High CourtsDivision Bench(2026) 09 BOM CK 8149

Hindustan Petroleum Corporation Ltd. vs Arcon Powerinfra India Pvt. Ltd. (Formerly, M/s. SKP Buildcon Pvt. Ltd.)

Bombay High Court · Decided on 8 September 2026

RESULT
Dismissed
CASE NUMBER
Arbitration Appeal No. 14 of 2025 in Arbitration Petition No.187 of 2023 with Interim Application (L) No. 11667 of 2024
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

16 paragraphs · 997 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

JUDGMENT (Per : A.S. Gadkari, J.):-

1)

By this Appeal under Section 37 of the Arbitration and Conciliation Act, 1996, (for short, “the Arbitration Act” ) the Appellant, a public sector company of Government of India, has impugned the Order dated 1st March, 2024, passed by the learned Single Judge in Arbitration Petition No.187 of 2023, filed under Section 34 of the Arbitration Act, dismissing the said Petition and upholding the Award dated 26th July, 2022, passed by the sole Arbitrator.

2)

Heard Mr. Hussein, learned counsel appearing for the Appellant, and Mr. Joshi, learned counsel for the Respondent. Perused entire record.

3)

The argument of the Appellant that the Respondent company did not disclose the fact that it was on the holiday list of, or banned by, National Hydro Power Company Ltd. (NHPC), a Government of India enterprise, while bidding for the said contract and that the Respondent did not carry out necessary work as per the contract, does not appeal us.

3.1) Paragraph Nos.62 and 63 of the Award reads as under:-

“62.

I will now proceed to address Claim No.1 of the Claimant. This is for work that is stated to have been done on the site prior to the termination. The Claimant had submitted its first RA Bill for an amount of Rs.25,73,262/-. This RA Bill was sent to the Respondent on 27th June, 2017. The Claimant contends that there was never any dispute raised regarding this bill or any mistake or discrepancy pointed out. In defence, the Respondent drew my attention to Clause 7 of the General Terms and Condition of the subject contract and the fact that the RA Bill in question did not contain measurements jointly taken by the parties, nor was it certified by the Engineer-in-Charge/ Site-in-Charge. I do not agree with the Respondent that Clause 7 aids it. On the contrary, Clause 7.1 requires certification to take place by the Respondent and payment to be made within 15 days from the date of receipt of the bill. Furthermore, Clause 7.a.2 states as follows:

“For the purpose of taking joint measurement, the Contractor/representative shall be bound to be present whenever required by the Engineer-in-Charge / Site-in-Charge.”

63.

It is the Claimant’s case that RA Bill was sent with the measurements and that it would have been present in the event that the Respondent had asked it to under Clause 7.a.2. Even in cross-examination, CW-1 says that the Claimant had done its measurements and submitted them to the Respondent for checking and counter-signing. The Respondent failed to do so because of its “negative attitude”, a phrase that CW-1, with some variation, has repeatedly used for the Respondent and its officers. To my mind, the contractual clause is clear – it did require joint measurements to be taken and obliged the Claimant’s officers to remain present when called upon to do so by the Respondent. Admittedly, the Respondent did not call upon the Claimant to do so. There is thus no question of the Claimant failing to remain present.”

4)

The learned Single Judge has dealt with the contention of blacklisting and affirmed the finding of the Arbitrator. In our view, the contention is entirely baseless. The Supreme Court in Shri Kishan vs. Kurukshetra University, Kurukshetra, reported in (1976) 1 SCC 311, has held that, where a person on whom a fraud is committed is in a position to discover the truth by due diligence, fraud is not proved. The Appellant has not acted diligently. It ought to have found out lacunae or misrepresentations, if any, prior to permitting the commencement of work though contract was awarded. Such a defence could not have been raised after the work was completed and it was time to pay for it. This attitude is rank dishonesty on the part of the Appellant and cannot be countenanced.

5)

It is the settled position of law that, in an Appeal under Section 37 of the Arbitration Act, this Court cannot reassess the evidence to arrive at an independent conclusion. According to us, the Arbitral Award is also not in conflict with the public policy.

5.1) The contract between the Appellant and the Respondent was purely a civil transaction and/or a contract executed under the Indian Contract Act and nothing more than that. Appellant cannot be permitted, after completion of the work by the Respondent, to raise a specious plea that, it is against the public policy. We do not appreciate such a stand taken by the Appellant who is a Government of India undertaking.

5.2) We note that repeatedly raising the contention of bias and misconduct raised against a Counsel who acts as an Arbitrator in the matter is extremely disturbing to say the least. Such a stand ought not to be taken casually as a standard defence by any Appellant. The Appellant has alleged that the Arbitrator appeared in an unrelated matter against the Petitioner. This contention was addressed by the learned Single Judge correctly and ruled that the contention was based on a clear misreading of Sections 12(1) and 12(2) of the Arbitration Act. He further held that there was no violation of Section 12(5) read with 7th Schedule of the Arbitration Act. We emphatically affirm the said view.

6)

Considering the rival submissions and perusal of record clearly indicates that the impugned Order does not suffer from the vice of any legal perversity. The Learned Arbitrator has taken into consideration the entire evidence available on record in its proper perspective. The Learned Single Judge, in the Petition filed under Section 34 of the Arbitration Act, has fully and rightly considered the case in its entirety and passed a well-reasoned order dealing with each of the Appellant’s contentions.

7)

In view of the above, we are of the considered opinion that, there are no merits in the Appeal.

7.1) Appeal is accordingly dismissed.

8)

In view of dismissal of Appeal, Interim Application (L) No.11667 of 2024 does not survive and is also disposed off.