Judgment
Ajay Mohan Goel, Judge
By way of this petition, filed under Section 34 of the Arbitration and Conciliation Act, 1996, the petitioner has prayed for setting aside of the award passed by learned Arbitral Tribunal, dated 17.08.2019, in terms whereof the claim petition of the respondent has been allowed by learned Tribunal in the following terms:
“(i)An amount of Rs.11.70 Crore under claim No.1.
(ii)An amount of Rs.13.60 Crore under claim No.2.
(iii)Under Claim No.3, the Claimant is held entitled to Rs.6.07 Crore towards simple interest @ 12% per annum from 07.04.2016, the date when cause of action arose to the Claimant till 07.04.2018 the date of filing of statement of claim on the awarded amount of Rs.25.30 Crore.
(iv)Claimant is also held entitled to Rs.4.12 Crore towards pendente lite interest @ 12% per annum on the awarded amount of Rs.25.30 Crore from 08.04.2018 to 17.08.2019 the date of award.
(v)The Claimant is also held entitled to future interest @ 12% per annum from the date of award till payment on Rs.35.49 Crore, the awarded amount of (Rs.25.30 Crore+Rs.6.07 Crore prelitigation interest+ Rs.4.12 Crore pendente lite interest). In case payment, including interest is made within three months from the date of Award no future interest will be payable.
(vi)The Claimant is held entitled to proportionate costs of the proceedings from the Respondent, as provided under Section 31 (a) of the Act, qualified at Rupees Eighty Lakh only, which includes the fee payable by the Claimant to the Arbitrators, the unpaid amount of fees, which was payable by the Respondents and was ordered to be paid by the Claimant and the expenses of the Arbitrators including their travel and hotel expenses paid by the Claimant.”
Brief facts necessary for the adjudication of the present petition are as under: The case of the petitioner is that the parties, i.e. the petitioner and the respondent entered into a Contract, in terms whereof, the respondent agreed to execute the works relating to widening and strengthening of UnaBarsarJahuKalkhar Nerchowk Road, Section Una to Barsar from Km 45+000 to Km 90+800. A formal Contract embodying the terms of the agreement was duly executed and was numbered as Contract No.PW SRP/RIDC/Procurement ICB3/2008 of May 06, 2008. The works were completed by the respondent belatedly, however, the petitioner decided to grant extension of time till the completion of the work. After the payments with regard to the work executed stood made to the respondent, the respondent invoked the arbitration agreement with respect to its claim for damages for prolongation of the Contract. The respondent nominated Shri Ashok Khurana, Director General (Retd.), CPWD, as its Arbitrator nominee. On receipt of such notice of invocation of the arbitration, the petitioner nominated Shri R.K. Sharma, EngineerinChief (Retd.) IPH, Himachal Pradesh as its Arbitrator nominee and they both nominated Hon’ble Mr. Justice Devinder Gupta (Retd.) as the Presiding Arbitrator and the constitution of the Tribunal was completed on 24.02.2018.
The claim was filed before the Tribunal by the claimant and reply thereto was filed by the present petitioner and objections thereto were taken by the petitioner with regard to maintainability of the claim petition including the claim petition being hopelessly time barred as also the authority of the person who had filed the claim. Thereafter, the issues were framed by learned Tribunal and the parties led their respective evidence which led to the passing of the impugned award.
Learned Senior counsel appearing for the petitioner has argued that the award under challenge is not sustainable in the eyes of law, for the reason that learned Tribunal erred in not appreciating that the claim was beyond limitation. Learned Senior Counsel submitted that the findings returned by learned Tribunal that the claim was within the period of limitation were perverse findings and were inconflict with the Public Policy of India. Learned Senior Counsel further submitted that the findings of learned Tribunal that the claim was filed by a duly authorized person were also bad in law as the claim was not filed by the claimant through a duly authorized person and this also results in the award being inconflict with the Public Policy of India. Learned Senior Counsel further submitted that the findings returned by learned Tribunal that the claims were maintainable even in the absence of any notice in terms of Clause 24.1 of the Contract was a result of complete misreading of the provisions of the Contract and further, the findings returned by learned Tribunal pertaining to prolongation cost in maximum retail prises (MRPs) by ignoring the express provisions of agreement also amounted to the violation of requirements of Section 28 of the Arbitration and Conciliation Act. As per learned Senior Counsel, learned Tribunal erred in not appreciating that it was the claimant who had violated the terms of the agreement and while agreeing to extend the time for completion of the work, the present petitioner had not agreed to compensate the claimant for that and in fact the claimant had not led any claim qua the cost compensation and said claim was deemed to have been given by the respondent. According to learned Senior Counsel, learned Tribunal completely ignored the provisions of Clauses 14.10 and 14.11 of the agreement and it also erred in not taking note of the provisions of Clause 2.21 of the Contract in terms whereof, compliance as required was not done by the claimant. Learned Senior Counsel further argued that learned Tribunal failed to take note of the fact that extension of time as sought by the claimant was granted by the petitioner vide variation order No.3, dated 08.04.2011, as per determination by the Engineer without any prolongation cost and the condition in the extension of time to the effect that it was being granted without prolongation cost was accepted by the claimant even though the time being granted was contested. As per learned Senior Counsel, these aspects of the matter were not gone into by the learned Tribunal which renders the award inconflict with the Public Policy of India. Learned Senior Counsel further submitted that while quantifying claim No.1, learned Tribunal took the amount as claimed by the respondent without even referring to the stand of the petitioner and a mere certificate of the Chartered Accountant without any account details etc., who was not even produced as a witness by the party was construed to be correct and extremely exaggerated claim was granted in favour of the claimant to the deterrent of the petitioner. Learned Senior Counsel also submitted that while deciding claim No.2, pertaining to additional overhead cost during the extended period, learned Tribunal proceeded on the assumption that delay was attributable to the petitioner without even considering the defence of the petitioner or referring to the documents which were filed by the petitioner before learned Tribunal. Learned Senior Counsel further submitted that in fact a perusal of the award demonstrates that the same was passed by learned Tribunal with a predetermined mind and the evidence on record was neither correctly appreciated nor the pleadings were gone into in the correct perspective which renders the award to be against the Public Policy of India. Accordingly, a prayer has been made that the petition be allowed and the award be set aside.
Opposing the petition, learned counsel for the respondent argued that the present petition is not maintainable, for the reason that the grounds which have been urged in the same for setting aside the award are not available to the petitioner. Learned counsel submitted that the award passed by learned Tribunal is a reasoned and a speaking award which was passed by learned Tribunal after taking into consideration respective contentions of the parties and after referring to the documents relied upon by the parties and therefore, as the award stood passed by learned Tribunal by taking into consideration all that was placed before it by the parties, the same does not calls for any interference by this Court, more so in view of limited scope of interference under Section 34 of the 1996 Act. Learned counsel submitted that the petitioner has not been able to make out any case so as to invite interference of this Court under Section 34 of the 1996 Act and the intent of the petitioner is to call upon this Court to reappreciate the evidence on record which is not permissible in law. Learned counsel submitted that the petitioner wants this Court to arrive at its own conclusion with regard to the issues which were raised by the parties before learned Tribunal which is not permissible in law and accordingly he submitted that as there was no merit in present petition and further as the award passed by learned Tribunal was a valid award in terms of the Public Policy of India, present petition be dismissed. It was refuted by learned counsel that either the clauses of the agreement were not correctly appreciated by learned Tribunal or the claim petition was filed by a person not authorized to do so. Learned counsel also submitted that the award was within limitation as was correctly held by learned Tribunal as the acts of omission on the part of respondent before learned Tribunal were all continuing wrongs. He further submitted that delay in execution of the work was not on account of any acts of omission by the claimant, but the same was completely attributable to the present petitioner as has been rightly held by learned Tribunal. Accordingly, a prayer has been made for dismissal of the present petition.
Before the Court ventures into the adjudication of the present petition, it is necessary to refer as to what is the scope of interference by a Court with an Award under Section 34 of the 1996 Act. In terms of the law which has been laid down by Hon’ble Supreme Court of India, the jurisdiction conferred on the Courts under Section 34 of the 1996 Act is stated to be fairly narrow and when it comes to the scope of an appeal under Section 37 of the Act, the jurisdiction of the Appellate Court in examining an order setting aside or refusing to set aside an Award is said to be all the more circumscribed.
In MMTC Limited Versus Vedanta Limited, (2019) 4 Supreme Court Cases 163, Hon’ble Supreme Court held that the position is well settled by now that the High Court does not sit in appeal over the arbitral award and may interfere on merits on the limited grounds provided under Section 34 (2)(b) (ii), i.e. if the award is against the public policy of India. Hon’ble Supreme Court held that as per the legal position clarified through decisions of Hon’ble Supreme Court prior to the amendments to the 1996 Act in 2015, a violation of Indian public policy, in turn, includes a violation of the Fundamental Policy of Indian Law, a violation of the interest of India, conflict with justice or morality, and the existence of patent illegality in the arbitral award. Hon’ble Supreme Court further held that additionally, the concept of the “Fundamental Policy of Indian Law” would cover compliance with statutes and judicial precedents, adopting a judicial approach, compliance with the principles of natural justice, and Wednesbury reasonableness. Hon’ble Court has further held that ‘patent illegality’ it has been held to mean contravention of the substantive law of India, contravention of the 1996, Act and contravention of the terms of the Contract.
In K. Sugumar and Another Versus Hindustan Petroleum corporation Limited and Another, (2020) 12 Supreme Court Cases 539, Hon’ble Supreme Court held that the contours of the powers of the Court under Section 34 of the Act are too well established to require any reiteration and even a bare reading of Section 34 of the Act indicates the highly constricted power of the Civil Court to interfere with an arbitral award. Hon’ble Court has further held that the reason for this is obvious as when parties have chosen to avail an alternative mechanism for dispute resolution, then they must be left to reconcile themselves to the wisdom of the decision of the arbitrator and the role of the Court should be restricted to the bare minimum. Interference will be justified only in cases of commission of misconduct by the arbitrator which can find manifestation in different forms including exercise of legal perversity by the arbitrator.
In Dyna Technologies Private Limited Versus Crompton Greaves Limited, (2019) 20 Supreme Court Cases 1, Hon’ble Supreme Court in Para24 thereof has been pleased to hold as under:
“24.There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various Courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the Court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the Courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.”
Similarly, in Parsa Kente Collieries Limited Versus Rajasthan Rajya Vidyut Utpadan Nigam Limited, (2019) 7 Supreme Court Cases 236, Hon’ble Supreme Court has reiterated that construction of the terms of a Contract is primarily for an arbitrator to decide unless the arbitrator construes the Contract in such a way that it could be said to be something that no fair minded or reasonable person could do. Hon’ble Court further held that a possible view by the arbitrator on facts has necessarily to pass muster as the arbitrator is the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award. Hon’ble Court has also held that an award based on little evidence or no evidence which does not measure up the quality to trained legal mind would not be held to be invalid on this score.
Similarly, in Dyna Technologies Private Limited (supra), Hon’ble Supreme Court also held that the Court should not interfere with an award merely because an alternative view on facts and interpretation of Contract exists and the Courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act.
After referring to all the judgment mentioned hereinabove, Hon’ble Supreme Court in UHL Power Company Limited Versus State of Himachal Pradesh, (2022) 4 Supreme Court Cases 116, while reiterating the above mentioned legal position has reiterated that under Section 34 of the Act, the High Court cannot reappreciate the findings returned by learned Arbitral Tribunal and take a different view in respect of interpretation of relevant clauses of the agreement governing the parties. Hon’ble Court has observed that the High Court cannot act as a Court of appeal and the powers conferred under Section 34 of the Act are fairly narrow.
A perusal of the award demonstrates that on the basis of the pleadings of the parties, learned Tribunal ordered that each claim of the claimant will be treated as a separate issue and in addition, four more points were formulated for determination. The genesis of claim of the claimant before learned Tribunal was that it was awarded the work for construction and completion of widening and strengthening of BarsarJahu Section from Km 45 to Km 90.809 having total length of 45.80 km of UnaNerChowk Road. The Contract consisted of widening and strengthening of existing single/intermediate lane road to two lane standard invoking 37,000 cum bituminous works, 145,000 cum aggregate base work 650,000 cum earth work in excavation and embankment and 6 bridges with 33,000 cum concrete, Contract completion period would be 33 months. The contract was awarded on 29.02.2008. A formal agreement was executed on 06.05.2008 and total Contract value was Rs.103,93,81,256/. In terms of the Contract, entire stretch of 45.8 km of the road was to be completed within a period of 33 months from the date of issue of notice to proceed which was issued by the respondent through Engineer on 07.05.2008. As per the claimant, the completion of work was inordinately delayed due to various reasons attributable to the respondent and beyond the control of the claimant compelling the claimant to overstay at the site with all requisite men and machinery, which resulted in incurring substantial costs over and above the Contract costs. According to the claimant, the respondent/ employer was liable to reimburse to the complainant said costs as per law. It was further the case of the claimant that several notices were issued to the respondent under Clause 20.1 of the Contract, in terms whereof, the claim was raised by the claimant towards additional cost suffered due to prolongation of the Contract for reasons attributable to the respondent and beyond the control of the claimant. The respondent granted nine extensions of time, but additional cost incurred by the claimant on account of extension of time was not reimbursed. Further, according to the complainant, through its letter dated 07.04.2016, it included the claim prolongation cost in IPC 73 alongwith all contemporaneous record for payment by the respondent, but the Engineer through its letter dated 17.05.2016 abruptly and arbitrarily rejected the claim. After the claim was rejected by the Engineer and as the DRB being defunct, the claimant through its letter dated 13.09.2017 invoked arbitration and referred the disputes for adjudication. The case of the respondent before learned Tribunal was that the claims were not maintainable as the same were not raised as and when the same were alleged to have arisen and further the claimant failed to give requisite notice in terms of Clause 21.4 of the Contract. As per the respondent, while submitting the monthly progress reports, the claimants had repeatedly been mentioning the claim as ‘Nil’ and therefore, the claims referred were nothing, but an afterthought and were without any merit. The person filing the statement of claim was neither having any authority on behalf of the claimant to initiate the proceedings nor any authority has been filed with the statement of claim and therefore also the claim rejected merit. The pleas raised by the claimant were barred by limitation and it was the claimant who had sought nine extensions of time which were allowed by the respondents and this was done by the respondent by taking a lenient view as the work had to be completed and in fact the extension of time was granted to the claimant without imposing any liquidated damages so that to enable the claimant to utilize the amount. The claimant was illequipped and short of man power and equipment to undertake the work and certain minor hindrances which were there were in fact removed on priority basis. There was no hindrance as per the respondent in the execution of work created by local inhabitants as was claimed by the claimant and no notice raising the claim towards additional cost suffered due to prolongation of the Contract was sent to the respondent by the claimant in terms of the Contract.
In terms of the impugned award, the claim has been allowed by learned Tribunal, details whereof have already been stated in the judgment hereinabove.
In terms of the award, the following claims were made by the claimant:
“Claim No.I: Additional Cost incurred due to prolonged retention of the Equipment during extended period.
Claim No.II: additional Overhead Costs during Extended Period.
Claim No.III: towards Interest on the above claimed amounts of Prolongation Cost calculated as per clause 14.8 GCC.”
As I have already observed hereinabove that besides treating each the claim of the claimant to be a separate issue, learned Tribunal formulated the following points also for determination:
“a. Whether the clams are within the period of limitation? (onus on the Claimant)
b. Whether the clams have been filed by a duly authorized person on behalf of the Claimant? (onus on the Claimant).
c. Whether the claims are not maintainable for want of notice in terms of Clause 20.1 of GCC, as alleged? (onus on the Respondent)
d. Whether the Claimant is precluded from filing the claims after stating in the Monthly Progress Reports the claims as ‘NIL’, as alleged? (onus on the Respondent).”
Learned Tribunal answered Claim No.1 after referring to the respective stand of the parties as also the case law on the issue of holding that the contractor was entitled for additional costs for carrying out the Contract work in the extended period of Contract when the delay was caused on account of events which are either mentioned in the Contract itself or which are permissible for additional costs under the law. Learned Tribunal held that in terms of the provisions of the Contract as well as the judicial precedents referred therein, the claimant was entitled to both additional time as well as additional costs under the Contract for Delay Events attributable to the employer. It held that in the present case extension of time was granted to the claimant, but the Engineer as also the employer failed to consider the costs claimed and the entitlement of the claimant for additional costs arose under the Contract and not as an outcome of the extension of time granted by the respondent. Learned Tribunal held that the delay was not attributable to the claimant, but the same was attributable to the respondent and therefore, the claimant was entitled to recover from the respondent Rs.1.20 crore towards claim No.1.
With regard to claim No.2, learned Tribunal held that after due appreciation of the submissions of the parties, learned Tribunal was of the view that overhead costs are time related costs which are incurred with the passage of time and are not dependent on the value of work or quantum of work executed during the relevant time. It held that the site expenses were provided by the claimant to the respondent for its inspection at the material time, but no objection was raised at the relevant time and as regard Head Office overhead costs, the same was not uncommon that Head Office provides necessary support to project management and providing such support incurs expenses. Learned Tribunal after deliberating on the issue held that the claimant was entitled to an amount of Rs.13.07 crore under claim No.2.
With regard claim No.3, learned Tribunal held that as per Clause 14.8 of GCC as modified by the PCC, if the contractor does not receives payment in accordance with subclause 14.7 GCC, the contractor was entitled to receive interest compounded monthly on the amount unpaid during the period of delay and interest was to be calculated at 1% above the PLR rate fixed by the Reserve Bank of India to commercial Banks for payments in local currencies. Learned Tribunal further held that the claimant had filed the PLR rate fixed by Reserve Bank of India downloaded from its official website and Section 31 (7) (a) of the 1996 Act provided that the award may include such rate of interest between the date on which cause of action arose till the date of award as made. In light of said provision, learned Tribunal allowed simple interest @ 12% per annum from 07.04.2016, i.e. the date when the cause of action accrued to the claimant upto 07.04.2018, i.e. the date of filing of the Statement of Claim. The Pendente Lite interest was also allowed @12 % per annum 08.04.2018 to 17.08.2019. The future interest was held to be payable on the awarded sum from 17.08.2019 till the date actual payment @ 10% per annum with the condition that in case payment including interest was made within three months from the date of award, no future interest will be payable.
As far as the additional issues framed, learned Tribunal returned its findings as under:
With regard to Additional Issue(a): Whether the claims are within the period of limitation, Learned Tribunal held that as the claimant had raised its prolongation cost claim on 07.04.2016 which was rejected by the Engineer on 17.05.2016 and the claimant raised its additional cost incurred in its final bill on 09.05.2017 which was not paid, it is thereafter that the claimant invoked arbitration on 13.09.2017 and as the statement of claim was filed with supporting documents on 07.04.2018, i.e. within the period of three years from the date of accrual of cause of action on 17.05.2016 and 20.05.2017, therefore, the claim was within limitation in terms of the ratio of the law laid down by Hon’ble Supreme Court of India in Inder Singh Rekhi Versus Delhi Development Authority, AIR 1988 Supreme Court 1107.
With regard to Additional Issue(b): Whether the claims have been filed a duly authorized person on behalf of the Claimant, learned Tribunal held that this issue was framed on the objection taken by the respondent in its statement of defence, but the claimant had placed on record authorization dated 18.01.2016 in favour of Deepal Hooda, alongwith Board’s Resolution dated 13.01.2014 with the documents filed with rejoinder and therefore, objection of the respondent taken in the statement of defence had become redundant and moreover, this objection was not pressed by the respondent during final argument stage.
With regard to Additional Issue(c): Whether the claims are not maintainable for want of notice in terms of Clause 20.1 of GCC, as alleged, learned Tribunal returned the findings that the claims were maintainable even in the absence of notice in terms of Clause 20.1 of GCC, by agreeing with the contention with the contention of the claimant that Clause 20.1 of the Contract was in contravention of Section 28 of the Contract Act, 1872, whereby any agreement restricting enforcement of a party’s right absolutely or which limits the within which rights may be enforced is void. Learned Tribunal clearly held that when the Delay Events occurred, the claimant promptly notified the Engineer about the occurrence of such events to EOT and costs. In its EOT application, the claimant had narrated in detail the occurrence of consequences of Delay Events which was sufficient compliance in terms of Clause 20.1 of the Contract. Learned Tribunal also held that the Delay Events were reviewed and evaluated by the Engineer and on such evaluation, nine extensions were granted to the claimant and therefore, the Engineer was bound to determine the cost to which the claimant was entitled under the same Clause, but it failed to do so. Accordingly, it held that it was therefore not correct on the part of the respondent to urge that it had no notice of the Delay Events. Learned Tribunal also held that even assuming that the claimant had failed to give any notice of its claim as required under Clause 20.1 of the Contract, the same cannot be taken benefit of by the respondent in denying the claim because of Section 28 of the Contract Act.
With regard to Additional Issue(d): Whether the Claimant was precluded from filing the claims after stating in the Monthly Progress Reports the claims as ‘NIL’, as alleged, learned Tribunal returned the findings that as per the procedure brought to the notice of learned Tribunal, it was mentioned that on receipt of the copies of MPRs, the Engineer makes its comments and forwards it to the employer and in the case in hand, the copy of MPR which was shown to learned Tribunal, the entry against claim shown as ‘NIL’ was not shown by the claimant but by the Engineer and the same cannot be taken benefit of by the respondent.
As I have already mentioned in above part of the judgment in terms of the law as it stands today, the scope of interference under Section 34 of the Act qua an arbitral award is fairly narrow. In terms of pronouncements of Hon’ble Supreme Court, the High Court should not interfere with an award merely because an alternative view on facts and interpretation of Contract exists and further the Courts need to be cautious and should defer to the view taken by learned Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration and Conciliation Act. The High Court cannot reappreciate the findings returned by learned Tribunal and take a different view in respect of interpretation of relevant clauses of the agreement governing the parties.
A perusal of the award under challenge demonstrates that learned Tribunal in extensio took note of respective contentions of the parties. The case of the claimant has been dwelled with at length from para15 onwards of the award and similarly, the case of the respondent has been dwelled with again elaborately from para35 onwards of the award. The relevant Contract Clauses have been referred to by learned Tribunal from para64 onwards of the award. The chronological narration of the milestones finds mention from para65 onwards of the award with reference to the communications which were exchanged between the parties in the interregnum, which are part of the record. The chronological narration continuous till para157 of the award. From para158 onwards, learned Tribunal has returned its observations on the issues including the issue of limitation, the issue as to whether the claim was filed by a duly authorized person on behalf of the claimant, the issue whether the claims were not maintainable for want of notice in terms of Clause 20.1 of GCC as also the issue whether the claimant was precluded from filing the claim after stating in the Monthly Progress Reports the claims as ‘nil’ as alleged. The findings on the main claims are contained in the arbitral award from para201 onwards and perusal thereof demonstrates that while returning its findings on the claims, learned Tribunal has dwelled upon the respective contentions of the parties and thereafter returned its findings.
A careful perusal of the entire award thus demonstrates that the award has been passed by learned Tribunal after referring to the respective contentions of the parties and after taking into consideration the evidence which was led by them to substantiate their respective contentions. Therefore, in this background, this Court cannot say that the award has been passed by learned Tribunal without appreciating the respective contentions of the parties or without taking into consideration the documents which were produced before learned Tribunal by the parties.
Now, the next question which arises for consideration before this Court is as to whether this Court can in this background go into the findings returned by learned Tribunal by reappreciating the pleadings and evidence on record ? The answer to this in the considered view of this Court is in negative. Once, the findings that have been returned by learned Tribunal are based upon construction of respective contentions of the parties as also the evidence on record and the terms of the Contract entered into between the parties, then the findings returned by learned Tribunal in the considered view of this Court cannot be interfered with under Section 34 of the Act, more so as after carefully going through the findings so returned, this Court does not finds that the findings are against the law of land or are so perverse so as to shake the judicial conscious of this Court. In fact, this Court will hasten to act that in terms of the law as it stands today, when the parties have chosen to avail an alternative mechanism for dispute resolution, then they must reconcile themselves to the wisdom of the decision of Arbitrator and interference is justified only in cases of commission of misconduct by the Arbitrator which does not exists as far as present case is concerned. Learned Arbitral has not indulged in any exercise of legal perversity nor the findings returned are against settled laws of the land. The findings which have been returned by learned Arbitrator are simple findings of fact which have been so returned after appreciating respective stand of the parties as also the evidence led by them. This Court again reiterates that as reappreciation of evidence is not within forte of this Court under Section 34 of the Act, therefore, this Court is refraining itself from reappreciating the evidence so as to return the finding on merit qua the issues which were raised before learned Arbitral Tribunal by the claimant.
Suffice to say that in the backdrop of learned Tribunal having taken note of the facts, the evidence, the law governing the field and the Clauses of the Contract, the award so passed by it does not calls for any interference.
The thrust of the arguments of learned counsel for the petitioner as has been referred to hereinabove primarily was that learned Court misread and misappreciated the evidence on record and the findings which have been returned thereafter, therefore, are not sustainable in law. This Court is of the considered view that in light of the law as has been laid down by Hon’ble Supreme Court, referred to hereinabove, once this Court is satisfied that learned Arbitral Tribunal took into consideration the respective contentions of the parties, referred to the relevant documents relied upon by the parties, assigned reasons for arriving at the conclusion which have been arrived at, then the High Court cannot interfere with the Award so passed under Section 34 of the Act, because reappreciation of evidence by the High Court under Section 34 of the Act is not permissible in law. This Court reiterates that it is for the Arbitrator to construe the terms of the Contract and he is the ultimate master of the quantity and quality of evidence being relied upon by the parties. That being the case, now this Court cannot sit as an Appellate Court and reappreciate the evidence on record and then apply its mind and return the findings as to whether the conclusions which have been arrived at by learned Arbitrator are correct or not. It is not the case of the petitioner that the Award is in conflict with justice or morality or that there is patent illegality writ large over it as the same is in violation of the statutes or judicial precedents.
After going through the Award under challenge, it cannot be said that the findings which have been returned by learned Arbitral Tribunal are such that no fair minded or reasonable person could return such findings. Similarly, as the mandate under Section 34 of the Act is to respect the finality of the Arbitral Award, then if this Court was to interfere with the Arbitral Award in the usual course on factual aspects as is done in the case of an appeal, then the same would defeat the commercial wisdom behind opting for alternative dispute resolution as has been held by Hon’ble Supreme Court in Dyna Technologies Private Limited (supra).
Accordingly, in view of the above discussion, as this Court is of the considered view that the petitioner has not been able to make out any case for interference therein in terms of Section 34 (2)(b)(ii)of the Act, the present petition being devoid of any merit is dismissed. Pending miscellaneous applications, if any, stand disposed of. Interim order, if any, stands vacated.