Tribunals and CommissionsSingle Bench(2021) 03 TDSAT CK 0031

India Cast Media Distribution Pvt. Ltd. vs E-infrastructure And Entertainment (india) Pvt Ltd & Ors

Telecom Disputes Settlement And Appellate Tribunal · Decided on 12 March 2021

HON’BLE JUDGES
Shiva Kirti Singh, CP
RESULT
Allowed
CASE NUMBER
Broadcasting Petition 743 Of 2020 & Broadcasting Petition 743 Of 2020

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

8 paragraphs · 164 words

Heard learned counsel for the petitioner, learned counsel for respondent No. 1and learned counsel for respondent nos. 2 & 3.

Although in the last order, it was clearly indicated that petitioner's interim prayer shall be positively considered on the next date on the basis of

materials available on record on behalf of respondents, an accommodation is being sought by way of last opportunity to bring their materials on record

by way of reply/short reply. The prayer is that considering the broad facts and circumstances relating to the respondents, the further delay of two

weeks will not have any material effects on the properties and assets of the respondents.Â

In the larger interest of justice, one last opportunity is granted. Two weeks' time is granted for filing reply/short reply. Rejoinder, if required,Â

may be filed within one week thereafter. Post the matter under the same head on 8.4.2021.

The interim prayer shall be positively considered on the next date without granting further adjournment for reply.