Tribunals and CommissionsFull Bench(2022) 05 RERA CK 0847

Harpreet Singh Kapoor vs M/s Vardhman Estates & Developers Private Limited

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 19 May 2022

RESULT
Dismissed
CASE NUMBER
Comp. No. 76/2021

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

13 paragraphs · 679 words
1.

A complaint was filed in FORM ‘M’ on 09.08.2021 by Mr. Harpreet Singh Kapoor (hereinafter referred as “Complainant”) stating that in the year 2013 he approached M/s Vardhman Estates & Developers Private Limited (hereinafter referred as “Respondents”) for booking of a residential apartment in the respondent’s project “Vardhman’s I V@lley”, Plot no. 26/1, Knowledge Park-III, Greater Noida, Uttar Pradesh. A Builder Buyer’s Agreement was executed between the parties on 29.01.2014 for a 600 sq. ft. area residential apartment at a total sale consideration of Rs. 22,20,000/- (Rupees Twenty Two Lakh Twenty Thousand Only) and Complainant made full payment to the Respondents. The Complainant submitted that the Respondents have failed to handover the possession for more than eight years and, therefore, he seeks refund of amount deposited with the Respondents along with interest.

2.

A preliminary hearing in the case was held on 12.10.2021. Considering the an appeal was filed by the Complainant before Hon’ble REAT, the case was adjourned for 23.11.2021. An application dated 22.12.2021 was moved by the Complainant in order to restore the complaint as it was dismissed in default on 23.11.2021. The application was allowed, in the interest of natural justice, and the complaint restored.

3.

The Complainant submitted that "jurisdiction' has not been defined under the RE(RD)Act, 2016. Though, he booked an apartment in the project located at Knowledge Park-3, Greater Noida which is registered with RERA, Uttar Pradesh, but since the Head Office of the Respondents is located in Delhi and as the Builder Buyer Agreement specifies that all the disputes, between parties be settled in Delhi, therefore RERA, NCT of Delhi has jurisdiction to entertain the complaint and adjudicate in this matter.

4.

We have heard the arguments of both the parties and perused the records.

5.

The Respondents submitted that the project is already registered u/s 3 of RE(RD) Act, 2016, with the RERA, Uttar Pradesh. As per section 20 of RE(RD) Act, 2016 every appropriate Government has to establish RERA to exercise the powers and perform functions under the RE(RD) Act, 2016. Section 2(g) of RE (RD) Act, 2016 defines “appropriate government” which is given below:

“2(g). “appropriate Government” means in respect of matters relating to,—

(i)

the Union territory without Legislature, the Central Government;

(ii)

the Union territory of Puducherry, the Union territory Government;

(iii)

the Union territory of Delhi, the Central Ministry of Urban Development;

(iv)

the State, the State Government;” The Appropriate Government i.e. Govt of Uttar Pradesh accordingly established RERA, Uttar Pradesh for projects in Uttar Pradesh, and similarly the Appropriate Government i.e. Ministry of Housing and Urban Affairs, Govt. of India established RERA, NCT of Delhi for projects in NCT of Delhi. Any complaint with regard to any project and/or for enforcement of any right under the RE(RD) Act, 2016 remedy lies with the RERA of State / UT where the project is located. Thus, this Authority has no jurisdiction to adjudicate on the complaint filed u/s 31 of the RE(RD) Act. 2016 in respect of a project located in Uttar Pradesh.

6.

As per Rule 33 of National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016, a complaint has to be filed in Form-M before the Authority. Under Clause 3 of the Form-M, the Complainant has to declare that the subject matter of the claim falls within the jurisdiction of the Authority. The RE (RD) Act, 2016 is project centric. The Authority within whose jurisdiction of project is registered gets the jurisdiction to decide dispute arising under the RE (RD) Act, 2016, qua the project. As the project in question fall in Uttar Pradesh and is registered with the RERA, Uttar Pradesh, the present complaint does not fall within the purview of RERA, NCT of Delhi. As present complaint is not maintainable before this Authority, no relief can be granted to the Complainant against the Respondents. The complaint is dismissed on account of maintainability.

7.

The Complainant, however, will be at liberty to file a fresh complaint before RERA, Uttar Pradesh as per law.

8.

No order as to cost.