amenity and in fact the Circular dated 07/10/1995 laid down procedural steps for grant of TDR, including phased release of FSI and the need to inform the Corporation about completion of amenity work to get the final credit. Thus, according to Mr.Godbole, it is open for the owner to elect the route of constructing the amenity and follow the stipulated process i.e. approval of the plans, estimates, supervision by Corporation etc., but unfortunately the Petitioner did not adopt this route and nowhere between 2009-2013 did it apply to the Corporation for developing the reserved Playground (PG) or Recreation ground (RG) as an amenity project, but only on completion of surrender and acquisition process, the Petitioner submitted an application belatedly in 2019, much after the land was vested and being recorded in the name of the Corporation.
Thus, the claim of the Petitioner is opposed on the ground that the Petitioner did not satisfy essential conditions for earning such development rights, as it neither sought nor carried out any development of the reserved amenity, and what was handed over by it was the land with minimal preparatory work, with no amenities at all.
It is pertinent to note that the application by the Petitioner undisputedly is under Regulation 34 read with Appendix VII, but it do not specifically invoke clause (6) thereof. In Appendix VII of the DCR 1991, which pertain to Transfer of Development Rights, where the development potential of a plot is allowed to be separated from the land itself and which may be made available to the owner of the land in form of TDR and these rights are available subject to the Regulations in Appendix VII. Appendix VII, is the regulation governing the grant of TDR to the owner and the conditions for grant of such rights and it clearly provide that the owner of a plot of land which is reserved for public purpose in the DP and for additional amenity deemed to be reservation, shall be eligible for award of TDR in the form of FSI to the extent and on the condition set out in the Regulation and such award entitled the owner of the land to FSI in form of DRC which he may use himself or transfer it to any other person. What should be the amount of FSI that is available is provided in clause (5) as it permit the owner to avail the FSI credit in form of DRC, which shall be equal to the gross area of the reserved plot to be surrendered and clearly this is the benefit which is made available to the owner for the land component which he has surrendered. However, there is a distinct provision in the regulation in form of clause (6), when an owner or lessee also develop or construct the amenity on the surrendered plot at his cost and subject to such stipulation as prescribed by the Commissioner or the appropriate authority and then hand over the developed/constructed amenity to the Commissioner free of cost and he may be granted a further DR in form of FSI equivalent to the area of construction/development done by him.
The Regulation further clarify that such a DRC shall be issued only on satisfactory compliance of the conditions prescribed in the Appendix VII. It is therefore, necessary that the two components contemplated under clause (5) and (6) which give rise to the entitlement of the land owner to receive TDR are different and distinct; the first being available at the time when the land itself is surrendered and the second becomes available when the amenity is constructed/developed to the satisfaction of the Corporation and it is handed over.
Keeping this regulation in tune, the BMC had issued a circular on 09/04/1996 covering the aspect of grant of additional development rights in lieu of construction of amenity as per sub-clause (6) of DC Regulation 34, Appendix VII and it made it crystal clear that the additional FSI in lieu of construction of amenity spaces on the PG and RG does not include the work of levelling, construction of compound wall, providing compound gate, landscaping, drainage arrangement etc., thus, indicating that for availing the additional TDR for the built up amenity, something more is expected.
As per the said circular, 100% FSI constructed as per the Municipal specifications is available for built up reservations set out therein. It is clarified that in the course of undertaking the construction, certain activities like construction of elevated tanks, lift rooms, pump room, watchman’s cabin etc., are not be considered as constructions available for grant of additional development right. As far as the open space amenities like garden, playground, RG are concerned, the following stipulation governs the grant of amenity TDR and it reads thus:-
“2. OPEN SPACE AMENITIES LIKE GARDEN, PLAY GROUND, R.G. PARKING, OPEN SPACES & BURIAL GROUND
i)The application for additional Development Right in respect of the above mentioned amenities will be within the reservations as per the provisions of D.C.R. No.23(g) to the extent of built-up area of such structures, subject to maximum of 15% area of the reservations.
ii) No additional Development Right will be granted for execution of the items such as levelling, construction of compound wall, retaining wall, providing compound gate, providing layer of red-earth, land-scapping & drainage arrangements etc.
(iii)Procedure & terms and conditions for considering grant of additional Development Rights for such structures will be the same as per Item No.1 above.”
It is in light of this circular, it is noted that the Petitioner voluntarily surrendered the BMC for surrender of the land and by undertaking the activity of levelling, construction of compound wall, providing compound gate, landscaping etc., had attempted to construe this as developing the amenity but it is to be noted that this activities were undertaken as per the LOI condition and possession of the lands along with the storm water drainage was taken by BMC and it is evidently clear from the letter of intent issued to the Petitioner that land filling or cutting, construction of compound wall as per design and specifications was to be carried out as a consideration of grant of DRC in lieu of the aforesaid land and we find that the Petitioner did nothing more than this.
In terms of the circular of the Corporation dated 09/04/1996 in respect of grant of TDR in lieu of construction of amenity under Regulation 34, clause (6), Appendix VII, the constructions of amenity spaces on PG and RG is not restricted to work of levelling, construction of compound wall/gate, landscaping etc and infact what the Petitioner did was only as a compliance of the letter of intent for availing the DRC in lieu of surrender of the land. The entire transaction of transferring the title of the land to the BMC is seen to be completed between January, 2009 to July 2013 in terms of Section 126 (1)(b) of the MRTP Act, 1966 but belatedly, the applicant chose to prefer an application and according to the Corporation, on 30/01/2019, the application came to be rejected.
Since, we have already noted that there is a clear demarcation between clause (5) of Appendix VII of Regulation 34 and clause (6) and reading of clause (15) of Appendix VII also throws light on its distinct nature as clause (15) provide that DRCs shall be issued only after the land is surrendered to the Corporation or to the State Government, and three things are required to be done on ensuring compliance of three stipulations namely (1) the land is surrendered free of cost and free of encumbrances, after the owner has levelled the land to the surrounding ground level, (2) he has constructed 1.5 mtr high compound wall with a gate at the cost of the owner and to the satisfaction of the Commissioner and (3) the cost of the transaction involved shall be borne by the owner or lessee. Therefore, it is evidently clear that for availing DRC in lieu of land, these compliances must be ensured by the owner, but for availing benefit of clause (6) of Appendix VII, there must be a clear proposal, exhibiting the intention to develop/construct the amenity, its acceptance by the Corporation, subject to conditions and stipulations for development of amenity and acceptance of conditions by the Developer and issuance of an LOI contemplating the aforesaid. Unless the Commissioner stipulate the nature of development of construction of amenity on the surrendered plot and the developer construct it to the satisfaction of the MCGM and hand it over, free of cost, the entitlement of the amenity DRC do not arise. An attempt on part of the owner of voluntarily showing readiness to develop an amenity without the Municipal Corporation according its approval will not confer the benefit on the owner as the proposal being made and it being accepted by the Municipal Commissioner and thereafter the actual development/construction of amenity taking place are the sine qua non for grant of additional TDR.
If the test is to be applied, and this is what has been laid down by the Hon’ble Apex Court in Godrej and Boyce (II), when the owner had not evinced any intention to develop the amenity but has merely handed over the land and, in lieu of its surrender had availed the first component of the deed namely FSI/TDR, we do not see how the entitlement of the second component i.e. developing/constructing amenity accrues to the benefit of the Petitioner.
Mr. Godbole, appearing for the Corporation is right in submitting that when it comes to a development of a recreational ground (RG), it would involve development of amenities like providing drainage, public conveniences like toilet, development of gardens, pathways, erection of recreational equipments for children like swings etc. In case of a playground, merely creating an open ground by levelling it, and compounding it would not be sufficient, but it would contemplate development of amenity like creation of cricket /football/ hockey pitches, ground for volleyball, basketball etc., construction of a swimming pool, or any sport activity but in its absence, merely because an open area has been levelled and handed over by erecting a compound wall, do not in our view amount to development/construction of amenity.
Clause (6) of Appendix VII has clearly contemplated ‘Development or the Construction of the Amenity’ on the surrendered plot, subject to stipulations prescribed by the Commissioner and then handing over of the developed amenity to the Corporation free of cost. Thus, an owner, who not only surrender the reserved land but also execute the actual amenity project like build a road, construct the amenity structure etc., and then transfer it to the authorities, so that it is ready for being used and that the Corporation is not required to undertake its development further, additional FSI credit equal to the built-up area of that amenity entails.
The phrase ‘develops or constructs the amenity’ in clause (6) requires something more than what is contemplated in clause (15) of Appendix VII. It is only when the owner undertakes the responsibility of developing or constructing the public amenity after the land has been surrendered, it makes him eligible for some additional advantage as the owner has also gone a step ahead in developing/constructing the amenity and did not stop at surrender of the land in lieu of which he has already availed the FSI/TDR. Development of the amenity may include various steps like bringing up a facility which is commensurate with the use of the land like if it is a open space reservation or a reservation for playground/garden that the owner shall develop the facility so that it can attend the purpose of it being a playground/garden. It is this additional work that is done, that act as an incentive to compensate the owner, who has invested in fulfilling the public amenity itself as a result of which the planning authority is not required to spend amount on the same, and this makes the owner entitled for amenity TDR. The mandatory surrender conditions of levelling the land to the surrounding ground, erecting a compound with gate for its protection and bearing of the cost of the aforesaid, is not an additional work that is done but these are the mandatory surrender conditions to secure and make the plot usable and anyone who surrenders the land in the wake of the reservation in the development plan is expected to perform this minimum stipulations so as to avail the basic FSI credit. On the other hand, clause (6) is an additional step, when the owner volunteers to provide the amenity. The owner himself has voluntarily undertaken to develop the amenity at his own cost but to the satisfaction of the Commissioner then he earns the benefit of additional FSI/TDR.
By failing to formally apply under the amenity development scheme and obtain prior approval, the Petitioner has failed to make out a case for attraction of clause (6) of Appendix VII. In fact, the first and only application for amenity TDR from the Petitioner was made in the year 2019, which according to the Corporation, was much after it had expanded the resources and plans for those reserved lands on its own and in this view, the Corporation has rightly refused the request. Whatever benefit is granted to the Petitioner as TDR/FSI is only in respect of the land and not developed amenity and though it is a stand of the Corporation that the Petitioner utilised the TDR (75% being utilised immediately) and 25% of it being subsequently granted, its entitlement to avail 100% FSI/TDR in lieu of surrender of land is already attained. We must make it clear that we are not rejecting the claim of the Petitioner on the ground of delay only but we have also considered the claim of its entitlement on merits to conclude that the Petitioners claim for additional FSI/TDR under clause (6) of Appendix VII DCR 1991 is not tenable as no steps over and above, the basic requirement of the LOI conditions have been achieved by the Petitioner as it has never carried out any development of the reserved amenity. What is handed over to the Corporation was the land with minimal preparatory work and therefore clause (6) is inapplicable to the case of the Petitioner. The BMC’s refusal to grant additional TDR is fully satisfied and though we do not oust the Petitioner on the ground of delay it is on examining the entitlement of its claim, we are turning it down.
Hence, the Petition is dismissed.
(III) WRIT PETITION NO.359 OF 2010
The Petitioner No.1 is the owner of several land parcels at village Marol. Out of the said land parcels, the land admeasuring about 7861.40 sq.mtrs. in CTS No.1498-A/1 is reserved for 18.5 mtr. and 27.45 mtr. wide DP Road in the Development Plan for Greater Mumbai.
According to the Petitioners, on 01/01/2005, in compliance of the commencement certificate dated 05/03/2005, the Petitioners undertook the construction of the amenities which were on the verge of the completion. Thus, the Petitioners claim that the total area of TDR that the Petitioners are entitled to is equivalent to the area of land under reservation, which has been surrendered by them.
It is the claim of the Petitioners that since they were entitled to construct on the reserved land, the amenity for which it was reserved, being a road, as per the specifications of the Respondents, with the installation of drainage and street lights, it was entitled to obtain in lieu thereof, additional TDR equivalent to the area of the amenity constructed in accordance with the provisions of the DC Regulations in force.
After the total area of reservation of DP Road, the Petitioners were required to hand over to the MMRDA a road consisting of 5721.1 sq.mtrs. and this was so done and the name of MMRDA was mutated in the record of rights and the property card.
By letter dated 09/01/2009, by the Respondent No.2-MCGM, the Petitioners were intimated about the broad specifications of construction of DP Road with the list of consultants and amongst them, the Petitioners appointed M/s Vhatkar & Associates and its services were engaged for construction of road and the design and other particulars, as set out in the IOD, were taken into account before the Petitioners awarding the contract to M/s Prism Infra Concrete (India).
The Planning Authority-MCGM approved the designs for the DP road and on 19/11/2009, a letter was issued in form of a completion certificate for construction of storm water drain as part of the amenity constructed by the Petitioners.
The Petitioners having completed the base of the road and having made provision for completion of DP Road and for handing over its possession and enabling the Respondents to mutate their name in the record of rights, claimed their entitlement in development right as per DCR 1991.
The Petitioners requested for allowing them to utilize 100% additional development rights as per DCR 1991, they were informed that the Respondents would give only 25% of the additional development rights in lieu of the duly constructed amenities, but it is the claim of the Petitioners that having substantially completed the construction of the amenity, being a road, they are entitled for 100% TDR.
The Petition, therefore, seek a relief of withdrawal of the impugned Circular dated 05/04/2003, issued by MCGM revising the policy guidelines for grant of additional TDR as per clause (6) of Appendix VII for construction of DP Road and set back, which had restricted the TDR to 25% instead of grant of 100% TDR for constructed amenity as provided in the Regulation.
Learned senior counsel Mr. Godbole, while contesting the Petition which pertain to the road amenity, would submit that the land of the Petitioners is affected by the DP roads as per the sanctioned revised Development Plan, which formed part of layout sanctioned in the year 2001 itself. The Petitioners architect submitted an application in prescribed format on 23/11/2007 for grant of TDR under Regulation 34 of DCR 1991, in lieu of handing over of the land affected by the DP Roads. MCGM thereupon intimated broad specifications for construction of the road in the year 2009, approving the design for 18.30 and 27.45 meter wide DP Roads.
According to the Petitioners, the construction of the road was completed in all respects on 13/04/2010 and it was inspected by the MCGM, which issued completion certificate on 06/10/2010 and possession receipt for the constructed road with amenities was issued on 30/07/2011, but both being issued subsequent to 17/06/2010.
With reference to the amendment in the modification in Regulation 33(1) DCR, Mr.Godbole has contended that the amendment squarely applies to an owner, who constructs a development plan road on surrendered land and hand over the same to the Commissioner on or after 17/06/2010, subject to exception carved out, where road FSI has been utilized and full occupation certificate has been granted before that date. According to Mr.Godbole, the case of Petitioners is governed by the amended Regulation and not by Godrej And Boyce (I), which was decided on 06/02/2009, which held that the words “equivalent to the area of the construction/development” appearing in clause (6) of Appendix VII of DCR 1991 entitle an owner, who constructs a road amenity on surrendered land, to additional FSI/TDR equivalent to 100% of the area and it struck down the Municipal Corporation’s executive circulars restricting it to 15% and 25% respectively. However, according to the learned senior counsel, the right of additional FSI/TDR for construction of a road amenity accrues and the quantum thereof must be determined by reference to the date on which the constructed amenity is actually surrendered to the authority and not by reference to the physical completion of construction work.
According to him, on the Petitioners showing, the completion certificate for the road was issued on 06/10/2010 and the possession receipt for the constructed road was issued on 30/07/2011 and even according to the Petitioners’ own application in the prescribed format claiming additional TDR for the constructed road amenity was filed on 13/03/2012. It is, therefore, urged that each of the aforesaid event has taken place after 17/06/2010 and on that ground the claim for balance 75% of TDR is strongly contested by the Corporation. By submitting that the Petitioners right to avail additional FSI/TDR for construction of road amenity in question crystallized, and warrant to be determined by reference to the law in force on the date when the constructed road was surrendered or handed over to the MCGM and this was all done after 17/06/2010.
The present Writ Petition involved the amenity in form of TDR and the Petitioners Indrajit Properties Pvt Ltd, is a company and claim to be the owners of several parcel of lands with different measurements at village Marol, out of which land admeasuring 7861.40 sq mtrs in City Survey No. 1498 A/1 is reserved for 18.5 meter and 27.45 meter wide DP Road, in the Development Plan for Greater Bombay.
It is the case of the Petitioners that, MCGM granted 25% TDR for construction of road and the Petitioners seek balance 75% towards Constructed Road amenity.
The aforesaid relief is sought in the background that it is on 20/07/2001, the MCGM approved the proposed amalgamation cum layout/subdivision of the land of Village Marol, Andheri (East) of larger land by stipulating certain terms and conditions and it was made clear that the plot/plots reserved in the Development Plan for Recreation admeasuring 3958.17 sq mtrs., shall be kept open and handed over to MCGM in lieu of TDR whenever required. It was also directed that the access road/roads in the layout shall be constructed and lighted as per the specifications of the Municipal Corporation and it was agreed to be maintained by the Petitioners. It was also agreed that the land within the regular line of roads in the holding shall be kept open un-built upon and shall be handed over to the Municipal Corporation duly constructed and its ownership will be duly transferred in the name of Municipal Corporation of Greater Bombay and the floor space index of the setback land shall be utilised as per the prevailing DC Rules.
On 01/01/2005, IOD was granted for a proposed building at 1498 A/2 under which the Petitioners were under obligation to comply with the all the terms and conditions including construction of the DP Road and this IOD at Exhibit A of the Petition set out the conditions to be followed being worded in the negative and this included the following condition:-
“4)That the specifications for layout / D.P. / or access roads / development of setback land will not be obtained from E.E.R.C. (W.S.) K/East, before starting the construction work and the access and setback land will not be developed accordingly including providing street lights and S.W.D. from E.E.R.C. (W.S.)/ E.E.S.W.D. of W.S. K/East, before submitting B.C.C.”
In addition, there were several other conditions to be complied by the user before grant of the Commencement Certificate. It is on 14/09/2006, the MMRDA took possession of the land admeasuring 5721.1 sq mtr out of original plot with area of 7861.40 sq mtr and also issue possession notice and this was so done because MMRDA was the planning authority for airport infrastructure. However, possession of the land reserved for D.P. Road was handed over to the Corporation.
It is on 09/01/2009, the MCGM intimated the Petitioners the broad specification of construction of DP Road and this included the following stipulation:-
“ 1. The road treatment shall be designed through road consultants approved by M.C.G.M. (List of same is given below) and the same shall be submitted to the concerned E.E. (Roads) and after getting clearance, the road construction work shall be taken up.
2.During the progress, the work shall be supervised by the consultant and architect duly certified by different stages such as verification of C.B.R., level of the sub grade, confirmation of slope and camber, laying of W.B.M. D.B.M and A.C. layer & the details shall be submitted to this office and shall confirm to Municipal Road specifications in this behalf.
3.The material used shall be of approved quality and requisite tests shall be carried out in laboratories of Engineering Degree Collages preferably I.I.T & V.J.T.I.
4.a) Roads having width of 13.44 mtrs. These roads shall be constructed in asphaltic material having proper slope, camber and drainage arrangement.
b)These roads shall be provided with guard stones for segregating the Pedestrian and the vehicular traffic, The road side storm water drain shall be covered with M-20 grade RCC slab and the same shall be used as footpath for pedestrians. Footpath shall be finished with coloured paver blocks as directed. Footpath shall be having depressions at carriage entrances for making footpath user friendly for physically handicapped individuals. The central divider shall be provided wherever required as per the remarks as Dy. Ch. E. (Traffic).
6.That the road shall be constructed as per actual demarcation given by E.E.D.P./E.E.T.C./A.E.survey under the supervision of licensed Architect.
11.That the provision of duct for street light cable and other utilities, if made so as to prevent excavation in asphalt is advisable.
12.The date of commencement of work should be intimated to this office.”
The list of consultants was also provided along with the said communication.
Out of the approved consultants, the Petitioners appointed Vatkar & Associates for construction of 18.30 mtr and 27.45 mtr DP Road passing through its property.
The consultants after inspecting the site, through their letter, forwarded design and other particulars to the Petitioners.
It is on 05/03/2009, the Petitioners issued work order for construction of DP Road to M/s Prism Infra Concrete (India).
Immediately after this and to be precise on 24/04/2009, MMRDA made an application to the City Survey Officer (Vile Parle) to delete their name and enter the name of Respondent No.2 for an area of 5721.10 sq. mtrs out of CTS No.1498 A/1.
The MCGM approved the design of road and directed construction of the road in asphalt macadam only as per the design submitted by the road consultant. The said communication also categorically stated that for construction of the cement concrete road, the remarks from municipal and underground utility department shall be obtained and it is only after receipt of the remarks, the department would suggest the wearing course of road considering the future development and its connectivity to the airport.
It is on 29/09/2009 Letter of Intent was issued. It is on 29/09/2009, MCGM with regard to the application of the Petitioners Architect dated 23/11/2007 for grant of DRC in lieu of the land affected by the DP road, communicated that the request to grant ‘Development Right Certificate’ would be considered after complying with several formalities including submission of necessary legal documents for transferring the land as well as levelling the land by filling or cutting as may be necessary to formation of the level and also making provision for storm water drains and on obtaining a certificate from E.E. (Roads) W.S., stating that the road is brought up to the formation level.
It was also stated that the said letter of intent shall be valid for period of one year, but it may be re-validated for further period of one year at a time.
On completion of the construction of the road, on 12/10/2009, the Petitioner once again reiterated its request for grant of DRC and it also pressed its demand for 100% additional FSI for constructed amenity by placing reliance upon the decision of the Apex Court in case of Godrej and Boyce.
This demand was made in the backdrop with the following specific facts being placed on record.
“The land under reference admeasures 24,297.60 sq. mt. out of the said land, land admeasuring 7861 sq. mt. is affected by the proposed 27.45 mt, and 18.30 mt. Wide DP. Road and their junction. The plot is also affected by the Recreation Ground in 3 parts and the total area of 3 R.G. reservations admeasures 3803.40 sq. mt. The sub-division and the layout of the aforesaid land has also been approved by the Corporation. Two Plots, i.e. CTS No. 1498-A/2 and 1498-A/3 are only available for the developer. On the plot bearing CTS No.1498-A/2, a Commercial building has been proposed and the same has been approved by the Corporation vide IOD No. CE/8087/WS/AK dated 01.01.2005 and the C.C. for the whole building has also been issued. The plot bearing CTS No. 1498-A/3 which has been designated for the Hotel development has also been approved for the purpose of Residential Hotel and IOD has been issued u/No. 6E/7358/WS/AK dated 22.11.2002. CC for starting the construction of has been issued by the Executive Engineer, Bldg. Proposals, Western Suburbs in K/East Ward.
Out of total land admeasuring 7861 sq. mt. affected by the D.P. Road, only land admeasuring 961 sq. mt. is used on the development of a Commercial building on land bearing CTS No .1498-A/2. For the remaining land admeasuring 6960 sq. mt. we have claimed TDR for which Letter of Intent has been issued by the Chief Engineer, Development Plan on 29.09.2009.
In this context, you reference is invited to the judgment issued by the Hon’ble Supreme Court of India on 06.02.2009 in case of Godrej & Boyce Co. Ltd., v/s. Municipal Corporation of Greater Bombay. In the said judgment, Hon’ble Supreme Court has upheld the petitioners submission and laid down that as and when the D.P. Road is constructed by the owner / developer and TDR is availed for the said D.P. Road, then 100 % FSI in lieu of the construct road (amenity) as given in Clause 6 of Appn. 7 shall be granted as against the policy of Corporation for granting only 15% 25% TDR for constructed road. It is given to understand that Corporation has already acted accordingly and granted 100% TDR for constructed road amenity to the petitioner. Copy of the judgment is enclosed herewith.
Based upon the above judgment, it is incumbent upon the Corporation to grant 100% TDR for constructed amenity (i.e. constructed road) whether TDR is claimed under D.C. Regulation No. 34 subject to complying with condition mentioned in clause 6 of Appn. 7 of D.C. Regulation 1991.
In our case, since we have claimed TDR of the road land admeasuring 6960 sq.mt. Under D.C. Regulation No. 34, we shall also be granted 100% additional FSI for constructed amenity subject to complying with the requirements as may be laid down by the Corporation in this behalf.
As regards D.P. Road land admeasuring 961 sq.mt., advantage of which has been availed under DCR No.33(1’) and being loaded on the Commercial building we may be granted 100% additional FSI for construction of the road as per the directive issued by the Government in this regard.
We have therefore to request you to kindly advise the Chief Engineer, Development Plan to consider our request favourably and grant us 100% additional FSI for constructed road for land admeasuring 6960 sq. mt. And 100% additional FSI for land admeasuring 961 sq. mt. Of the road land.”
The application did not receive any consideration and this resulted in a Petition being filed in December, 2009.
The Petitioner contended that the road was completed prior to 17/06/2010 but the Completion Certificate for the road was granted only on 6/10/2010 but heavy reliance is placed upon communications from Consultancy Services Vatkar & Associates dated 13/04/2010, which reflected that a joint inspection was completed of the road, which was found to be complete as per all specifications, and request was made that a joint inspection be carried out by MCGM. Another communication on the similar lines issuing the final road completion certificate by the consultancy services was issued on 27/04/2010 where it was stated that the inspection was done with the MCGM Officer, who did not raise any objection during inspection of a completed road, and it was therefore, intimated that since the road was complete and even the inspection is carried out, the bill of the consultant be settled.
There is also a communication from the MCGM from the Chief Engineer (Development Plan) addressed to the Executive Director, (Western Region), Airport Authority of India, dated 14/05/2010, when a request was made by MCGM expressing its grievance that the road had been fully constructed, but had not been opened for public traffic, as it was indicated that though the subject road is constructed, it is not made open to the public, and if it is done, it will facilitate approach to the Airport from Eastern Suburbs after construction of bridge on river and it will ease traffic congestion. The Completion Certificate for the constructed road was ultimately granted on 6/10/2010 though the Part Completion Certificate for storm water drainage arrangement was granted on 19/11/2009. It is worth to note that the intimation the notification amending Regulation 33 (1) was published on 17/06/2010, but the case of the Petitioner is that the road was already constructed and even inspected, but a full Completion Certificate was issued by Respondent No.2 on 6/10/2010 and the formal possession of the constructed road was handed over to the Respondent No.2 after completion of formalities and in the property card the name of the Corporation was mutated in regards to the entire land admeasuring 7861.40 sq mtrs on 8/12/2011. It was on 17/02/2012, the DRC of area admeasuring 7861.40 sq. mtr was issued with the approval of the then Municipal Commissioner in respect of the land component and on 13/03/2012, the Petitioners applied for grant of 25% additional amenity TDR. On 5/12/2012, DCR for 1965.35 sq mtr towards additional 25% road amenity TDR to the Petitioner and the balance 75% claim is of 5896.05 sq mtr.
On perusal of the facts involved and placed before us with the counter claims set up by the Corporation, it is evidently clear, that the Petitioners were owners of various lands at Marol, which existed in form of distinct CTS Numbers and the total area of the land is 19426.30 sq mtrs but CTS Number 1498-A/1 was measuring 7861.40 sq. mtrs, which was reserved for two DP Roads. It is not in dispute that the Petitioner was the holder of land in CTS No. 1498 A/1 and out of the larger piece of land, area admeasuring 7861.40 i.e. area of CTS No. 1498A/1 was reserved for 18.5 mtr and 27.45 mtr wide DP Road.
Upon the IOD being issued in favour of the Petitioner, on 01/01/2005, the Petitioners were under obligation to comply with all the terms and conditions and this included the stipulation of construction of the road and the setback including providing street light and storm water drain, which shall be in accordance with the specification prescribed by the Executive Engineer (WS) K/East.
Out of the total area of reservation of DP Road, the Petitioners were required to hand over to the MMRDA a road consisting of area of 5721.1 sq. mtr and this was accordingly complied with and the name of MMRDA was mutated in the record of rights. In terms of the arrangement between MMRDA and the Corporation, a date was fixed for handing over the DP Road to the Corporation. Pursuant thereto, the Corporation intimated to the Petitioners about the broad specifications of the construction of DP Road along with the list of consultants expecting the Petitioners to choose one against them. The Petitioners, therefore, appointed M/s Vatkar & Associates for construction of the DP Road passing through its property and the consultant clearly followed the stipulations of the Corporation and the stipulations as provided in the IOD. This was followed by a contract being awarded for construction of DP Road to a contractor. The Corporation approved the designs of the road and the Petitioners completed the construction of the road and also incurred huge expenses on construction amenity. In the whole sequence of events and the correspondence exchanged between the parties, it would be noted that the consultants, which were chosen by the Petitioners from the choice that was offered after inspection of the site, forwarded the design and particulars to the Petitioners and only after this, the work for construction of DP Road was awarded to contractor. It is worth to note that the design of the road was approved by the Corporation and it also issued direction of constructing the road with Asphalt Macadam only. The road was completed prior to 17/06/2010 though the Completion Certificate was granted only on 6/10/2010 for which the Petitioners cannot be blamed. A joint inspection with the participation of the consultant and the Corporation reveal that the officer of the Corporation expressed no objection about the fact that the road was completely constructed and infact, the Corporation itself indicated to the Airport Authority to take necessary steps, so that the road can be made open for being used by public. It is worth to note that when the Occupation Certificate was issued by Respondent No.2 along with the plan for the Commercial Building on CTS No. 1498-A2 it reflect that the land component FSI of 961 sq. mtr. was used in the commercial building. The Completion Certificate is issued to the Petitioner after the amendment came and even the formal possession was handed over later on, but the road was already completed and the DRC of area admeasuring 7861.40 sq. mtr (less 961 sq.mtr) was already issued to the Petitioner in respect of the land component. The Petitioner applied for grant of 25% additional amenity as the BMC was offering only 25% as per the prevailing circular and DCR for the additional 25% road amenity was issued to the Petitioners and the Petitioners seek the balance 75%.
In our view, the case of the Petitioners is governed by Godrej and Boyce (I) as the construction of the amenity i.e. road was completed prior to 27/04/2010 and this allowed the Petitioner to claim amenity TDR and the land having been surrendered and the amenity being constructed prior to 2010, the Petitioner has a right to receive the TDR that had accrued. Merely, because the amendment to the Regulation came in 17/06/2010, which put a cap on the availability of the amenity TDR to 25% will not deprive the Petitioner as both the conditions as contemplated therein are satisfied namely, the 100% FSI for handing over of the land is already availed and utilised in construction of the building and the second stipulation of the possession of the amenity i.e. road and the road was completed and it was ready for taking possession, but the same was delayed purposely. The communication from the consultant, which is prior to 17/06/2010 itself, reflect that the amenity was fully constructed, but for the reasons best known to the Corporation, the possession thereof was not taken. It is seen that the Completion Certificate was issued on 6/10/2010, but we find that the road was complete in all respects and it was certified by MCGM enlisted consultants that it is complete in accordance with the specifications and even the MCGM official, who visited the site express consensus as he raise no objection as the consultant certified that the road was completed in all respects.
It is for this reason, in our view, the Petitioners cannot be deprived of 100% additional FSI, as the amenity in form of road was constructed as per the specifications prescribed by the Corporation and despite the construction being complete in all respects, and it having been so certified to be completed by the consultant and the Corporation, just because the Completion Certificate was issued, a little later after the DCR was amended on 17/06/2010, and taking of possession of the road was deliberately delayed, the Petitioners cannot be deprived of the benefit.
The Petition is therefore made absolute by declaring that the circular issued by the MCGM on 05/04/2003 cannot deny the Petitioner its entitlement for the construction of amenity to less than the equivalent of its area.
We, therefore, issue a mandamus to MCGM to forthwith grant Development Right Certificate to the Petitioner in terms of the application dated 12/10/2009, as we declare that the Petitioner is entitled for grant of 100% additional FSI for constructed road of land admeasuring 6960 sq. mtr and 100% additional FSI for land admeasuring 961 sq. mtr of the road land as the property of the Petitioner had two reservations in form of the DP Road.
(IV) WRIT PETITION NO.1185 OF 2017
In the Writ Petition No. 1185 of 2017, filed by East & West Builders, the owner of the land along with its proprietor seek quashing of the impugned order dated 5/08/2009, passed by the MCGM as well as the order dated 29/10/2015 passed by the Ministry of State, Urban Development Department. The Petitioner seek a direction to the Respondents to grant TDR equivalent to the area of constructed amenity of D.P. Roads/ Setback aggregating to 11186.90 sq. mtrs., and to process the application of the Petitioners for granting 100% TDR for handing over the constructed D.P. Roads.
The Petition is opposed by Mr. Aspi Chinoy, Senior Advocate, and the thrust of his contention is upon the observations of the Apex Court in the case of Godrej and Boyce (II) to the effect that all activities undertaken by the Petitioners till the handing over of possession of the land were merely restricted to the handing over of the DP Road as a part of the layout and as a condition of layout and the intention was never to avail the amenity TDR. The submission of Mr. Nankani, being contested by Mr. Chinoy, have to be appreciated in the facts of the case.
The Petitioner No.1, a proprietary concern, alongwith the sole proprietor Mrs. Saranga Anil Agarwal, has approached this Court for quashing of the impugned order dated 05/08/2009 passed by the MCGM as well as the order dated 29/10/2015 issued by the Minister of State, Urban Development Department, seeking a writ of mandamus to the Respondents to grant TDR equivalent to the area of constructed amenity of DP Roads/Setback aggregating to 11186.90 sq.mtrs. The Petitioner No.1, being the owner of the land bearing various city survey numbers of village Kandivali (W) in R/South Ward, submits that the Petitioners submitted a proposal for the sanction of layout/sub-division/amalgamation for the purpose of developing the property, which was affected by 5 DP Roads and also road set back area. Upon the application being preferred by the Petitioner for sanction of layout/sub-division, on 18/09/2000, the MCGM sanctioned it and Condition Nos.3 and 4 of the sanction provided that the Petitioners shall construct the amenity/reservation on the said property and hand it over to the MCGM.
It is on 18/09/2000, the MCGM sanctioned the Petitioners layout and Condition Nos.3 and 4, which required the Petitioners to construct the Development Plan road, and hand over to the MCGM in order to receive 100% FSI thereagainst subject to a maximum 40% of the plot area. The communication clearly stated that the final approval to the subdivision/layout will be given after construction of the roads including lightning, drainage, sewerage etc. The conditions specifically read thus:-
“3.That the land within the regular line of roads in our holding shall be kept open and un built upon and shall be handed over to the Municipal Corporation of Greater Mumbai duly constructed as the floor index of the setback land is proposed to be utilised as per prevailing rules., which will be distributed proportionally on all sub-divided plots.
4.That the land within the proposed Development roads falling in our holding shall be kept open free of any encumbrances and shall be constructed to its full width as per Municipal Specifications, including providing street light, drains, etc., and shall be handed over to the Municipal Corporation of Greater Mumbai after construction and its ownership shall be duly transferred in the name of M.C.G.M within the Development Plan road, 100 % floor space, index shall be availed of subject to a maximum of 40% of the plot area as permissible under D.C.R The floor space Index permissible for this Road shall be distributed on prorata basis over the various plots as indicated on the plan.
5.That adequate storm water drains shall be provided in the layout area at our cost including provision for admitting storm water from the surrounding locality.
6.That adequate arrangement shall be made for providing sewerage line in the layout area at our cost to the satisfaction of the Municipal Commissioner and shall got the same connected to the Municipal Sewer.
7.That the cost of channeling and draining the natural water course in the locality shall be done proportionately by us as determined by the Municipal Commissioner.”
After the sanction of the layout, the Petitioner corresponded with the Executive Engineer, who approved the laying down of sewer lines as well as the 18.30 mtr D.P. road for development on the plots with various CTS Numbers. Upon work being completed, Deputy Chief Engineer (SWD) issued receipt against the payment made by the Petitioner towards prorata charges for property.
The Executive Engineer Water Works also certified that 300 mm cast iron water mains are laid down in DP Roads in the layout passing through the CTS number. Not only this, on 12/07/2002, the Corporation issued receipt for payment of Rs.4,58,983/- towards prorata charges for constructing street light and on 7/2/2003, upon the Petitioner making payment towards prorata charges for Setback land, the Corporation acknowledged the receipt of amount of Rs. 11,01,425/-.
The MCGM on 17/02/2003 issued a Handing Over Report certifying that the Petitioners have completed the construction of DP Road and the storm Water Drain and paid the charges for constructing street light.
The correspondence placed on record by the Petitioner thus reveal that between 2003 to 2015, pursuant to the condition in the layout approval dated 18/09/2000, the Petitioners constructed and developed DP Roads and handed over the same to the Corporation, in order to claim and receive 100 % FSI and actually it received and utilized the FSI.
There is no dispute about the fact that the Petitioners constructed the DP Road along with the storm water drain, laid down cast iron water mains and also laid down the sewer lines, which were subsequently maintained by the Corporation.
The affidavit-in-reply filed on behalf of the MCGM has adopted a stand that the suit property is a part of layout approved by the Corporation on 18/09/2000 and the layout is not granted completion certificate as on date, but the scheme included construction of DP Roads. As per the affidavit, the conditions in the Schedule, which the Petitioners agreed to abide by, included specific conditions as below :-
“Condition no.(4) - That the land within the proposed development roads falling in our holding shall be kept open free of any encumbrances and shall be constructed to its full width as per Municipal Specifications, including providing street light, drains etc., and shall be handed over to the Municipal Corporation of Greater Mumbai after construction and its ownership shall be duly transferred in the name of M.C.G.M within the Development Plan road. 100% floor space index shall be availed of subject to a maximum of 40% of the plot area as permissible under D.C.R. The floor space index permissible for this Road shall be distributed on prorata basis over the various plots as indicated on the plan.
Condition no.(5) - That adequate storm water drains shall be provided in the layout area at our cost including provision for admitting storm water from the surrounding locality.
Condition no. (6) - That adequate arrangement shall be made for Providing sewerage line in the layout area at our cost to the satisfaction of the Municipal Commissioner and shall got the same connected to the Municipal Sewer.
Condition no.(7)- That the cost of channelling and draining the natural water course in the locality shall be done proportionately by us as determined by the Municipal Commissioner.”
The affidavit proceed to state that the Petitioners submitted an application on 10/03/2009 through their licensed surveyor stating that they have already handed over DP Road alongwith the construction and FSI of the same has already been utilized as the DP portion of the land is constructed by them and they have claimed the additional 100% DP Road benefit which is rejected. The relief in the Petition is opposed by specifically pleading thus :-
“13.For availing FSI/TDR against the area of land surrendered free of cost and further additional FSI or TDR against the development or construction of amenity is in terms of and is provided under Final Development Control Regulation. The Development Control Regulation was initially in force from the year 1991 w.e.f. 25.03.1991 called DCR, 1991 which was in force till 12.11.2018, and thereafter DCPR, 2034 is in force. It is important to mention here that in terms of DCR, 1991, the availing of FSI/TDR could be done by landowner or lessee by exercising an option under Regulation 33(1) of DCR, 1991 or under Regulation 34 of DCR, 1991 as was then existing (which has now become Regulation 32 under DCPR, 2034). There is a material difference on availing of FSI or TDR under Regulation 33(1) and Regulation 34 of DCR, 1991.
14.The introduction of the novel mode for land acquisition based on the concept of Transferable Development Rights against the area of surrendered land free of cost and free from all encumbrances and a further Additional Floor Space Index or transferable development rights against the development or construction of amenity on the surrendered land by the land owner or the lessee at his own cost assumes a great amount of significance.”
The affidavit also state that the Petitioners have not submitted the completion certificate for laying water mains and sewer line and the entire layout is not yet completed, as the occupation certificates to all the buildings in the entire layout is not granted and as per the layout terms and conditions, street lights are not provided to all the DP Roads mentioned in the layout and the failure of the Petitioners to complete the DP Road in all respects complying layout terms and conditions disentitle them from claiming any relief.
The question for consideration is whether the work undertaken by the Petitioners was towards the condition imposed while sanctioning the layout or whether it was on account of its intention to construct an amenity as to claim amenity TDR or that was only to enable the Petitioners to avail 100% FSI as per the layout condition to accept the surrender of the land by the Corporation. Pertinently, we have noted the pleading in the Petition and particularly, in paragraph 3.9 when the Petitioner pleaded thus:-
“3.9In the year 2003 to 2015, pursuant to the condition in the layout approval dated 18.09.2000 by MCGM, the Petitioners constructed and developed the amenity / reservation of D.P. Road and handed over the constructed amenity / reservation to MCGM.”
The condition no.4 of the sanction layout, which we have already reproduced above, made it imperative for the Petitioners to construct the development road falling in their holding, as per the full width as per Municipal Specifications and include provision for street light, drains etc., and thereafter, hand over the same to the Municipal Corporation, when its ownership would be transferred in the name of MCGM. This would entitle the owner of the land to avail 100% FSI, subject to a maximum of 40% of the plot area as permissible under DCR and it was permissible for it to be distributed on prorata basis over various plots as indicated in the plan.
It is to be noted that, after accepting the condition of layout and on construction of the DP Road and the storm water drain along with the laying of sewerage line and cast iron water mains, the Handing Over Report indicate that, it is in the year 2004 itself, the same was handed over to the Corporation and it included the set back land at CTS No. 672A/2 and 662B. Possession receipts were issued in favour of the Petitioner certifying completion of the construction of storm water drain with DP Road and provision of street light as the charges were paid by the Petitioner.
These all being completed in the year 2004, the Petitioners maintained a stoic silence and availed the 100% FSI. However, they never claimed amenity TDR and no form claiming TDR under Appendix VII was ever filed by the Petitioners to claim TDR under clause (5) or amenity/additional TDR under clause (6). The Petitioners did not claim or receive additional/amenity TDR of 15-25% which was then available under clause (6) of Appendix VII nor did they make any claim for balance 75% amenity TDR.
However, after the Supreme Court delivered its judgment in Godrej and Boyce (I) on 06/02/2009, holding that the owner of the land handing over amenity/reservation to MCGM is entitled to TDR equal to it and this accrued as an additional benefit for further TDR, for the first time on 10/03/2009, the Petitioners architect addressed a letter to MCGM to avail additional 100% DP Road benefit against construction and its handing over and specifically this demand was raised by relying upon the judgment of the Apex Court in Civil Appeal No. 1746 of 2007.
On 05/08/2009, the request was rejected by the MCGM on the ground that when the DP road was handed in lieu of FSI benefits as per the Terms and Conditions of the approved layout and as per the policy, the construction of TDR for roads handed over in lieu of FSI benefits was not admissible. As against this, an appeal was filed which came to be to be rejected.
Mr. Chinoy, the learned senior counsel representing the Corporation, by placing on record the list of dates and events would submit that the MCGM sanctioned the Petitioners layout on 18/09/2000 and the condition Nos.3 and 4 thereof, required the Petitioners to construct the DP Road and hand over it to the MCGM in order to receive 100% FSI thereagainst, subject to a maximum of 40% of plot area. Accordingly, the Petitioners constructed and developed DP Road and handed over the same to the MCGM in order to claim and receive 100% FSI and they actually received and utilized the 100% FSI. However, according to Mr.Chinoy, the work of construction of the roads was not done to construct an amenity or claim amenity TDR, but only for surrender of the land against 100% FSI as per the layout condition. He would submit that no form claiming TDR under Appendix VII was filed by the Petitioners to claim TDR under clause (5) or amenity/additional TDR under clause (6) and the Petitioners did not claim or receive additional/amenity TDR either 15% or 25%, which was then available under clause (6) of Appendix VII or make any claim for the balance 75% amenity TDR. Whatever was done, according to Mr.Chinoy, was in compliance of the condition of sanctioned layout for which the Petitioners got the benefit of 100% FSI, but then they kept stoic silence and never claimed amenity TDR.
According to Mr.Chinoy, he is not attempting to contest the claim of the Petitioners on the ground of delay, but by inviting our attention to the observations in Godrej And Boyce (II), it is his specific submission that in order to claim the amenity TDR, it is necessary for the party to evince its intention of development/construction of the amenity being carried out for claiming the additional amenity TDR under clause (6) of Appendix VII. Relying upon the observations in Godrej And Boyce (II), where it was noted that the activities undertaken by the appellants through their architects till handing over the possession of the land were not towards the development of the amenity and for the grant of additional TDR and rather all the works were undertaken as a part of the efforts to make the Corporation accept the surrender of land and to grant TDR and it was specifically observed that whatever was done by the appellants (Godrej) upto the date of handing over possession and getting the DRC, was not projected by them as development of amenity.
Mr. Chinoy, appearing for the Corporation has invited our attention to the decision of the Apex Court in Godrej and Boyce (II) arising from the decision of the Bombay High Court, when it rejected the Petition filed by Godrej and Boyce Manufacturing Company, in the backdrop that the Petitioners had surrendered the land covered by RG reservation to the Corporation and they have given TDR in the year 1996 equal to the area of the said land in accordance with clause (5) of Appendix VII of Regulation 34. Thereafter, at their considerable expense, the Petitioners developed and handed over the amenity/RG in accordance with the plans/layouts sanctioned by the Corporation and made a request for equivalent TDR/FSI, now under clause (6) of Appendix VII of the Regulation 34, but the Corporation refused to grant additional TDR by relying upon its policy circular to the effect that the additional TDR will be given for buildable amenities upto 15 to 25% for road developed/constructed and would not be admissible for recreational grounds developed.
The Division Bench carefully scrutinized the entire correspondence entered between the architect of the Petitioner and the Corporation adopted a specific stand that whatever work was done by the Petitioner, which included work of cutting, filling, etc., it was as a condition precedent for obtaining TDR in lieu of surrender of land under reservation as per clause (15) of Appendix VII, and not for availing of TDR. The Petitioner was also issued two separate DRCs in lieu of surrender of the lands and therefore, the Corporation adopted a stand that while handing over possession of RG and accepting DRCs, the issue of additional TDR was never raised by the Petitioners, and the same was handed over only for doing the required work as per clause (15) of Appendix VII i.e. for availing 100% FSI.
Referring to the entire correspondence, the Division Bench of the High Court specifically observed thus:-
“Secondly, the above correspondence does not establish that the petitioners intended to avail additional T.D.R. in terms of clause 6 of Appendix VII of Regulation 34. This is because in terms of clause 6 of Appendix VII of Regulation 34, the owner or the lessee who intends to develop or construct the amenity on the surrendered plot at his cost, has to approach either the Commissioner or the appropriate authority with the proposal, which, after due scrutiny and subject to such stipulations, as may be prescribed, the owner or the lessee has to carry out the construction or development to the satisfaction of the authorities of the Corporation. In the instant case, we have already noted that the petitioners had not submitted any proposal before availing of T.D.R. in terms of clause 6 of Appendix VII of Regulation 34……
If at all the petitioners were carrying on development on or before 7/06/1995, they would have certainly claimed additional T.D.R. in terms of clause 6 of Appendix VII. However, what was claim was T.D.R. as per clause 5 of Appendix VII of Regulation 34. It is also significant to note here that between 20/12/1995 and 20/11/1996, when M/s Mayfair Housing addressed a letter, no material is brought on record by the petitioners to substantiate that the development/construction of the amenity was carried out by them. Even the petitioners accepted the D.R.C.s dated 2/01/1996 without any protest.”
With the aforesaid observations, coupled with another observation in para 30 to the effect that the Petitioners did not fill in the printed form which was done earlier while claiming TDR as per clause (5) and that on the earlier occasion, when the Petitioner No.1 applied for grant of TDR on surrender of lands reserved for RG, after completion of the work, M/s Worthy Enterprises, the Architects of the Petitioner No.1 submitted the Completion Certificate and the work was found to be completed as per amended plans. The Completion Certificate submitted by M/s Worthy Enterprises while claiming TDR on surrendered lands under reservation in terms of clause (5) of Appendix VII is conclusive proof of the Petitioner No.1 complying with the stipulations prescribed by the Commissioner or appropriate Authority and completing the work to its satisfaction. In any case, recording that the Petitioner No.2 was not the owner or the lessee of the land, his request was accepted for development/maintenance on a condition that no TDR shall be claimed, it was concluded that the Petitioners had not established that they had developed/constructed the amenity in terms of clause (6) of Appendix VII.
However, the relief was refused also on the ground that the claim in terms of clause (6) of Appendix VII was raised after period of 12 years reflecting that the Petitioners have abandoned their claim for additional TDR.
This decision when subjected to challenge before the Hon’ble Apex Court, while answering the issue, as to whether the finding of fact arrived by the High Court that the Appellants did not and could not have developed the amenity calls for any interference, the decision find an extensive discussion on the statutory provision and the Apex Court found sufficient reasoning and upheld the finding of the High Court, when it is noted that it is only when the Appellant No.2 a builder, entered into the scene, the claim for additional TDR cropped up and this happened only in November, 1996, when it sought permission to develop and got power of attorney executed in its favour. It is pertinently noted by the Apex Court that what was applied for in form enclosed with the letter of the Architects was only a DRC for surrender of the land.
There was no indication in the letter that Appellant No.1 was interested in developing an amenity for the purpose of claiming additional TDR but the scenario changed after the Appellant No.2 came into picture. Thus, it was clearly concluded that the work done by the Appellant No.1 was only towards compliance of stage 1 TDR and construction of storm water drains was also for the purpose of grant of DRC even for surrender of land. In very specific terms, the Apex Court observed that the possession receipt notes that a compound wall with a gate has been provided and that DP Road with provisions of storm water drain has been constructed and the possession of the land is taken subject to the owner agreeing to rectify the defects.
Therefore, it was clear that whatever work was undertaken by the Appellant No.1 and their Architect was part of the conditions fulfilled to make Corporation accept the surrender of the land and issue a DRC towards TDR and the steps were not towards the development of amenity and for want of additional TDR and all those steps contributed towards the efforts taken to make the Corporation to accept the surrender of land and to grant TDR. It is in the wake of these observations that the Appeals were dismissed on merits.
We find the decision of the Division Bench of this Court as well as the Apex Court in Godrej and Boyce (II) quite similar to the facts before us, as the facts reveal that the conditions of the layout approval dated 18/09/2009, itself require the Petitioners to construct the DP Road and hand over the same to the Corporation in order to claim a 100% FSI and actually the same was received and also utilized by the Petitioner.
Never ever did the Petitioners raise any claim for construction of amenity and claimed amenity TDR nor did it fill any form to claim TDR under clause (6) of Appendix VII. The layout which was sanctioned by the Corporation on 18/09/2000 with permission of subdivision, clearly imposed conditions on the Petitioners that it shall demarcate the boundaries of various plots/the reservation and the road alignments on site as per the approved plans and the work of construction of roads, filling of/levelling land, diverting nallas, laying sewer line etc., shall not be undertaken without due intimation to the Executive Engineer of Roads and without securing the permission of the Assistant Engineering Planning. As a condition of the layout, it was imperative for the Petitioners to keep the land, for the proposed development roads open, free of any encumbrances and it was directed to be constructed to its full width as per Municipal Specifications by providing street lights, drains etc., before it is handed over to the Corporation, pursuant to which it shall be transferred in the name of MCGM.
Condition Nos.(5) and (6) also made it imperative for the owner to provide storm water drains in the layout area at its cost including provision for admitting storm water from the surrounding locality. The conditions subject to which the layout was sanctioned also contemplated a provision for adequate storm water drain, sewerage line in the layout area to be provided with the cost of the owner to the satisfaction of the Municipal Commissioner along with the cost of channeling and draining to be shared proportionately as determined by the Municipal Commissioner.
Therefore, in our view, all the work that is carried out by the Petitioner was towards availing the 100% FSI/ TDR as per clause (5) of Appendix VII and not as per clause (6), to avail amenity TDR. It is also pertinent to note that Appendix VII of Regulation 34 through clause (5) entitled the owner or (lessee) of a plot to avail FSI credit in the form of DRC equal to the gross area of the reserved plot to be surrendered and clause (15) provided that the DRCs shall be granted only after the reserved land is surrendered to the Corporation, free of cost and free of encumbrances after it is levelled to the land of surrounding ground level and there is a construction of 1.5 mtr high compound wall with a gate at the cost of the owner to the satisfaction of the Commissioner. This being a condition of availing the FSI credit in form of DRC, on the Petitioner having undertaken the work of construction of DP Road along with the storm water drain etc was only towards availing the 100% FSI which was actually received and utilized by the Petitioner. It is only upon the decision in case of Godrej that for the first time on 10/03/2009 the Petitioner expressed its desire to avail the benefit of additional 100% D.P. Road over and above the benefit already granted, but when the layout was sanctioned by MCGM subject to the conditions therein, the Petitioner never contemplated development of the amenity for availing amenity TDR, and therefore, for the similar reasons on which Godrej was refused the benefit of additional amenity TDR we must turn down the request of the Petitioner. The Petition, therefore, raising a claim for grant of amenity TDR of 11186.90 sq. mtrs cannot be entertained and same is dismissed by upholding the impugned order passed by the MCGM as well as the Ministry of State, Urban Development Department.