High CourtsSingle Bench(2022) 06 DEL CK 0956

General Manager Northern Railway vs Pioneer Publicity Corporation & Anr.

Delhi High Court · Decided on 1 June 2022

HON’BLE JUDGES
C. Hari Shankar, J
CASE NUMBER
O.M.P. (COMM) 154/2020 and OMP (ENF.) (COMM.) 120/2018 & E.A. 868/2020
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

369 paragraphs · 12,306 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

These petitions arise out of Interim Award-I dated 19th May, 2010, Interim Award-II dated 1st November, 2010 and interim Award (III) dated 29th October, 2012, passed by the learned Arbitrator in arbitral proceedings between Pioneer Publicity Corporation Pvt. Ltd. (“PPC” hereinafter), as the claimant and the General Manager, Northern Railway (“the Railways” hereinafter) as the respondent. Of the three Interim Awards, OMP (Comm) 154/2020, by the Railways, assails Interim Award III dated 29th October, 2012. Interim Awards I and II have not been challenged by either party. OMP (Enf) (Comm) 120/2018 by PPC seeks enforcement of all the three Interim arbitral Awards.

Facts

2.

Vide Commercial Circular No. 36 of 2006 dated 1st May, 2006, the Railway Board in the Ministry of Railways announced its intention to implement its scheme of awarding sole rights for commercial publicity on nominated divisions of the Railways to individual parties. In pursuance thereof, a notice inviting tender (NIT) was issued by the Railways in December, 2006, inviting tenders for commercial publicity in the Delhi division of the Railways. PPC emerged as the successful bidder. PPC‟s bid was accepted by the Railways vide letter of acceptance dated 18th May, 2007, which read thus:

“No.7 PUB/TN/Sole Right/DLI/DIV./2007 Date: May 18, 2007 DRM‟s Office New Delhi M/s Pioneer Publicity Corporation 274-CM-I, Office Complex, Jhandewalan, New Delhi-55 Sub: Acceptance of Sole Commercial Publicity Rights for ent Division for a period of five years. Ref: Tender dated 22/01/2007 In reference to above, it is to inform you that your offer of Rs.22,85,500/- (Rs.Twenty Two Crore Eighty Five Lacs Eighty Five Thousand Five Hundred only) with an Increase of 100%, 15%, 20% & 25% respectively over the previous year‟s license fee for Sole Commercial Publicity Rights of entire Delhi Division has been accepted by the competent authority for a period of five years. Before starting the work, you are required to fulfil the following formalities: 1. Submit a bank draft of Rs.11,00,42,750/- (after adjusting the EMD for Rs.42,50,000/- deposited in the tender) as license fees for first six months in favour of Sr. Divisional Finance Manager, Northern Railway New Delhi. 2. Submit FDR of Rs.2,28,58,550/- (10% of bid amount) as Security Deposit in the form of FDR or Irrevocable Bank Guarantee issued by a Scheduled Commercial Bank for a period of two years, within 15 days from issue date of issue of this letter in favour of Sr. Divisional Finance Manager, Northern Railway, New Delhi. 3. Stamp paper of Rs.100/- for execution of agreement. The above mentioned formalities should be fulfilled within 15 days of issue of this letter. Sd/-Sr. Divisional Commercial Manager New Delhi”

3.

As required by Clauses 31 to 33 of Section III of the tender documents, license fee, for the first six months of ₹ 11,00,42,750/-, alongwith security deposit of ₹ 2,28,85,500/- was paid, by PPC, to the Railways, on 1st June, 2007. Clause 31 to 33 of the Agreement may be reproduced thus:

“Payment schedule for license fees

31.

The licensee will have to pay license fee for a period of five years subject to an enhancement of 10% for second year, 15% for third year, 20% for fourth year & 25% for fifth year over the previous year's licensee fee respectively.

32.

The licensee will have to pay the 1st six months' rent in advance after adjusting the earnest money deposit within 15 days of the receipt of the acceptance letter sent by this office.

33.

Further payments for subsequent three months period shall be made on completion of three months from award of contract and so on every quarter.”

4.

Section V of the tender documents envisaged the making, by the Railways, of 213147 sq. ft. of area available to the successful bidder. This total area available for the tender was denoted, in Section V as „P‟ area. This „P‟ area was divided, further, into two sections, (A) and (B). Section (A) included 63 sites, comprising a total area of 167923 sq. ft, whereas Section (B) included 45 sites, with a total area of 45224 sq. ft.

5.

Section V of the tender documents is pivotal to resolution of the controversy in issue and is, therefore, reproduced, in extenso thus:

Sites assessed by Railways for advertisements in this Tender

Important Note: The details given in this section are for

general guidance of tenderers. They are expected to visit

the area and familiarize themselves with the earning capacity of advertisements before quoting for this tender
(A) Existing Medias as per running contract already awarded.
Shivaji Bridge-PalwalExistingArea (Sq.ft.)Availability Date
SectionNeelam Flyover1040013.07.2007
Faridabad485009.10.2008
Ballabhgarh135009.10.2008
Tughlakabad60409.10.2008
Faridabad New Town78409.10.2008
Palwal83409.10.2008
Shivaji Bridge26409.10.2008
Tilak Bridge26409.10.2008
Okhla66409.10.2008
Sub Total19814
Delhi Cantt-RewariExisting
SectionGurgaon213008.10.2007
Delhi Cantt.129008.10.2007
Palam43508.10.2007
Level Crossing Palam140008.10.2007
Sub Total5255
South Punjab Railway SectionExisting
Rohtak212716.01.2009
Bahadurgarh60416.01.2009
Level Crossing Rohtak140016.01.2009
Shakurbasti123816.01.2009
Delhi Sadar Bazar15416.01.2009
Delhi Kishanganj38416.01.2009
Sub Total5907
Ghaziabad-SaharanpurExisting
(Via Meerut City)Meerut City196122.05.2007
SectionMeerut Cantt54422.05.2007
Level Crossing Meerut City160005.07.2007
Level Crossing Muzaffar Nagar240005.07.007
Sakhoti Tanda Flyover80005.07.2007
Sub total7305
Delhi Ambala SectionExisting
Panipat215022.08.2008
Sonepat155022.08.2008
Karnal215022.08.2008
Kurukshetra155022.08.2008
Gannaur40022.08.2008
Narela107822.08.2008
Naya Azadpur40022.08.2008
Sub Total9278
Delhi Area SectionExisting
Delhi Sarai Rohilla135008.10.2007
New Delhi PF-2-1125020.05.2007
New Delhi FOB-164015.07.2007
New Delhi Main Hall117412.09.2007
New Delhi PF-194609.03.2008
New Delhi PF-121860
New Delhi Circulating area1721102.02.2008
New Delhi FOB-II883
New Delhi FOB-I/II56402.04.2007
Delhi Jn Overhead signage104804.10.2007
Delhi Jn Circulating Area550111.06.2008
Delhi Jn.Main Hall44029.09.2008
Delhi Jn.PF-11/13, 12/15, 16/17/18, 1A502
NizamuddinPF-6/7344
Nizamuddin Main Hall PF-172102.12.2006
Nizamuddin PF-2/3/4/5 FOB-1/II150402.09.2007
Nizamuddin overhead signage78404.10.2007
Ghaziabad239223.03.2007
Delhi Shahdara166502.03.2007
Subzi Mandi104519.02.2007
Sahibabad216818.06.2007
Level Crossing Ghaziabad180030.05.2007
IRCA772
PRS locations over Delhi Division479715.10.2008
Bridge Panel Zone-I196014.09.2009
Bridge Panel Zone-III696814.09.2009
Bridge Panel Zone-IV400001.10.2009
Bridge Panel Zone-V360001.10.2009
Protection Screen Zone-III863701.03.2007
Unipoles Zone-I256011.02.2007
Unipoles Zone-II528011.02.2007
Electronic Displays3700001.05.2007
Sub Total120366
Grand total Area Available for existing sites (Sq. Ft.)187923
(B) Proposed Media Not awarded yet ad immediately available to contractor
Shivaji Bridge-Palwal SectionProposedArea
Bata Flyover640
Sub Total640
Delhi Cantt.-Rewari sectionProposed
Pankha Road Flyover640
Palam Flyover640
Level Crossing Palam480
Road under Bridge near Shahbad Mohammadpur640
Level Crossing Gurgaon480
Sub Total2880
South Punjab Railway SectionProposed
Rotak1192
Sampla504
Nangloi160
Gohana400
Level Crossing Rohtak1200
Road Over Bridge Hisar Road320
Road Over Bridge Ismaila160
Level Crossing Sampla800
Level Crossing Asaudha400
Level Crossing Bahadurgarh400
Level Crossing Ghevra400
Level Crossing Nangloi400
Level Crossing Rohtak-Panipat800
Sub Total7130
Ghaziabad-Saharanpur (viza-Meerut City) SectionProposed
Murad Nagar500
Modi Nagar192
Muzaffarnagar580
Deoband300
Level Crossing Muzaffarnagar800
Sub Total2452
Delhi Sahadara-Shamli-Saharanpur SectionProposed
Shamli472
Baraut544
Baghpat404
NOU440
Sub Total1860
Jind-Jakhal SectionProposed
Narwana824
Tohana832
JIND832
Level Crossing Narwana1600
Level Crossing Tohana400
Delhi Ambala SectionProposed
Gannaur400
Narela700
Badli500
Kurukshetra800
Sonepat400
Panipat600
Sub Total3400
Delhi AreaProposed
Bridge Panels Zone-II3740
Protection Screen Zone-I3760
Protection Screen Zone-II4484
Protection Screen Zone-IV2724
Unipole Zone-III2240
Circulating Area Nizamuddin5420
Sub Total22368
Grand Total Area available for proposed site45224
Total area available for the tender (A+B) Sq.Ft.213147Say Area „P‟
Note: Exact location indicated in Part 'A' above shall be made over to the contractor w.eJ. date shown against each. However, the contractor shall be at liberty to display equivalent / more area at adjoining locations in accordance with para 4.9 of. Section II of Tender Document.
6.

The aforesaid transactions culminated in the execution of an agreement between PPC and the Railways. The agreement bore no date; however, PPC and the Railways consented, both before the learned Arbitrator as well as before this Court, that they were bound by the said agreement. The following clauses of the agreement merit reproduction :

“1.

The licensee shall be given the sole rights for display of advertisements over Delhi Division as per the area specified in the Annexure appended for a period of five years i.e. from 20/09/2007 to 19/09/2012.

2.

The advertisement rights for the sites mentioned in the annexure would vest with the licensee. The total assessed area for such sites works out to 213147 sq. foot.

3.

The contractor will be permitted to display advertisement at any station/and belonging to Delhi Division for a period of five years i.e. from 20/09/2007 to 19/09/2012.

4.

The exclusive Advertisement for Railway Stations/Platforms Concourse Halls/Circulating Area will vest with the licensee. All advertisers, recognized agents or otherwise, wishing to advertise will have to deal directly with the licensee and will have no dealing with the railways or stake any claim on the Railways for any commission etc.

5.

The ownership of the existing contracts will pass on to the contractor for display of commercial advertisement only after the expiry of the term of the contract. The contractor will have no locus-standi on the advertisement displayed by existing contractor until the expiry of the contract. The list of the contract in the order of their expiry is enclosed along with the terms and conditions of the contract.

Period of contract

6.

The contract will be for a period of Five years i.e. from 20/09/2007 to 19/09/2012.

*****

Reserving 10% area for Railways Slogan

15.

Railway will reserve 10% of the area free of cost, for display of commercial/safety posters, or/and other advertisements to promote socially relevant messages and railway services at the bottom/side of the display. The licensee will not have any claim over these displays. The matter for such displays shall be provided by Railways which the contractor shall arrange to print, erect, display at his cost. This will also be displayed on same pattern as remaining 90% area.

Pro-Rata Allotment

16.

The amount quoted by the tenderer in Packet „B‟ of this tender, will be applicable for total advertising area (P) assessed by the Railway or part thereof (including 10% free area as per para 15 above). Total assessed area (P) is, as indicated in Section V of these tender documents. The contractor will be allotted extra sites over and above the assessed area on his request, only after getting the technical and aesthetical feasibility of the sites from the Railway Administration. However, for this purpose the contractor will have to pay to Railway pro-rata extra amount that will be calculated for the relevant year and subsequent years based on total amount quoted for first year and worked out for the subsequent years as per formula given in Packet „B‟ in the Tender Documents.

****

Security Deposit

25.

The licensee will have to deposit the security deposit equivalent to 10% of license fee for the relevant year before start of each year in the form of FDR or irrevocable Bank Guarantee issued by a Scheduled Commercial Bank for a period of two years, within 15 days from issuing date of acceptance letter. The security deposit will be refunded on satisfactory completion of the contract period taking into consideration that all Railway dues are cleared.

Payment Schedule for license fees

31.

The licensee will have to pay the license fee for a period of five years, subject to an enhancement of 10% for second year, 15% for third year, 20% for fourth year & 25% for fifth year and the previous year‟s license fee respectively.

32.

The licensee will have to pay the 1st six months rent in advance after adjusting the earnest money deposit within 15 days of the receipt of accepting letter sent by this office.

33.

Further payments for adjustments three months period shall be made on completion of three months from award of contract and so on every quarter.

Commencement of contract

37.

The date of commencement of contract will be 120 days from the date of issue of the allotment letter or first display of any advertisement anywhere in this contract, whichever is earlier.

Arbitration

41.

In the event of any dispute or difference of opinion arising out of this Agreement or any special condition of contract or in connection with this agreement, the same shall be referred to the sole arbitration of a Gazetted Railway officer appointed by the General Manager/NR. The Gazetted officer appointed as arbitrator, however will not be one of those who had an opportunity to deal with the matter to which the contract relates or who in the course of their duties as Railway servants have expressed view on all or any of the aspects of the matter under dispute or difference. The award of the arbitrator shall be final and binding on the parties to this contract subject to aforesaid, the Arbitration & Conciliation Act, 1996 and the rules made thereunder or any statutory modification thereof for the times being in force shall be deemed to apply to the arbitration proceeding under this clause. The venue of arbitration shall be the place from which the acceptance note is issued. ****

48.

For the purpose of this agreement, the competent authority is Divisional Railway Manager/New Delhi.”

7.

Disputes having arisen between PPC and the Railways with respect to execution of the aforesaid Agreement, PPC, after following the protocol prescribed in that regard in the Arbitration and Conciliation Act, 1996 (“the 1996 Act”) moved this Court, under Section 11 thereof, by way of Arb. Appl. 30/2009. The Railways disputed the existence of an Arbitration Agreement, whereupon the petitioner filed CS (OS) 659/2009 (Pioneer Publicity Corpn Pvt. Ltd. v. UOI & Anr.). Ultimately, with consent of parties, this Court, vide order dated 26th May, 2009, referred the dispute to the learned Arbitrator, who came to pass the aforesaid Interim Awards.

8.

Claim petition was filed, by PPC, before the learned Arbitrator, on 18th August, 2009. On one ground or the other, the grievance of PPC, against the Railways, was that the contractually stipulated number of workable sites had not been provided by the Railways within the time stipulated in the agreement read with the tender documents. PPC raised, essentially, four claims against the Railways, resulting in nine reliefs claimed from the learned Arbitrator. Claim 1 was predicated on PPC‟s asserted entitlement to be provided 213147 sq. ft. of area of advertising space from the commencement of the contract till its conclusion, i.e. for the entire period of the contract. In the event of non-availability of any particular advertising site, PPC asserted that the agreement obligated the Railways to provide equivalent area to PPC at no extra cost. Failure, on the part of the Railways, to comply with both these alternative requirements, contended PPC, entitled it to be refunded the license fee paid by it in respect of the non-available advertising sites. Claim 2 sought adjustment, by the Railways, of the advance license fee paid by PPC. Claim 3 sought fixation of the date of commencement of the contract as the date when display was put up, by PPC, on at least 50% of the contracted advertising sites. Claim 4 envisaged merger of pre-existing contracts for commercial publicity/advertising, between PPC and the Railways, with the sole rights contract forming subject matter of the present controversy. Claim 4, asserted PPC, was in the event of the learned Arbitrator holding Claim 1 (iii), claiming refund of the license fee in respect of the unavailable advertisement sites, to be inadmissible.

9.

Predicated on these claims, PPC prayed, in its claim petition, for (a) a declaration that the Railways was liable to make available to PPC 2,13,147 sq. ft. of area of advertisement space from the commencement of the contract and for its full term, (b) a declaration that in case the Railways was unable to provide the advertisement space enlisted in the contract, then the Railways was liable to make available to PPC 'equivalent' or 'alternate‟ advertisement space in lieu of the non-available enlisted advertisement space, without any additional cost, (c) a declaration that demands raised by the Railways for license fee vide its letters dated 27th December, 2007, 8th May, 2008, 4th June, 2008, 3rd March, 2009, 25th March, 2009 and 6th August, 2009 were null and void abinitio, being contrary to the terms of the contract, (d) a declaration in favour of PPC and against the Railways declaring Clause 37 of the Agreement, regarding the “commencement date of contract” unconscionable, oppressive and unenforceable and therefore null and void and severable from the Agreement, (e) a declaration that the contract was deemed to have commenced from on or around 23rd March, 2008 or such other date as the learned Arbitrator determined, (f) a direction to the Railways to pay the claimant a sum of ₹ 11,32,36,050 being the principal sum of the excess license fee paid to the Railways during the first year of the contract, reckoned by the Railways from 20th September, 2007 to 19th September, 2008. (g) a direction to the Railways to pay, to PPC, a sum of ₹ 5,21,73,780.64/- being the sum of the excess license fee paid to the respondents (from 20th September, 2008 to 31st September, 2009) during the second year of contract, reckoned by the Railways from 20.9.2008 to 19.9.2008 and any other claim for such further periods, as may have arisen during the pendency of these proceedings, (h) a direction to the Railways to pay PPC interest @ 2% per month towards past, pendente lite, and for future on the sums found due and payable by the Railways to PPC, (i) in the alternative to prayers (f), (g) and (h), a declaration in favour of PPC and against the Railways, extending the period of contract for a period equivalent to the days as would be assessed against the excess amount of license fee paid by PPC to the Railways.

10.

The learned Arbitrator notes, in para 19 of the impugned Award, that the total 213147 sq. ft. of area which, according to Section V of the tender documents, was to be made available to PPC, was divided into Parts A and B, consisting of 63 and 45 items/sites respectively. The 63 sites/items comprising Part A (covering 167923 sq. ft.) were already in occupation by other contractors, consequent to pre-existing advertising contracts executed by the Railways which were still in operation. They would, therefore, become available to PPC only after expiry of the said contracts, on the dates stipulated in Part A of Section V. Part B consisted of 45 items/sites (covering 45224 sq. ft.), which were vacant and were, therefore, to be made immediately available for possession by PPC. The total area of 213147 sq. ft. was denoted in Section V as the „P‟ area.

11.

In order to avoid confusion amongst the various categories of sites, a systematic procedure was followed by the learned Arbitrator. Initially, he called upon the parties to assign numbers to the various sites, with which we need not, in this case be particularly concerned. Thereafter, on 31st December, 2009, a joint signed chart was prepared for all the 108 tendered items/sites.

12.

Thereafter, 10 Joint Lists of items were prepared by consent of both the parties in the arbitral proceedings, i.e. Joint Lists A, A-1, A-2, B, B-1, C, D, E, F and G. Joint Lists A, A-1 and A-2, which were jointly signed on 10th February, 2010, 5th April, 2010 and 28th April, 2010, respectively covered 39, 15 and 13 sites which the Railways admitted, for various reasons, not to have been able to make available to PPC. Joint Lists B and B-1, which were signed on 10th February, 2010 and 5th April, 2010 covered new sites, or sites of which the area was increased by the Railways on PPC‟s request. Joint List F covered 13 sites on which display was disrupted due to interference by various local or governmental agencies, who were third parties, and in respect of which the interruption was admitted by the Railways. The remaining disputed sites were, therefore, covered by Joint Lists C, D, E and G.

13.

Interim Award-I dated 19th May, 2010 and Interim Award-II dated 1st November, 2010 were passed, by the learned Arbitrator, in respect of the admitted sites covered by Joint Lists A, A-1, A-2, B, B-1 and F, for the periods 20th September, 2007 (the date of commencement of the contract) to 31st December, 2009. The learned Arbitrator held PPC to be entitled, for the aforesaid periods, to ₹ 1,35,54,035/- and ₹ 1,06,48,631/- respectively.

14.

These Interim Awards, i.e. Interim Award-I dated 19th May, 2010 and Interim Award-II dated 1st November, 2010, have not been challenged by the Railways.

15.

Interim Award-III, which forms subject matter of challenge in OMP (Comm) 154/2020, dealt with the sites/items covered by Joint Lists C, D, E and G. The particulars of these lists may be provided thus:

(i)

Joint list C covered sites reflected in Part A of Section V of the tender documents (which dealt with sites which would not be immediately made available to PPC as they were already being worked under pre-existing contracts with other contractors), in respect of which no future dates on which the sites would become available were stipulated in the tender documents. There were 4 items in the said Joint List C, of which one item was shifted to Joint List A and 3 items were shifted to Joint List G which dealt with the relief that PPC was seeking in respect of such sites.

(ii)

Joint List D contained 17 items in respect of which refund was sought, by PPC, owing to delay in sanctioning approval, by the Railways, of the site plans submitted by PPC, as a result of which PPC was unable, during the period for which the site plans remained unapproved, to display on the said sites. There were initially 17 items in Joint List D, of which 8 were shifted to joint list A-1 and 9 remained to be adjudicated by the learned Arbitrator.

(iii)

Joint List E comprised items in respect of which PPC alleged that the sites were not feasible for advertising. There were 25 items in Joint List E of which, by consent, 21 items were shifted to Joint List A-1 and A-2 and 4 items remained to be adjudicated by the learned Arbitrator. To these four, one additional item, i.e. Item 169 (Gurgaon Level Crossing) was added, after shifting it from Joint List A-2. There were, therefore, 5 items for adjudication by the learned Arbitrator in Joint List E.

(iv)

Joint List G comprised the 41 items, which under Part (A) of Section V of the tender documents, and would not be available to PPC at the commencement of the contract, but would be made available on future dates, specified or unspecified. In respect of these sites, PPC claimed refund of license fee deposited by it, as the Railways had neither made the said sites available at the time of commencement of the contract, nor had provided equivalent alternative sites.

Re-prayer regarding fixation of date of commencement of contract

16.

As already noted in para 9 supra, one of the prayers of PPC, in its claim petition, was that the date of commencement of the contract be fixed as the date when PPC was able to display on at least 50% of the contractually envisaged advertising sites. The learned Arbitrator did not agree, and fixed the date of commencement of the contract as 20th September, 2007, being the date stipulated in the tender documents as well as in the agreement executed between the parties.

17.

This finding, of the learned Arbitrator, is not in challenge. Accordingly, the date of commencement of the contract stands at 20th September, 2007.

Findings, grounds of challenge and analysis thereof

18.

The stage having thus been set, one may proceed to the findings of the learned Arbitrator, insofar as they are under challenge at the instance of the Railways, in OMP (Comm) 154/2020.

Re. Joint List D

19.

The learned Arbitrator proceeded, first, to deal with the items covered by Joint List D, which comprised the sites in respect of which refund of license fee deposited by it was claimed by PPC on the ground of delay, by the Railways, in approving the site plans submitted by PPC.

20.

This covered tendered items Serial No. 1, 20, 21, 33, 34, 46, 49, 53 and 108. Of these, the learned Arbitrator allowed all the claims except the claim in respect of Serial Nos. 1 and 108. The amounts awarded in respect of these items were as under:

Serial No.ItemAmount
20Meerut City Station₹ 557336/-
21Meerut Cantt Station₹ 154610/-
33New Delhi PF 2-11₹ 410200/-
34New Delhi FOB 1₹ 210022/-
46NZM Station₹ 236603/-
49Ghaziabad₹ 784958/-
53Ghaziabad Lxing₹ 590688/-
21.

The aforesaid awarded amounts have not been challenged by the Railways. They, therefore, are upheld.

Re. Joint List E

22.

This list comprised 4 items in respect of which, according to PPC, it was not feasible to erect displays at the site. Of the four items 1, 60, 63 and 69, the learned Arbitrator allowed three, rejecting the claim in respect of Serial No. 1. The amounts awarded in respect of these three items are as under:

Serial No.ItemAmount (Rs)
60Protection Screen Zone-III (a) Paharganj Bridge (b) Zakhira Bridge2,44,221 7,74,253
63Electronic Display (a) Pankha Road Flyover (b) School Lane Flyover5,04,546 NIL
69Gurgaon Level Crossing3,83,947/-
23.

The amounts awarded in respect of Joint List E are also not under challenge in the present OMP filed by the Railways. The award in that respect is also, therefore, upheld.

24.

The total amount awarded by the learned Arbitrator in respect of joint lists D and E is ₹ 48,51,386/-.

25.

With that, one comes to the items in respect of which the Railways have disputed the impugned Award, which are contained in Joint Lists C and G.

26.

These lists pertained to the items covered by Part A of Section V of the tender documents, i.e. the sites which could not be immediately be made available to PPC as they were already subject matter of pre-existing contracts with other contractors, who were working on the said sites. As already noted hereinbefore, PPC‟s contention was that (i) contractually, the Railways were required to make available, throughout the period of the contract and starting with the date of commencement of the contract, 213147 sq. ft. of advertising area, (ii) in the event of any part of the said area not being available, the Railways were required to make available, to PPC, equivalent area and (iii) failing that, the Railways were required to refund, to PPC, license fee, deposited by it in advance, proportionate to the area which had not been made available.

27.

In respect of this, the learned Arbitrator held as under:

(i)

It was true that, in Section V of the tender documents, the sites in Part A were reflected as available to PPC only prospectively, on future dates, as they were under possession by third parties, with whom publicity contracts were in progress. The allotment letter dated 6th August, 2007 assessed that PPC would acquire (a) by the end of 2007, 65% of the total advertising area, admeasuring 135664 sq. ft, (b) by the end of 2008, 87% of the total advertising area, admeasuring 183593 sq. ft. and (c) by October, 2009, the entire advertising area, comprising 213174 sq. ft.

(ii)

Vis-a-vis the position as it existed in the tender documents, by the time of issuance of the allotment letter on 6th August, 2007, 2747 sq. ft. of area had been shifted from Part B of Section V to Part A thereof. With this change, the area in respect of which the dates by which the sites would be made available to PPC were postponed stood reduced to 6418 sq. ft.

(iii)

On 19th June, 2010, PPC and the Railways mutually agreed to reduce the total tendered area from 213147 sq. ft. to 199295 sq. ft.

(iv)

As per the allotment letter dated 6th August, 2007, 123985 sq. ft. of area was to be immediately available to PPC and 89162 sq. ft. was to be made available on stipulated future dates. Even so, between the time of floating of the tender in December, 2006 and commencement of the contract on 20th September, 2007, 17 sites, which were earlier included in Part A of Section V, covering 84690 sq. ft., became physically available for use by PPC. The details of these sites are provided in the impugned award thus:

S. No. of Tender ItemName of item/site/mediaArea (Sq.Feet) as per TenderArea (Sq.Feet) as per Allotment letter
1Neelam fly over1040010400
20Meerut City19611961
21Meerut Cant544544
33New Delhi PF 2-112501250
34New Delhi FOB 1640640
35New Delhi Main Hall11741174
40Delhi Jn FOB I & II504504
46NZM Main Hall/PF-1721721
47NZM PF 2/3/4/5 FOB I & II15041504
49Ghaziabad23922392
50Delhi Shahdara16651665
52Sahibabad21682168
53Lxing Ghaziabad18001800
60Protection Screen Zone III86378637
61Unipoles Zone I25604000
62Unipoles Zone II52806240
63Electronic display3700039090
Total7920084690
(v)

With the making of the aforesaid 17 items available, 46 sites/items, in Part A of Section V of the tender documents, remained unavailable for display, by PPC, on the date of commencement of the contract, i.e. on 20th September, 2007. These 46 items covered an area of 88663 sq. ft.

(vi)

Of these, with the issuance of the letter of allotment on 6th August, 2007, the future dates when the sites would become available were stipulated in respect of all but two sites.

(vii)

5 items out of the aforesaid 46 items, covering an area of 7534 sq. ft., were settled between the parties and included in Joint Lists A and A-1 and B-1 and were, therefore, covered by Interim Award-I. 41 items, covering 81120 sq. ft. therefore, remain to be adjudicated by the learned Arbitrator.

(viii)

The findings of the learned Arbitrator, therefore, insofar as they are subject matter of challenge by the Railways in the present case, are in respect of the aforesaid 41 items covering 81120 sq. ft.

(ix)

The prime issue that arose for consideration, as identified by the learned Arbitrator, in respect of the claim of PPC in the above regard was the relationship between the offered price and the assessed area. The learned Arbitrator has delineated the issue thus, in para 26 of the impugned Award:

“a)

The issue which arises for my determination is whether the liability of the Claimant to pay the license fee of Rs. 22.85 crores (approx.) for the 1st year has any nexus with the Respondent's obligation to provide the entire area of 2,13,147 sq. ft. for the entire period of 1st year i.e. 20.9.2007 to 19.09.2008.

Or

Is the Respondent entitled to receive the entire payment of license fee of Rs.22.85 crore (approx) in the 1st year, even if the area provided, is admittedly much short of tendered area of 2,13,147 sq.ft., and it has provided the advertisement area/ sites , in phases and in a staggered manner, as per the dated specified in Section V of the tender?

b)

The same issue shall also arise for determination in respect of liability of enhanced license fee payable for 2nd year and enhanced license fee payable for the 3rd year ending with 12.10.2009, when admittedly, as per the Respondent, all sites would have been handed over to the Claimant, as per the dates specified in Section V of the Tender and modified in allotment letter.”

(x)

Relying on Clauses 1, 2, 3, 4 and 16 of the Agreement, and paras 4.1, 4.9 of Section II read with the Annexure and Section V of the tender documents, the learned Arbitrator has, in paras 27 to 30 of the impugned award, held that the Railways were required, ab initio and from the date of commencement of the contract, to make available, to PPC, 213147 sq. ft. for display/publicity. Paras 27 to 30 of the impugned award read thus:

“27.

The relationship of quoted price by the licensee (Rs.22.85,85,500) with the area(2,13,147sq feet) to be provided by the Respondent with reference to the Agreement has been scrutinized and appreciated further (Claimant's Documents Vol. I {pages 5. to 55. and Respondent's filed a copy of the agreement on 7.09.2009):-

(a)

Under Clause 1, it is announced and committed that licensee would be given the Sole Rights for display of advertisements over entire Delhi Division, as per the area specified, for a period of five years. It is reproduced below:

"The licensee shall be given the sole rights for· display of advertisements over Delhi Division as per the Annexure appended for a period of five years i.e. from 20.9.2007 to 19.9.2012" The Paragraph 4.1 of tender conditions state that 'contractor will be permitted to display advertisement at any station, land belonging to Delhi Division for a period of five years." ....

(b)

Under Clause-2 of the Agreement, it is promised that all advertisement rights for the sites mentioned would vest with the licensee The total assessed area for such sites works out to be 2,13,147 sq.ft . lt is reproduced below:

“The advertisement rights for the sites mentioned in the Annexure would vest with the licensee. The total assessed area for such sites works out to be 2,13,147 sq. feet. Paragraph 4.9 of tender conditions states that “The amount quoted by the tenderer will be applicable for total advertising area assessed by. The Railway ....” Paragraph 4.5 of tender conditions state that “The exclusive advertisements (rights) for railway stations/platform/concourse halls/circulating area will vest with the successful tenderer

(c)

Clause 3 and 4 of .... the Agreement define the freedom of the Licensee to display advertisement at any station/land belonging to Delhi Division for a period of 5 years and confirm that the licensee will be vested with exclusive rights and will have direct relationship with advertiser/space buyers, who will not be entertained by the Railways. (These correspond to contents of Paragraph 4.1 and 4.5 of tender conditions)

(d)

Clause 16 of the agreement states:-

"The amount quoted by the tenderer in Packet 'B' of this tender, will be applicable for total advertising area (P) assessed by the .Railway or part thereof (including 10% free area as per Para 15 above) Total assessed area (P), is as indicated in Section V of these documents. The contractor will be allotted extra sites over and above the assessed area on his request only after getting the technical and aesthetical feasibility of the site from the railway administration. However, for this purpose, the contractor will have to pay to Railway pro rata extra amount that will be calculated for the relevant year and subsequent years based on total amount quoted for first year and worked out for the subsequent years as per formula given in Packet 'B' of the Tender documents."

(e)

Para 4.9 of Section II of the Tender document (Terms & Conditions) also stated the same, that "The amount quoted by the tenderer will be applicable for total advertising area assessed by the Railways, or part thereof (including 10% free area as per para 4.8 above). Total assessed area is indicated in Section V of these tender documents. The contractor will be allotted extra sites over and above the assessed on his request, only after getting technical and aesthetical feasibility, or the sites from the Railway administration. However, for his purpose, the contractor will have to pay to Railway pro rata extra amount, that will be calculated for the relevant year and subsequent years, based on total amount quoted for the first year and worked out for the subsequent years, as per formula given in Packet B of the Tender documents."

28.

The “Annexure” referred in clauses 1 and 2 and “Section V” referred in clause 16, (and also referred in Para 4.9 of tender conditions) is one and the same thing. The title page of Section V of Tender documents has the following contents inscribed on it:

“Section V: Area assessed by railways for advertisement for the purpose of present tender and quoting the rate for first year "(Sheets 24 to 26).

The usage of words "first year" for inviting the bids and out-lining the scope of the assessed area is vital. This establishes the relationship of the „area‟ with the offered rate for the first year .At the end of list of tendered items, it is stated that "total area available for the tender (A+B) Sq. Ft ...... 213147.... Say area "P" .

29.

These clauses of the Agreement and Paragraphs of the Tender conditions bring out the following facts:

a. Total area assessed by the Railway and offered for the bid is 'P' (and it is 2,13,147 sq. feet)

b. Offered license fee will be applicable to total assessed area (it includes 10% area to be used as free and is meant for Railway messages)

c. Any additional area on request will be over and above the assessed area and offered price.

d. Request for additional area can be made by licensee at any time during the currency of the contract of five years.

e. Pro rata license fee payable for additional area will be derived, based on the first year calculations of price, and recalculated for the particular subsequent year, for the purpose of 'extra charge' to be levied.

30.

Para 4.9 of tender conditions and clauses 2 and 16 of the Agreement clearly provide that the amount quoted by the tenderer will be applicable for total advertising area assessed by the Railways, (including 10% area meant to be earmarked free of cost for railway messages). In other words, for the assessed area i.e. 2,13,147 Sq ft., a fixed license fee is to be charged, and for the additional area, licensee is liable to pay more charges.”

(xi)

The learned arbitrator has, thereafter, proceed to deal with the Note in Section V of the tender documents, thus, in paras 33 and 36 of the impugned award:

“33. Significance and Implications of the NOTE in the Tender

a)

The "Note" contained at the end of Section V of the tender reads as under

"Note: Exact location indicated in Part A above shall be made over to the contractor w.e.f. date shown against each. However, the contractor shall be at liberty to display equivalent/more area at adjoining locations in accordance with para 4.9 of Section II of Tender Document."

b)

It has been admitted in the written statement of Respondent that 'additional' or more area/sites were to be given on specific request to be made by the Claimant and scrutinized/assessed and, permitted by the Respondent. The provision of additional/more extra area over and above the assessed area of 213147 sq. ft as reflected in Section-V, to be charged at the prevailing rate during the currency of the contract is already covered in tender conditions 4.1 & 4.9 (Section-II) and Clause 16 of the agreement (Section-III). These provisions make it absolutely clear the action to be taken by the licensee if it wants more advertising area after it has been allotted and handed over possession of 213147 sq. ft. The method and formula of calculation of applicable tariff has been specified in (Packet B) of the tender document. No further clarification was needed.

c)

If there was no intention of providing the 'equivalent area' , corresponding to unavailable area, as such area was occupied by the pre-existing contracted sites, such a special Note at the end of the list of tender items ( Section -V) was unnecessary and redundant. The usage of words 'equivalent area' & 'adjoining' makes the provision unique and attractive for the prospective bidders. These are the key words and have not been found referred or used hitherto, anywhere in the tender/ agreement, before one reaches the 'Note'.

d)

This entitles the licensee to seek '"equivalent" area at adjoining locations. But the Respondent says "only on extra payment" in accordance with Para 4.9. However, this particularly referred paragraph covers the allotment of extra sites over and above the assessed area (and not before that ) and requires a request from the licensee ,examination of the proposal from technical and aesthetic point of view by the railway and payment of extra charge. Charges are payable when the additional sites are allotted, and the area increases beyond the 'assessed area'. It is implied and intended that in respect of these sites which enables the licensee to reach and remain within the total assessed figure of 2,31,47 sq. feet of area (P area), no further charges are to be paid. No one can say "I will use the area for a specified period, but will not pay for it. Similarly, nobody can turn and say that "I will take the full amount but will not give total 'area' as specified." In other words there has to be 'quid pro quo' i.e. it has to be an equal exchange or substitution of goods or services. It also indicates an item or a service which has been traded in return for something of value.

36.

The Tribunal has gone into the meaning as found in the Dictionaries, as far as word 'equivalent' is concerned. Though 'more' , 'additional' and 'extra' fall in the same category, and mean and connote the same thing, but 'equivalent' implies 'equal in value', 'identical', 'corresponding' co-relative' 'comparable' and 'commensurate' etc. By no stretch .of imagination 'equivalent' can be termed synonymous of 'additional' or 'extra' or 'more'. ”

(xii)

The learned arbitrator also holds that the stipulation, in Clause 31 of the Agreement, that in each year, the fee payable by PPC to the Railways would be 5% over the previous year‟s fee would stand defeated if the quoted rate were to be applied to the entire area on 213147 sq. ft. or any part thereof.

(xiii)

Reliance was also placed, by the learned arbitrator, on a communication dated 25th July, 2007, from the Divisional Railways Manager (DRM), Delhi Division to the NDMC, MCD and the Faridabad Municipal Committee, in which the tender rate, per square foot, for the first year of the contract between the Railways and the PPC was stated as ₹ 1072.43. This figure of ₹ 1072.43, noted the learned arbitrator, was arrived at by dividing the total contracted fee payable for the first year, of ₹ 22,85,85,500 /- by 213147 sq. ft. This, therefore, amounted in the view of the learned arbitrator, to an acknowledgement of the fact that, during the first year of the contract, the Railways were required to make available, to PPC, 213147 sq. ft. of advertising area.

(xiv)

The learned arbitrator also notes that in the Joint Lists drawn up and signed by them, PPC and the Railways had applied the pro rata charges, as envisaged by the agreement, of ₹ 1072/- per square foot for the first year, ₹ 1180/- per square foot for the second year and ₹ 1357/- per square foot for the third year.

(xv)

The learned arbitrator, thereafter, proceeded to examine whether Clause 5 of the Agreement militated against the requirement of the Railways making available, to PPC, of 213147 sq. ft. of advertising area in the first year. Clause 5, it may be recalled, reads thus:

“The ownership of the existing contracts will pass on to the contractor for display of commercial advertisement only after the expiry of the term of the contract. The contractor will have no locus standi on the advertisement displayed by existing contractor until the expiry of the contract. The list of the contract in the order of their expiry is enclosed along with the terms and conditions of the contract.”

The learned arbitrator holds that Clause 5 could not be used as a justification for the Railways not making available, to PPC, 213147 sq. ft. of advertising area during the first year, as it merely gave a protective cover to pre-existing contracts. Effectively, therefore, according to the learned arbitrator, the Note in Section V of the tender documents read with Clause 5 of the Agreement counterbalanced the rights of PPC and the contractors with whom pre-existing contracts were still in operation, by protecting the rights of such latter contractors till the expiry of their contracts and, at the same time, requiring the Railways to make available, to PPC, 213147 sq. ft. of advertising area during the first year or, in the event of non-availability, providing equivalent alternate space.

(xvi)

The Railways sought to contend that PPC‟s right to alternate equivalent area under the note in Section V of the tender documents was conditional on PPC making payment for such additional area as envisaged by Clause 4.9 of Section II of the tender documents. In holding that no additional fee would be recoverable from PPC for the “equivalent area” envisaged by the Note in Section V, the learned arbitrator placed reliance on Notice Inviting Tenders (NIT) which specified that, after the provision for “P” area was over, additional “Q” area could be provided to PPC, on requisition, against additional payment. This indicated, according to the learned arbitrator, that so far as 213147 sq. ft., covered by the “P” area was concerned, there could be no question of additional payment being made by PPC.

(xvii)

In this context, the learned arbitrator relies on letters dated 20th July, 2007 and 29th August, 2007, from the Chief Commercial Manager (CCM) to the Senior Divisional Commercial Manager and to the DRM, Delhi Division. The former communication stated that it was “obvious that there was every intention of the division to provide the total area for the full period of the contract, right from the first year, and as some of the areas were not immediately available, due to running contracts, there was a provision of giving an alternative area on equivalent basis (equivalent area)”, whereas the latter communication stated that “for locations, which are not immediately available, due to an existing contract having validity for the next one year to two years, there is a provision in the entire bunch of tender documents of an equivalent area to be provided”. The Background Note, dated 24th July, 2007, to which these communications pertain, having been endorsed by the Railways to PPC, the learned arbitrator held that these communications could not be treated as mere internal missives. He also relied on the known position that the CCM was the head of the commercial department in a zonal railway for all divisions in respect of which, subject to being overruled by the General Manager, he was the final authority. In this context, the learned arbitrator extracted the following passages from the communications of the CCM:

“basic issue to be decided is, whether the area to be given to the contractor is 2,13,147 sq. ft. right from the start of the tender. This is because Section V of the tender document mentions details of the sites in two parts, item (A) and (B) and it's total as assessed by the Railways, called (P), for this tender. In item (A), .the sites where contracts awarded are running have been mentioned along with the respective area, the total area has been shown as 1,67,923 sq. ft. In item (B), the sites available immediately to the contractor along with their areas, have been separately shown; the total area available under this head is 45,224 sq. ft. The total of (A) and (B) adds up to 2,13,147 sq. ft. It is mentioned in a note below this that "Exact location indicated in Part A shall be made over to the contractor w.e.f. the date shown against each. However, the contractor shall be at liberty to display equivalent/more area at adjoining locations in accordance with Para 4.9 of Section-II of Tender Documents"

“We may also study the respective Clauses of the agreements:”

(a)

Clause 5 of the Agreement only protects the rights of the existing Advertising Contracts, as these cannot be removed and their Contract terminated just because a Sole Right Tender has been awarded. These contracts shall continue till their validity. This is confirmed by Para 4.2 of Instructions to Tenderers and the Terms and Conditions.

(b)

Clause 2 of the Agreement specified that the Site mentioned in Annexure to the Tender Document would vest with the licensee. The total assessed Area works out to 2,13,147sq.ft.”

(c)

There is no mention of time frame for handing over this area to the Licensee. The obvious conclusion is that it is envisaged the full area equivalent to 2, 13,147 sq. ft. would be made available to the licensee for the total period of the contract.

(d)

Clause 16 confirms that the “amount quoted in Packet-B will be applicable for total Advertising Area assessed by the Railway” (The wordings "part thereof' is to identify the 10% area for Railway Slogans etc. as per Clause 15)-This area is as mentioned above 2, 13,147 sq. ft.

The obvious conclusion is that Clause 16 and 2 are supplementing each other. In Clause 16 as the words 'total advertising area" had been recorded; it had to be clarified by words, or part thereof so that 10% area could be excluded from the advertising area for Railway's own slogans/messages. This is again confirmed in Clause 16 itself where it is written- total assessed area (P) is SIS indicated in Section V of these documents" The area (P) is the total of items (A) and (B) and, hence, it was envisaged that 2,13,147 sq. ft. of area is to be given for the entire period of the contract"

"Let us now see what Section V of the Tender Document provides":

Section V of the Tender Document has the Title- "Area assessed by Railways for Advertisement for the present Tender Quoting the Rates for the First Year". The words "First Year" are very relevant. The total area (P) which includes under all items (A) and (B) to be given is 2,13,147 sq. feet.

"It is obvious that the total area is to be given from the First Year'' itself.

If for some reason, the total area cannot be given, then there is an alternative of giving an Alternative Area so called "Equivalent Area" in this Annexure. There is also a separate provision of More Area. However, for 'More Area', if asked for, there shall be a separate pro-rata charge. There is, however, no such provision for a separate charge for the 'Alternate Area' provided."

"The Reserve Price fixed can also be an indication, if the above contention is correct. We may also confirm the above from the basis on which the Reserve Price of the Tender was fixed. The total earning from all Areas on the entire Division was earlier around Rs. 7 crore. The Reserve Price fixed (3 times the earlier earnings as per Board's policy i.e. approximately Rs. 21 crore) was taken irrespective of the Areas immediately available. The yearly increase in the valuation is 10%, 15%, 20%, 25% percent etc. each year is not linked to the different Areas to be made available to the party year after year. Hence, it was envisaged that because of sites under running Contracts; the total Area can only be given if an "Equivalent Area" is given as an alternative. Then only would the total valuation of the contract be justified".

"It is, therefore, obvious that there was every intention of the Division to provide the total Area for the full period of the contract, right from the first year, and as some of the Areas were not immediately available due to running contracts, there was a provision of giving an alternative area on equivalent basis (equivalent area)".”

(xviii)

Reliance was also placed by the learned Arbitrator, on the following passage from the subsequent communication dated 29th August, 2007, from the CCM to the DRM, Delhi Division:

“Clause 16 of the Agreement provides that "Amount quoted in packet B will be applicable for total advertising area assessed by the Railways" (the wordings-"part thereof” - is to identify 10% Area for Railway Slogans etc. as per Clause 15). This total Area is, as mentioned above 2,13,147 sq. ft. The amount quoted in Packet 'B' in the Tender of this contract is for the total area it would be less for a lesser area. The obvious conclusion is that if the same amount of the Advertising Area, as assessed by the Railways, and mentioned in the "Tender Documents" cannot be given (or an equivalent area thereof cannot be provided by the Railways), the amount quoted in packet 'B' should be correspondingly reduced.”

Thus, holds the learned Arbitrator, the Agreement envisaged grant of sole rights, to PPC, to advertise at the various sites in the Delhi Division, during the period of the contract, i.e. 20th September, 2007 to 19th September, 2012. A conjoint reading of Clauses 1 and 2 of the Agreement indicated that, during this period of five years, PPC would enjoy sole advertising rights in respect of the Delhi Division over an area of 213417 sq. ft. This assurance, under the agreement, noted the learned arbitrator, was belied, inasmuch as it was only on 13th April, 2010, when the last of the sites envisaged in part A of Section V of the tender documents was made available to PPC, consequent on the expiry of the pre-existing contract in respect of the said sites. Sole rights over the area of 213417 sq. ft were, therefore, made available to PPC only on or after 13th April, 2010. The consideration of ₹ 22,85,85,500/- envisaged by the tender documents and the agreement as being payable by PPC for the first year of the contract being relatable to availability, during that year, to PPC of 213417 sq. ft. of the advertising area, the learned arbitrator held that, to the extent the area made available to PPC during that year shall short of 213417 sq. ft., PPC was entitled to refund of proportionate advance license fee paid by it.

(xix)

Similar entitlement would ensue, in PPC‟s favour, during the second and the third years of the contract.

(xx)

On the aforesaid reasoning, the learned arbitrator held that

(a)

there was a contractual obligation, on the Railways, to provide, to PPC, 213417 sq. ft. of advertising year during the first year,

(b)

to the extent the available advertising space fell short of these figures, the Railways were bound to make available, to PPC the equivalent alternate area at no extra costs and

(c)

in default, the Railways were bound to refund, to PPC, the proportionate advance license fee paid by PPC to the Railways.

(xxi)

The learned Arbitrator also rejected the submission of the Railways, that before being entitled to equivalent alternate space, PPC was required to make a requisition in that regard to the Railways. On facts, the learned arbitrator found that, apart from the fact that no such request was made by the Railways to PPC, PPC had, on the other hand, addressed several communications to the Railways for being provided the entire area of 213417 sq. ft.

(xxii)

PPC had also contended, before the learned arbitrator, that seven of the sites, contained in Part A of Section V of the tender documents, were already contracted to PPC, and that the contracts were in existence on the date of the present “sole rights” agreement. It was, therefore, sought to be contended that in respect of these seven sites, the Railways had recovered fee twice over from PCC.

(xxiii)

The learned arbitrator observed that, in its letters dated 26th February, 2010 and 6th March, 2010, addressed to the learned arbitrator, the Railways had acknowledged thus:

“Find herewith the list of sites, out of location enlisted in Section “V” of Tender documents, that ran parallel to the Sole Rights contract for commercial publicity over entire Delhi division. The list contains details of the contract viz the allotted rate (i.e rate for first year), their per year revised rates for subsequent years or the pro rata tariff, number of days a contract ran parallel to Sole Right Contract (per year wise) the accrual of annual amount on pro rata basis for the days calculated thereof and the total accrued earnings out of these parallel running contract till their respective expiry from the start of the Sole Rights contract i.e. 20.9.2007 & till 31.12. 2009 …..The copies of their respective Agreements were also enclosed ...... there is no scope of any rectification ...... and these may be taken on record on as is basis.”

(xxiv)

From the statement provided by the Railways, the proportionate advance license fee, paid by PPC under the Sole Rights Agreement, which would overlap with the periods during which the earlier contracts between the Railways and PPC continued to remain in existence after the date of commencement of the present agreement, stands tabulated thus, in the impugned award:

S.No.Tender S.No. (Super-imposed)Item/Site/group of sitesOverlapping period (from MCD of Sole right contract to expiry date of pre-existing contractProportionate license fee accrued in pre-existing contracts (in Rs.) based on Respondent statement) (6.3.2010)
138NDLS(CA)20.09.07 to 1.2.0832,91,200
241Delhi Jn Overhead signage20.09.07 to 3.10.0718,896
348NZM overhead signage20.09.07 to 3.10.0713,724
456BP Zone I20.09.07 to 13.09.091,53,89,452
557BP Zone III20.09.07 to 30.09.091,27,51,260
658BP Zone IV20.09.07 to 30.09.091,46,42,808
759BP Zone V20.09.07 to 30.09.091,35,38,966
(xxv)

As a result of the afore-noted discussion, the learned arbitrator held PPC to be entitled, in respect of the seven sites for which pre-existing contracts with PPC itself were in operation on the date of commencement of the contract in the present case, to a refund of ₹ 4,11,78,730/- and, in respect of the remaining 34 sites in Part A of Section V of the tender documents, to a refund of ₹ 4,31,87,700 /-.

Submissions on behalf of the Railways:

28.

Disputing the entitlement of the PPC to the awarded amounts of ₹ 4,11,78,730/- and ₹ 4,31,87,700/-, the Railways have submitted before this Court through Dr. Sarabjeet Sharma, learned Counsel, thus:

(i)

Part A of Section V of the tender documents made it clear that the 41 sites enlisted therein would not be made available to PPC at the commencement of the contract, and would become available only on future dates, consequent on the pre-existing contracts, in respect of the said sites, coming to an end. The learned arbitrator could not, therefore, have held that PPC was entitled to be provided 217417 sq. ft. of advertising area from the commencement of the contract during the entire five year period. The area, which was contractually made available to PPC during the entire five years, was the area covered by Part B of the contract.

(ii)

This position was made apparent by the Note in Section V of the tender documents. A reading of the said Note made it apparent that the entitlement of PPC to equivalent/more area was to be in accordance with Para 4.9 of Section II of the tender documents, which required an advance requisition, in that regard, to be made by PPC, upon which the area would be provided on additional payment at pro rata basis.

(iii)

Internal notings of the CCM, which were contrary to the terms of the tender documents and the contract, could not take precedents over the provisions of the contract and the tender documents, to which they were contrary.

(iv)

Reliance was also placed, by Dr. Sharma, on Clause 5 of the Agreement, which provided that ownership of existing contracts would pass on to PPC only consequent on expiry of pre-existing contracts.

Analysis

29.

Having examined, in detail, the documents as well as the findings of the learned arbitrator regarding the issues in controversy and the contentions of Dr. Sharma, I do not find any reason to interfere with the ultimate decision of the learned arbitrator, insofar as the impugned award is concerned.

30.

The learned arbitrator has examined the clauses of the contract and taken a view thereon by harmonizing, as he thought it appropriate, the various clauses. He has taken into account the opening clauses of the agreement, Clauses 4, 9 and 16 of the Agreement and Section V as well as the Note incorporated in the tender documents. Following a process of ratiocination which is unquestionably detailed and well considered, he has interpreted the various clauses as entitling PPC, ab initio, to 213417 sq. ft. of advertising area during the first year. He has also held that, in the event of any part of the said area not being available, the Railways were required to provide equivalent area at no extra cost and, in default, were required to refund, proportionately, the advance license fee paid by PPC.

31.

The law, regarding the scope of interference, by the Court, under Section 34 of the 1996 Act, is trite and well settled, progressing and developing, as it has, through the decisions of the Supreme Court in Associate Builders v. DDA1, Ssangyong Engineering & Constructions Co. Ltd. v. NHAI2 and Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation Ltd.3, among others.

32.

The offshoot of the above decisions is that, ordinarily, the Court, exercising jurisdiction under Section 34 of the 1996 Act, would not interfere with in the manner in which the Arbitral Tribunal has interpreted the contractual covenants. Having said that, when the interpretation placed by the arbitrator is clearly unreasonable, or contrary to the covenants of the contract read as a whole, or results in disharmony among the various clauses of the contract, the Court may interfere.4 Equally, the Court may interfere and enunciate what, in its view, is the correct legal position, where the same covenants of the contract have been interpreted differently by two arbitral awards in similar circumstances, as held in NHAI v. Progressive MVR (JV)5.

33.

In the present case, the submissions advanced by the Railways to challenge the impugned award are themselves indicative of the reason why the impugned award does not brook interference. The issue in controversy may be vivisected into three parts.

Was PPC entitled to 213147 sq ft of advertising area, ab initio?

34.

The first submission of Dr. Sharma; indeed, his main contention, is that Section V of the Tender Documents made it clear that the sites mentioned in Part A of Section V would be made available only on future dates, with some of the dates being mentioned in Part A of Section V itself and the remaining dates being provided in the letter of allotment dated 24th August, 2007 (except for two sites). As such, Dr. Sharma sought to contend that the learned arbitrator erred, and ruled contrary to the contractual covenants, in holding that PPC was entitled, ab initio, to be provided 213417 sq. ft. of advertising area.

35.

This submission of Dr. Sharma confuses and conflates the concepts of “site” and “area”. The learned arbitrator has, on the other hand, remained alive to the distinction between these two contractual concepts. The very opening recitals in the agreement reveal that the area to be made available to PPC during the first year was 213417 sq. ft. There is not a single covenant, to be found anywhere either in the tender documents or in the agreement, which derogates from this express stipulation. It is clear, unequivocal and non-negotiable. To reiterate, PPC was entitled, ab initio, and during the entire term of the contract to be provided 213417 sq. ft of advertising area.

36.

What Section V and the Note in Section V says, apropos Part A the sites mentioned in Part A thereof, is that would be made available only on future dates, as they were already being operated by other contractors, under pre-existing contracts. This is exactly what Clause 16 of the Agreement states as well. What is stated in Section V, the Note in Section V as well as in Clause 16 is, therefore, only that, qua the sites which were already being operated by other contractors, under pre-existing contracts, PPC would acquire advertising rights only consequent on the expiry of the said contracts.

37.

The learned arbitrator has correctly held that this stipulation cannot be treated as derogating, in any fashion, from the obligation, expressly envisaged in the opening recitals of the Agreement between the PPC and the Railways as well as in the tender documents, that PPC would be entitled, ab initio, to 213417 sq. ft. of advertising area. The fact that certain sites would, per contract, become available to PPC only in future would not detract from the requirement of providing, to PPC, 213147 sq ft of advertising area throughout the contract. Any other interpretation would render the express stipulation, in the Agreement as well as in the Tender Documents, that the area made available to PPC for advertising, during the period of contract i.e. 20th September, 2007 to 19th September, 2012, was 213147 sq ft, redundant. It is not permissible, while interpreting the covenants in a contract, so accord, to one clause, an interpretation which would render another redundant or otiose.

38.

I, therefore, find no reason whatsoever to interfere with the findings of the learned arbitrator, that 213417 sq. ft of advertising area was required to be made available to PPC during the entire period of contract.

Was PPC entitled to be provided „equivalent area‟ at no extra cost?

39.

The second aspect is regarding whether PPC would be entitled, in the event of any part of the said 213417 sq. ft of advertising area not being available, to be provided equivalent area, at no extract cost. The learned arbitrator interpreted the Note in Section V to mean as requiring advertising area, equivalent to the area in Part A of Section V, which was not immediately available to PPC, as being required to be provided by the Railways at no extra cost.

40.

On the interpretation of the Note in Section V, to this limited extent, I do not find myself entirely in agreement with the findings of the learned arbitrator. The learned arbitrator has adopted the view that the Note in Section V of the tender documents entitled PPC to equivalent area, to compensate for the area which was not immediately available for advertising, at no extra cost. I am unable to read the Note in such a fashion.

41.

The Note in Section V consists of two sentences. The first sentence states that the exact locations indicated in Part A of Section V would be made over to PPC w.e.f. the date reflected against such location. This, as I have already held, merely indicates that in respect of locations/sites, which were being operated by contractors with whom pre-existing contracts were still continuing, the right of PPC is emerged only after the said contracts came to an end. That did not derogate, from the obligation, of the Railways, to provide, to PPC, ab initio and during the entire term of the contract, 213417 sq. ft. of advertising area.

42.

The second sentence of the Note of Section V, however, in my view, has not been correctly interpreted by the learned arbitrator and, in fact, the interpretation placed by the learned arbitrator on the said sentence flies directly in the face only of the said sentence but also of Clause 4.9 of Section II of the tender documents. What is stated, in the second sentence in the Note in Section V, is that “the contractor (i.e. PPC) would be at liberty to display equivalent/more area at adjoining locations in accordance with para 4.9 of Section II of the tender documents”. Clearly, therefore, the entitlement of the contractor to additional/more area, under the second sentence in the Note in Section V was only in accordance with Clause 4.9 of Section II of the tender documents, and could not be understood de hors the said clause. Clause 4.9 of Section II of the tender documents permits grant of additional area to a contractor only on payment of additional fee and not free of charge. In holding that PPC would be entitled, by virtue of the Note in Section V, to advertising area, equivalent to the area, which was covered by pre-existing contracts, at no extra cost, therefore, in my view, the learned arbitrator held contrary to the expressed terms of Clause 4.9 of Section II of the tender documents, which have been incorporated by reference in the Note in Section V.

43.

Where the provisions of a clause are incorporated by reference into another, they are to be treated as bodily incorporated into the latter, as held in, inter alia, M. R. Engineers and Contractors Pvt. Ltd. v. Som Datt Builders Ltd.6

44.

I cannot, therefore, agree with the findings of the learned arbitrator, that PPC was entitled to be provided advertising area, equivalent to the area which was covered by the sites enumerated in Part A of Section V and which could not be provided to PPC owing to the continuance of pre-existing contracts covering the said sites. No such right to be provided equivalent area free of cost, in my view, can be gleaned from the tender documents.

Was PPC entitled to be refunded advance licence fee deposited by it, proportionate to the advertising area not made available?

45.

That, however, does not detract from the entitlement, of PPC, to be refunded the advance license fee deposited by it, proportionate to the area which was not made available to PPC. In view of my concurring, with the learned arbitrator, that the stipulation in the tender documents as well as the contract required the Railways to provide, during the entire period of contract, 213417 sq. ft of advertising area, to PPC, I can find no fault with the learned arbitrator, in his decision that, to the extent that the said area was not provided to PPC, PPC would be entitled to a refund. The Railways cannot be permitted to continue to retain the entire advance licence fee deposited by PPC, even while breaching the contractual obligation to make available, to PPC, the entire area of 213417 sq ft of advertising area. That, as the learned Arbitrator correctly holds, would amount to unjust enrichment.

46.

I, therefore, approve and concur with the decision of the learned Arbitrator that PPC is entitled to refund of Rs 8,43,66,430/-.

47.

The Railways have also challenged the award, by the learned arbitrator, of interest in favour of PPC. The learned arbitrator has granted interest, on the amounts awarded by Interim Awards- I, II and III, pre-reference and pendente lite @ 2% per month and post award @ 1.5 % per month. In doing so, the learned arbitrator has relied on the judgments of the Supreme Court in Central Bank of India v. Ravindra7, Bhagwati Oxygen Ltd. v. Hindustan Copper Ltd.8 and State of Rajasthan v. Nav Bharat Construction Co.9.

48.

No separate arguments were advanced by Dr. Sharma in respect of the award of interest. Nor do the written submissions filed by the Railways contest the award of interest by the learned arbitrator. However, in O.M.P. (COMM) 154/2020, the Railways have sought to contend that the agreement and tender conditions did not envisage grant of interest to PPC.

49.

The provision relating to grant of interest on delayed payment by PPC has, contends the Railways, been erroneously applied, by the learned arbitrator to award interest to PPC, at an exorbitant rate.

50.

Both arguments stand covered against the Railways by authoritative pronouncementS of the Supreme Court. The judgment in Bhagwati Oxygen8 clearly holds that, in the absence of any proscription, in the agreement between the parties, against award of interest by the arbitrator, the arbitrator was within his jurisdiction to award interest pre-reference, pendente lite as well as post-award. Insofar as the rate of interest is concerned, the learned arbitrator has 8, noted that, in Bhagwati Oxygen the Supreme Court upheld the award of interest, by the arbitrator, at 18% p.a. – incidentally, the same rate of interest at which the learned arbitrator has awarded interest in the present case, observing that, in this regard, the rate of interest charged by Hindustan Cooper Ltd. (the respondent in that case), to Bhagwati Oxygen was a relevant and germane factor. Applying this principle, the learned arbitrator has awarded interest, on the claims decided in favour of the PPC, at the rates at which the PPC was liable to pay interest in the event of delayed payments made to the Railways.

51.

No interference is, therefore, justified, with the said decision.

Conclusion

52.

In view thereof, the challenge, by the Railways, to the impugned award dated 29th October, 2012 of the learned arbitrator, fails.

53.

The petition of the Railways is, accordingly, dismissed, with no order as to costs.

OMP (ENF.) (COMM.) 120/2018

54.

This petition seeks enforcement of the Interim Award-I dated 19th May, 2010, Interim Award-II dated 1st November, 2010 and Interim Award-III dated 29th October, 2012, passed by the learned Arbitrator, and, therefore, seeks a direction to the Railways, to pay, to PPC, the amount awarded by the learned arbitrator.

55.

No separate submissions were advanced, by Dr. Sharma, assailing this petition. The reply filed by the Railways in response to this petition merely seeks to contend that, having allowed adjustment of the amounts awarded by Interim Awards-I and II, without claiming interest, the PPC was estopped from claiming interest now.

56.

As PPC has correctly contended in its rejoinder, this submission of the Railways is misconceived. Interim Awards-I and II expressly resolve the decision on the issue of interest payable on the amounts awarded under the said Interim Awards to be decided while adjudicating on Interim Award-III. As such, there was no waiver or abandonment, by PPC, of its right to interest on the amounts awarded; the issue of payment of interest was only deferred till the passing of the impugned Interim Award-III.

57.

In that view of the matter, Interim Award-III having been upheld in its entirety, the Railways become liable to pay, to the petitioner, the principal amount as well as interest.

58.

OMP (COMM.) 154/2020 having been decided by the judgment passed today, for the present, in OMP (ENF.) (COMM.) 120/2018, the Railways are directed to deposit, with the Registrar General of this Court, the entire amount awarded by the learned arbitrator, including principal and interest by way of a crossed cheque/demand draft within a period of four weeks from the date of uploading of this judgement on the website of this Court.

59.

List OMP (ENF.) (COMM.) 120/2018 before the concerned Bench, as per roster, on 15th July, 2022 to proceed further with the said enforcement petition and pass appropriate orders thereon.

Footnotes

  1. 1.(2015) 3 SCC 49
  2. 2.(2019) 15 SCC 131
  3. 3.(2022) 1 SCC 131
  4. 4.Refer South East Asia Marine Engineering and Constructions Ltd. v. Oil India Ltd. (2020) 5 SCC 164 & State of Rajasthan v. Nav Bharat Construction Co. (2006) 1 SCC 86
  5. 5.(2018) 14 SCC 688
  6. 6.(2009) 7 SCC 696
  7. 7.2002 (1) SCC 367
  8. 8.2005 (6) SCC 462
  9. 9.2002 (1) SCC 659