High CourtsSingle Bench(2007) 10 MAD CK 0034

Garware-Wall Ropes Ltd. vs The State of Tamil Nadu Kassim Nets Vs The Secretary to Government, Department of Animal Husbandry, Dairying and Fisheries, The Director of Fisheries and The Special Commissioner of Fisheries, Government of Tamil Nadu

Madras High Court · Decided on 12 October 2007

HON’BLE JUDGES
V. Dhanapalan, J
RESULT
Dismissed
CASE NUMBER
Writ Petition No''s. 27258, 28827 and 28485 of 2007 and M.P. No''s. 1 and 2 of 2007 in 28827 of 2007 and M.P. No. 1 of 2007 in Writ Petition No. 27258 of 2007 and M.P. No''s. 1 to 4 of 2007 in Writ Petition No. 28485 of 2007

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

1,199 paragraphs · 23,021 words

V. Dhanapalan, J.—The prayer in Writ Petition No. 28827 of 2007 filed by M/s. Garware-Wall Ropes Ltd. is for issuance of a Writ of

Certiorarified Mandamus, to call for the records in connection with Re-Tender Notification issued by the respondents dated 21.8.2007 and earlier

Tender Notification dated 25.4.2007 and quash the Notification dated 21.8.2007 and consequently direct the respondents to pursue the Tender

Notification dated 25.4.2007 in the matter of manufacture and supply of webbings to fishermen affected by Tsunami.

2.

According to the petitioner in W.P. No. 28827 of 2007, it is a Company registered under the Companies Act, engaged inter-alia in the

manufacture and supply of synthetic ropes, twines, yarn, nettings/webbings (including fishing nets), woven fabric and geo-synthetic products. It is a

Company which is the third largest manufacturer of synthetic cordage in the world and the largest in India. It has been awarded the Star Export

House status by the Ministry of Commerce, Government of India, besides ISO:9001:2000 accreditation. They have not only a strong domestic

performance, but are predominant in the field of export market also. The petitioner-Company is specialised in providing application-based specials

for fishing, shipping and oil exportation industries. The petitioner has a very big factory with more than 110 machines, which can be put to use for

the manufacture and supply of webbings for bulk quantities.

3.

The respondents herein have issued a Tender Notification on 21.12.2006 inviting tenders from manufacturers of webbings, who have a capacity

of 1250 Metric Tonnes (for short, Metric Tonnes as ""MT"") of supply to supply 1100 MT of webbings, as per the specification and the terms and

conditions referred to in the Tender Notification. In terms of the specifications mentioned in Tender Notification, the successful tenderers were

required to supply 1100 MT knotted nylon webbings to the fishermen of the Tamil Nadu. The tenderers were required to pay an EMD of Rs. 44

lakhs.

4.

The petitioner being a major company, having annual production capacity of more than 1250 MT, submitted their tenders with all the relevant

documents and proofs on 4.1.2007. In terms of the tender conditions, the tenders were opened on 8.1.2007. All the tenders submitted before the

prescribed time, were verified so as to examine whether they were qualified on technical grounds. The petitioners have all their qualifications and it

is understood that the bids were found technically qualified. Thereafter on 7.2.2007, a Committee constituted by the Director of Fisheries,

inspected the petitioner''s factory so as to ascertain the availability of infrastructural facilities and machineries and also to verify the manufacturing

capacity of the petitioner-Company (hereinafter referred to as ''the Company''). The Committee comprised of an official of the Fisheries Survey of

India (Government of India) and two State Government officials. On inspection, the Committee was fully satisfied with the manufacturing capacity

and the infrastructure of the Company, for the required supply of webbings. Thereafter, on 10.4.2007, the price bids of the Company were

opened. According to them, the petitioner-Company was the only Company which was technically qualified. After opening the price bids, the

Company was called for negotiations and there were four rounds of negotiations and in which, the price quoted was reduced by the petitioner-

Company to some extent. While that being the position, on 13.4.2007, the Tender Awarding Committee rejected the tenders on the ground that

there does not exist Bureau of Indian Standards (hereinafter referred to as ''the BIS'') for webbings, a condition stipulated in the tender. It is the

case of the Company that in this context, while submitting the bid by the petitioner, they had pointed out/clarified on this that the nylon multi filament

nettings will be made from the twine conforming to IS-4401. However since there is no BIS Standard for nylon mono filament yarn and nylon

mono filament webbings as well as nylon multi filament webbings, these will not be covered by any BIS specifications.

5.

Thereafter, a fresh Tender Notification was issued by the respondents on 25.4.2007 for the manufacture and supply of 1100 MT of webbings,

and by that Notification, the required capacity of tenderers was reduced to 600 MT as against 1250 MT stipulated in the earlier Tender. The

petitioner again submitted their tenders on 28.5.2007 with all relevant documents and proofs, as it was the last date for receipt of the tenders. The

respondents opened the technical bids of the tenderers on the said date. After evaluation, samples were called for from the petitioner-Company for

technical evaluation and approval. Accordingly, they submitted their samples and on 25.7.2007, an inspection was directed to be carried out by

the Committee comprising of official of the Fishers Development Corporation, the District Revenue Officer and an Accounts Officer constituted by

the Director of Fisheries. The Company made available to the said Committee all the infrastructural facilities, machineries etc. The Director of

Fisheries then called for an informal meeting with the Company on 9.8.2007 and the Company was shocked to know at the said meeting that the

report of the Inspection Committee had indicated that the Company''s production capacity was shown to be less than 600 MT/p.a. Therefore, the

Company addressed to the third respondent on the subject matter on 10.8.2007 clarifying the factual position on production capacity as well as

the delivery capacity. It was surprising and ununderstandable as to how the Company which had already been found to have a capacity of more

than 1250 MT while evaluating the earlier tender, has suddenly been found to have a capacity of only about 450 MT and therefore, the Company

sent a notice on 11.8.2007 requesting the respondents to give them an opportunity to explain regarding their manufacturing capacity.

6.

While so, the Company was shocked to know that the respondents have issued a Re-Tender Notification on 21.8.2007 inviting the tenders for

supply of the same quantity of 1100 MT of webbings by reducing the production capacity of the tenderers to 100 MT. According to them, the Re-

Tender Notification was issued with a reduced capacity from the manufacturers having a capacity of 100 MT, apparently on the premise that there

are no manufacturers including the petitioner-Company which has the capacity to manufacture 600 MT webbings, as contained in the earlier

Notification. Therefore, the action of the respondents in abandoning the earlier Tender Notification and issuing the Re-Tender Notification is wholly

illegal and proceeds on a misconception of facts and law, as also violative of the provisions of the (in short ""the Act"") and the petitioner, having no

other effective alternative remedy, has approached this Court for the above stated relief.

7.

The main grounds urged by the petitioner is that the decision of the respondents in coming to the conclusion that the petitioner''s annual capacity

is less than 600 MT, and therefore do not qualify for the re-tender issued in April 2007, is vitiated by non-application of mind and extraneous

consideration. The first Tender Notification in December 2006 has been scrapped on account of a mistake relating to BIS specification. The Re-

Tender issued in April 2007 was again for the supply of 1100 MT of webbings, in which the annual capacity of the tenderers was to be 600 MT.

When the petitioner is having a capacity of more than 1250 MT in the first tender, it cannot be said to be not possessing the qualification specified

in the second tender, but having inspected the factory of the petitioner, the Committee has not sent the details of the inspection or the report had

not been furnished to the petitioner. Therefore, the decision of the respondents appears to have been taken on the basis of the report of the said

Committee, a copy of which has not been furnished to the petitioner. The decision of the respondents cannot but be construed as arbitrary and

irrational.

8.

The Re-Tender Notification dated 21.8.2007 is again for the supply of 1100 MT. The production capacity of the tenderers has been reduced to

100 MT. On the facts stated by the petitioner, the fact pertaining to the petitioner''s capacity in the impugned Re-Tender Notification, by which the

production capacity of the tenderers has been reduced to 100 MT, smacks of irrationality and unreasonableness and there is no reason how with

such low production capacity could cater to the annual need of 1100 MT webbings to be supplied to the fishermen affected by the Tsunami.

Therefore, the Re-Tender Notification is vitiated by non-application of mind and arbitrariness and violative of Article 14 of the Constitution of

India.

9.

The decision taken by the respondents on 10.8.2007 is inconsistent with the earlier views of the respondents. Even though there was a

representation by the petitioner requesting them for a personal hearing to submit the materials to show their production capacity is more than 1200

MT, which was not taken into consideration and therefore, the inaction on the part of the respondents to consider the same and the decision to

issue the Re-Tender Notification, is wholly arbitrary and unreasonable.

10.

The right to reject all tenders and call for a re-tender is not an absolute right and the respondents should have valid and justifying reasons to do

so. In the petitioner''s case, the rejection of the second Tender floated in April 2007 seems to be a wrong premise, as the petitioner was not

qualified, which is non-est both on facts and in law. The true decision of the respondents to issue Re-tender Notification deserves to be set aside

both for the reason that it is based on non-existent fact and also causing serious prejudice and stigma on the petitioner.

11.

For the above reasons, the petitioner has approached for the relief to call for the records in connection with the Re-Tender Notification dated

21.8.2007 and the earlier Tender Notification dated 25.4.2007 and seeking to quash the Re-Tender Notification dated 21.8.2007 and for a

consequential direction to the respondents to pursue the Tender Notification dated 25.4.2007 in the matter of manufacture and supply of webbings

to fishermen affected by Tsunami.

12.

The first respondent has filed a counter affidavit for himself as well as on behalf of the other respondents. On behalf of the first respondent, the

Special Commissioner and Secretary to Government, Animal Husbandry, Dairying and Fisheries Department has filed the counter affidavit. The

respondents question the maintainability of this Writ Petition in law, as the issue under consideration falls in the realm of contract. According to the

respondents, it is settled law that in matters of awarding contract, which is essentially a commercial transaction, the State Government is entitled to

choose its own method and arrive at appropriate decision. The Government has the freedom of contract by taking its own decision and the scope

of judicial review of such decision-making process is severely circumscribed and restricted, especially when the State has taken the decision to go

in for a re-tender motivated by paramount public interest. According to the respondents, the Tsunami which hit the Tamil Nadu coast on

26.12.2004, caused damages to the life and fishing implements of the fishermen in the entire coastal districts of Tamil Nadu. The Government

sanctioned various relief schemes as rehabilitation measure to the fishermen community for repairing their nets and for replacing fully damaged/lost

fishing implements. About 42,000 fishermen were given relief assistance sanctioned under various Government orders. The Government in G.O.

No. 532, Revenue Department, dated 14.8.2006, and in Letter No. 32132/Revenue, dated 22.11.2006, sanctioned a sum of Rs. 110.36 crores

for the purchase and supply of following assistance under the Rajiv Gandhi Rehabilitation Package:

(i) Nets (webbings) : 1100 MT

(ii) Handy Rechargeable Lanterns

(iii) Heavy duty bicycles

(iv) Life jackets

(v) Insulated Ice boxes.

Further, the Government, among other things, has allocated a sum of Rs. 44 crores out of the total sanction of Rs. 110.36 crores for the supply of

nets (webbings) to the already benefited Tsunami affected fishermen under the above package. The total loss of nets, due to Tsunami, according to

the actual assessment, was 1,100 MTS and it was therefore proposed to purchase and supply 25 Kgs. of Gill Nets worth about Rs. 10,000/- to

each beneficiary.

13.

The Government also in G.O.Ms. No. 193, Animal Husbandry, Dairying and Fisheries Department, dated 22.11.2006, issued orders

constituting Technical Committees, Scrutinizing Committees, Award Committee for processing the tenders for the above commodities. The

Committees constituted for purchase of nets are as follows:

Sl. No. Name of the Committee Members of the Committee

1 Tender Technical Committee

1.

Spl. Commissioner of Fisheries - Chairman

2.

Director of his representative from CIFNET - Member

3.

Zonal Director or his representative of FSI, Chennai - Member

4.

Joint Director of Fisheries (Marine) Member Secretary

2 Tender Scrutinizing Committee

1.

Spl. Commissioner of Fisheries - Chairman

2.

Joint Director of Fisheries (Marine, Inland & Research) - Members

3.

Accounts Officer (Fisheries) - Member

4.

Deputy Director of Fisheries (Marine) - Member Secretary

3 Tender Award Committee

1.

Secretary to Government, AHD & F Dept - Chairman

2.

Secretary to Government, Finance Department or his/her

nominee - Member

3.

The Director of Fisheries - Member Secretary

The Tender Technical Committee suggested the following specifications for the knotted nylon webbings for the gill nets to be purchased with

suitable mesh size:

Knotted Gill Nets (only webbings) approved by BIS with the following specifications:

Sl. No. Type of material Twine size Stretched Mesh size in mm

1 Nylon Multifilament 210 d x 1 x 2 30

2 Nylon Monofilament 0.16 mm dia 27

3 Nylon Monofilament 0.16 mm dia 36

4 Nylon Multifilament 210 d x 1 x 2 36

5 Nylon Monofilament 0.23 mm dia 56

6 Nylon Multifilament 210 d x 1 x 3 56

The Committee also recommended that nets with BIS specifications may be purchased. Based on the recommendations of the Committee, tenders

for the purchase of all five components mentioned above including the nets were called for. The Tender Notice was published in the leading dailies

and the tenders were invited only from the manufacturers of nets (webbings) with a production capacity of not less than 1250 MT/p.a of the above

specifications. The EMD for the tender was fixed as Rs. 44 lakhs. Two cover system was adopted and the tender document was based on the Act

and the Tamil Nadu Transparency in Tenders Rules, 2000 (in short ""the Rules"").

14.

The last date for receipt of tenders was upto 3.00 p.m. on 4.12.2007. Eleven tenders were purchased and only four tenders were received

and respondents have taken all possible steps to process the tender as per the procedure laid down in Tender Transparency Act, 1998 and as per

the conditions mentioned in the tender document. The tenders were opened at 4.00 p.m. on 5.1.2007. Only the first cover, viz., technical bid was

opened. The technical bids were evaluated by the Tender Scrutinizing Committee on 22.1.2007 and only one tenderer viz. M/s.Garware Wall

Ropes Limited was found technically qualified. The other three tenders, namely M/s. Kassim Nets, Nagercoil, M/s. Nirmala Monofil Pvt. Ltd.,

Coimbatore and M/s. Raj Nylon Exports, Chennai-28, were rejected on technical grounds.

15.

It is the further case of the respondents that net manufacturing plant of the petitioner-Company was inspected on 7.2.2007 and based on the

recommendations of the Tender Scrutinizing Committee on the evaluation of the Inspection Report, samples of all the webbings of the

specifications mentioned in the tender document were obtained from the firm and sent to CIPET for testing on 20.2.2007. The test report on the

samples was received from CIPET on 9.3.2007 and the same was evaluated by the Tender Scrutinizing Committee on 12.3.2007. The Committee

recommended to conduct breaking load test of the samples as per the BIS specification by CIPET. Test report on breaking load was received

from CIPET on 23.3.2007 and the same was evaluated by the Scrutinizing Committee on 3.4.2007 and based on the recommendations of the

Committee, the price bid of the technically qualified tenderer was opened on 4.4.2007 and negotiation of rates was done with the tenderer on

10.4.2007.

16.

On the recommendations of the Tender Scrutinizing Committee, technical bids and price bids were placed before the Tender Award

Committee meeting for taking a decision on 12.4.2007. The Tender Award Committee took note of the information given by the Scientists

(Experts) from CIFT, Cochin, CIPET, Chennai, stating that there were no BIS specifications for webbings, unlike twines. However, BIS test

procedures are available for both webbings and twines. Since BIS specifications were not prescribed for webbings, the technical requirements

under this tender cannot be evaluated. In view of the above facts, the Award Committee asked to go for re-tender. The tender was therefore

cancelled and the EMD was returned to the tenderers on 25.4.2007. Thereafter, the Tender Award Committee instructed a re-tender should be

called for the purchase of 1100 MT of nets and the same was done with the following modifications:

1.

Tenders were invited from the manufacturers of nets (webbings) only with a production capacity of not less than 600 MT per annum of the

specifications mentioned above (The Twine size in Sl. No. 5 Nylon Monofilament was changed as 0.24 mm. dia instead of 0.23 mm dia).

2.

BIS specifications were given in the tender document as follows:

. Nylon webbings should be made up of Nylon twines/monofilament yarn of BIS specifications (i.e.)

Nylon multifilament (Twine): IS 4401 : 2006

Nylon monofilament : IS 7533 : 2003

. The webbing should be made up of virgin Polyamide (Nylon) twine/yarn.

. Recycled raw material (Nylon) should not be used for making webbings.

3.

The Tender Scrutinizing Committee recommended to fix the production capacity as 600 MTs/annum in view of the fact that only one responsive

bid was received for the first tender in which the production capacity was fixed as 1250 MTs/annum and also considering the uniqueness of the

purchase in terms of volume which needs to be supplied within one year.

Accordingly, the tender notice dated 25.4.2007 inviting tenders were published in leading dailies and the last date for receipt of tenders was fixed

as 3.00 p.m. on 28.5.2007. Totally, three tenders were received as follows:

(i) M/s. Garware Wall Ropes Pvt. Ltd., Pune.

(ii) M/s. Kassim Nets, Nagercoil.

(iii) M/s. Kumaran Fish Nets Private Ltd., Nagercoil.

The technical bids were opened at 4.00 p.m. on 28.5.2007 and the manufacturing plants of M/s. Kassim Nets, Nagercoil and M/s. Kumaran

Nets, Nagercoil were inspected on 2.6.2007 and 22.6.2007 and the inspection notes and the technical bids were evaluated on 30.5.2007,

11.6.2007 and 22.6.2007. Samples received from the petitioner-Company were sent to CIFT, Cochin on 29.6.2007 for testing to confirm

whether it meets BIS specifications. The test report received from CIFT, Cochin on 11.7.2007 confirmed the same.

17.

While that being the position, a specific complaint against the production capacity of the petitioner-Company was received, and it was decided

by the Tender Scrutinizing Committee on 24.7.2007 to depute a team of officials to inspect as to whether the petitioner-Company has the

production capacity of its own for the descriptions of the works as specified in the tender. The petitioner-Company was re-inspected from

25.7.2007 to 28.7.2007. The inspection team found that the petitioner-Company did not possess the capacity claimed in the tender document.

Thereafter, the Tender Scrutinizing Committee has evaluated the technical bids, inspection reports of all the tenderers and test reports on the

samples of the petitioner-Company. Since no one was found qualified in the evaluation process by the Tender Scrutinizing Committee, the tenders

of all the three tenderers including the petitioner-Company''s tender, were rejected.

18.

The Tender Scrutinizing Committee in its meeting held on 9.8.2007, has made the following recommendations:

1.

By experience in the previous two tenders, there were no suitable suppliers even after the reduced production quality of 600 MTs/year as

eligibility criteria.

2.

1100 MTs of Nylon webbings have to be distributed to the fishermen within a timeframe of one year.

3.

To ensure better participation in tender and going by the previous experience, that there is no suitable manufacturer with the production capacity

of 1250 MT/annum and 600 MT/annum, the production capacity may be reduced to 100 MT/annum.

4.

The Government may be addressed to permit the third respondent to go for re-tender under fixed rate contract system and to reduce the

production capacity to 100 MTs/annum (60% monofilament : 40% multifilament) of webbings of specified description in the tender and also to

reduce the time limit to 15 days for inviting tenders, since the tender call is for the third time and all the manufacturers were aware of the supply of

webbings to fishermen.

Therefore, the Government was addressed on the above lines in the letter No. 38116/TPIU/07, dated 9.8.2007 by the third respondent and the

Government in Letter No. 16926/FSI/2007-1, dated 17.8.2007 permitted the third respondent to go for re-tender under fixed rate contract

system and to reduce the time limit to 15 days. Therefore, the tenders were cancelled on 17.8.2007. The petitioner''s tender was also cancelled on

17.8.2007-vide third respondent''s letter No. 55055/P1/2007, dated 17.8.2007 and the EMD of Rs. 44 lakhs was returned to the petitioner. As

instructed by the Government in Letter No. 16926/FSIII/2007-1, dated 17.8.2007 to the third respondent, re-tender II was called for the

purchase of 1100 MTs of nets with the following modifications:

(i) Nylon webbings should be made up of Nylon twines/monofilament yarn of BIS specifications (i.e.).

Nylon Multifilament (Twine): IS 4401 : 2006

Nylon Monofilament : IS 7533 : 2003

(ii) The manufacturers shall have their production capacity of webbings in the ratio of 60:40 of monofilament : multifilament respectively.

(iii) The webbing should be made up of virgin Polyamide (Nylon) Twine/Yarn.

(iv) Recycled raw material (Nylon) should not be used for making webbings.

19.

Tender notice inviting re-tenders dated 21.8.2007 was published in the leading dailies and corrigendum was also issued on 23.8.2007. The

eligibility criteria for bidders have been prescribed in the tender notice as follows:

(a) The bidder shall be a registered manufacturer having a minimum individual annual production capacity of 100 MTs of nylon (Polyamide) nets

(Double knotted Nylon webbings) in the ratio of 60% monofilament : 40% multifilament nylon nets (double knotted nylon webbings) of the

specified description in the tender schedule and having experience in the production and marketing of the webbings of the specifications described

in the tender document for a minimum period of three years.

(b) Alliance or agreement of any type with any manufacturer/dealer/distributor dealing with the said nylon webbings like Consortium/lease rent/joint

venture etc. shall be rejected.

(c) The bidders should provide samples in a separate cover of multifilament twines and monofilament yarn for making knotted nylon webbings and

also samples of the webbings of the descriptions specified in the tender document made out of the above indicated twines/yarns along with tender

document.

(d) EMD has been reduced and fixed as Rs. 11 lakhs.

(e) Two cover system will be followed.

(f) Production of production plan has been made mandatory.

Last date for receipt of tenders has been fixed on 6.9.2007 upto 3.00 p.m.

20.

Hence, it is the case of the respondents that in view of the facts stated by the respondents as above, it reveals that there is no mala-fide or

wilful intention on the part of the respondents to cancel the earlier tender and invite fresh tender as notified on 21.8.2007. There is no iota of

evidence to show that the tender process is arbitrary or actuated by malice. The tender was necessitated only due to the ineligibility of the

tenderers and therefore, the re-tender is the only logical conclusion in view of the circumstances stated above.

21.

It is stated by the respondents that the petitioner-Company is having only 106 machines and not 110 machines as contended by the petitioner

for production of nets, and these nets are different from the requirement of the tender. The respondents have not issued any tender notice on

21.12.2006 as contended by the petitioner and the tender dated 4.12.2006 was for the supply of webbings of the specifications mentioned earlier.

This was clearly mentioned that the production capacity specified should be for the specifications mentioned in the tender document. The

contention of the petitioner that the tenders were opened on 8.1.2007 is not correct, but opened on 5.1.2007.

22.

Since the inspection of the manufacturing plant is one of the established methods to evaluate the technical bid, the team of officials as suggested

by the Tender Scrutinizing Committee was deputed to inspect the plant noted in the tender document, i.e. plant at Wai and verify with the details

furnished in the tender document to the field realities. The inspection team has inspected the net manufacturing unit of the petitioner at Wai on

7.2.2007 and 8.2.2007. It is submitted that the writ petitioner has shown in the tender document that the supply of nets as notified in the tender,

will be produced from the machines in the plant at Wai itself. In the tender document, the petitioner has mentioned that the plant at Wai has the

production capacity of 5520 MTs/annum, but these nets are different from the requirements of the tender. The inspection team was provided with

false information with a view to mislead the team so that the team can give a report that the petitioner''s plant at Wai has the capacity to produce

5520 MTs/annum. But by its own admission by way of a signed production plan dated 10.8.2007, the petitioner-Company proved itself that it did

not have the production capacity of 5520 MTs as shown in the tender document. It is proved from the production plan that the petitioner has

submitted that it has only the production capacity of 277.602 MT/annum from its own machines. The petitioner has shown in its first tender

schedule the annual production capacity from its own machines as 5520 MTs and in the first re-tender document as 5520 MTs and at the time of

inspection, 696 MTs by a production plan, which includes its 24 own machines and 29 machines taken on lease. The above details clearly

establish that the petitioner-Company has contradicted its own production capacity which it had furnished in the tender schedule of first tender and

first re-tender and at the time of inspection from 25.7.2007 to 28.7.2007 and the information furnished in the representation dated 10.8.2007. The

petitioner-Company gave false information in the tender document to the inspection team and has now come before this Court with mala-fide

intention of securing the contract with unclean hands. It is surprising to note that the petitioner-Company which claims to be awarded with ""One

Star Export House"" status, by the Ministry of Commerce, Government of India, and having an ""ISO:9001-2000"" accreditation, has suppressed the

real facts, but has come up with the reports of contradicting and false production capacity. No doubt, the petitioner has obtained such star status

for export. But at the same time, the petitioner does not have manufacturing capacity to produce the webbings as specified and described in the

tender document.

23.

It is submitted by the respondents that the team consisting of three officials of (i) a District Revenue Officer (ii) a General Manager with

experience in fishery activities from the Tamil Nadu Fisheries Development Corporation and head of the fish net manufacturing plant, a

Government of Tamil Nadu undertaking and (iii) Technician (not Accounts Officer, as contended by the petitioner) working in fish net

manufacturing plant of Tamil Nadu Fisheries Development Corporation was deputed to inspect the plant. By its own admission, the petitioner-

Company has proved that from the rest of the machines in the factory at Wai, the webbings of the specifications in the tender cannot be produced.

24.

The petitioner proved itself that the petitioner has production capacity around 148 MT/annum from the net (webbings) manufacturing plant at

Wai including the machines of higher pitch which cannot produce the webbings of the specifications given in tender. The petitioner-Company thus

by furnishing false information and by suppressing the fact on real production capacity, tried to mislead the Court with a mala-fide intention to gain

out of the scheme meant for the social cause. It clearly establishes that the petitioner-Company does not possess the production capacity as

mentioned in the tender document. Hence, there is no non-application of mind and there is no place for extraneous consideration as contended by

the petitioner.

25.

It is the case of the respondents that Rule 27 of the Tamil Nadu Transparency in Tenders Rules, 2000 clearly spells out that tender evaluation

process is a confidential one until the award of the contract is notified. In the production plan submitted to the third respondent on 10.8.2007 and

to the inspection team on 25.7.2007, the petitioner-Company has introduced two new elements i.e. ""machines at new location"" i.e. Silvassa and

the machines taken on lease"" that had not been shown in the tender document for the production of webbings of the specifications mentioned in

the tender and re-tender document.

26.

In the counter affidavit, it is further stated that the writ petitioner-Company is shown as its first tender schedule, the annual production capacity

from its own machines a 5520 MTs/annum and in the first re-tender document as 5520 MTs/annum and at the time of inspection by way of

production plan as 148 MTs/annum from its own machines at Wai and 129 MTs/annum from its own machines at Silvassa, putting together its 15

own machines at Wai and 9 own machines at a different location, viz. Silvassa and 29 machines taken on lease. The production capacity as shown

by it out of its own machines in the two locations (Wai and Silvassa) in the signed production plan is 277.602 MT/annum (plants at Wai and

Silvassa). The machines are running at an efficiency of 66% and if this efficiency is taken into account, then the in-house production capacity per

annum of the petitioner-Company is 143.626 MT/annum. The foregoing details clearly establish that the petitioner-Company has contradicted its

own production capacity which it had furnished in the tender schedule of the first tender and first re-tender and at the time of inspection from

25.7.2007 to 28.7.2007 and the information furnished in the representation dated 10.8.2007. Therefore, it is evident that the petitioner-Company

wants to gain out of the contract by producing false information in the tender document. The above details will clearly prove that there is no

arbitrariness. Without having the prescribed production capacity for the webbings of the prescribed specifications in the tender notice, the

petitioner-Company has submitted the tender, stating that it has 5520 MT per annum of nets (webbings) and then giving 696 MT/annum and then

by proving by its own admission in the production plan as 277.602 MT/annum from its own machines. The petitioner has shown in the tender

document, only the net manufacturing plant at Wai and in the Writ Petition, it has shown that 110 machines are there for the production of these

webbings, whereas 106 machines are there in the said plant. But of these 106, by its own admission in the production plan, the production of the

webbings of the specifications in the tender can be done only from 15 machines inclusive of four higher pitch machines. By the petitioner''s own

admission, it proved that the rest of the machineries in the said plant cannot produce the webbings of the said specifications in the tender document.

Therefore, the said action of the petitioner has caused much damage, delay and hardship to the respondents, besides, preventing them from

implementing the welfare schemes meant for the welfare of the downtrodden Tsunami affected fishermen.

27.

Thus, from the foregoing facts stated by the respondents, it is evident that the petitioner-Company did not have the production capacity for the

webbings of the descriptions specified in the tender dated 25.4.2007 and hence, the rejection of the tender of the petitioner-Company is based on

valid grounds. Had the contract been given to the petitioner-Company which did not have the production capacity, the end result would be non-

performance of the contract, which would ultimately affect the already-affected Tsunami fishermen.

28.

It is the further case of the respondents that the law laid down by the Supreme Court in Global Energy Ltd. and Another Vs. Adani Exports

Ltd. and Others, that the terms of the invitation to tender are not open to judicial scrutiny and the Courts cannot whittle down the terms of the

tender as they are in the realm of contract, unless they are wholly arbitrary, discriminatory or actuated by malice. Since the petitioner-Company has

not made out any case, the said decision reported in Global Energy Ltd. and Another Vs. Adani Exports Ltd. and Others, squarely applies and the

Writ Petition is liable to be dismissed.

29.

A reply affidavit was filed by the petitioner-Company reiterating its earlier stand taken in the affidavit filed in support of the writ petition.

30.

Mr. R. Muthukumarasamy, learned Senior Counsel appearing for the petitioner, in his submissions, has strenuously contended that the

petitioner-Company is one of the largest manufacturers of synthetic cordage in the world and one of the largest in India. It has been awarded the

Star Export House status by the Ministry of Commerce, Government of India, besides ISO:9001:2000 accreditation. The learned Senior Counsel

further contended that the petitioner-Company is having a strong domestic performance and are predominant in the field of export market. The

petitioner-Company is specialised in providing application-based specials for fishing, shipping and oil exportation industries. The petitioner has a

very big factory with more than 110 machines, which can be put to use for the manufacture and supply of webbings for bulk quantities. The learned

Senior Counsel stressed on the fact that on 21.12.2006, the tenders were called for the supply of 1100 MT of webbings from the manufacturers

having annual capacity of not less than 1150 MT and the petitioner''s capacity has been ascertained and found to be of 1250 MT or more annually.

While so, the decision of the respondents in coming to the conclusion that the petitioner''s annual capacity is less than 600 MT and does not qualify

for Re-Tender issued in April 2007, is vitiated by non-application of mind and the same is only based on extraneous consideration. Further, the

first Tender Notification issued in December 2006 has been scrapped on account of the mistake relating to the BIS specifications. The Re-Tender

issued was again for supply of 1100 MT of webbings with annual capacity of the tenderer at 600 MT. Earlier, though the petitioner was stated to

have a capacity of more than 1250 MT when the first Tender Notification was issued in December 2006, and when the Committee of the

respondents inspected, the copy of the inspection report having not been furnished, the decision of the respondents based on the said Committee

report, is nothing but arbitrary and irrational.

31.

The learned Senior Counsel appearing for the petitioner further contended that the Re-Tender Notification issued on 21.8.2007 is again for the

supply of 1100 MT of webbings, with the production capacity of the tenders being reduced by 100 MT and such an act of the respondents

smacks of irrationality and unreasonableness and it could not be understandable as to how such a low production capacity could cater to the

annual need of 1100 MT of webbings, to be supplied to the fishermen affected by Tsunami. Therefore, the impugned Re-Tender Notification is

vitiated by non-application of mind and arbitrariness, besides being violative of Article 14 of the Constitution of India.

32.

It is zealously contended by the learned Senior Counsel appearing for the petitioner-Company that even though there was a representation

requesting the respondents to give personal hearing to submit the materials to show that their production capacity is more than 1200 MT, it was

not at all considered and the inaction on the part of the respondents is arbitrary and unreasonable and therefore, the Re-Tender Notification is

liable to be set aside.

33.

It is lastly contended by the learned Senior Counsel appearing for the petitioner that the respondents ought to have given valid and justifying

reasons for calling for a Re-Tender and the rejection of the second Tender in April 2007 seems to be on a wrong premise that the petitioner is not

qualified, which is non-est both in law and on facts. Hence, looked at from any angle, the decision of the respondents to issue Re-Tender

Notification deserves to be set aside both for the reason that it is based on non-existent fact and also causing serious prejudice and stigma on the

petitioner.

34.

The prayer in Writ Petition No. 27258 of 2007 is for issuance of a Writ of Mandamus, directing the respondents to approve the technical bid

of the petitioner in cover No. 1 in T.D. No. 2, dated 2.5.2007 and declare the successful tenderer opening cover No. 2.

35.

The prayer in Writ Petition No. 28485 of 2007 is for issuance of a Writ of Certiorarified Mandamus, to call for the records pertaining to the

advertisement made by the third respondent in second Re-Tender Ref. No. 019/TIPU/2007, dated 17.8.2007 i.e. (DIPR/3473/Tender/2007,

dated 6.9.2007) for supply of 1100 MTs of Double Knotted Nylon Nets (Webbings) from the manufacturers under fixed rate contract system

advertised in the New Indian Express dated 21.8.2007 and corrigendum dated 23.8.2007 and quash the same and direct the respondents to

finalise the first Re-Tender DIPR/1521/Tender/Document/2007, dated 28.5.2007.

36.

The case of the petitioner in W.P. No. 27258 of 2007 is as follows:

The petitioner-Company is a reputed manufacturer of all kinds of fishing nets, that the petitioner has been in the trade since 1986, that M/s. World

Vision India and M/s. Salvation Arym placed orders to the petitioner for supply of fish nets having appreciated the quality products of the

petitioner, that by tender document in T.D. No. 02, dated 2.5.2007, the second respondent had invited sealed tenders from the manufacturers of

nylon webbings with a production capacity of not less than 600 metric tonnes per annum for the description of works specified in the tender

document and that the tender for the supply of 1100 MT of knotted nylon webbings is as per the following specifications:

Sl. No. Type of material Twine size Stretched Mesh size in mm

1 Nylon Multifilament 210 d x 1 x 2 30

2 Nylon Monofilament 0.16 mm dia 27

3 Nylon Monofilament 0.16 mm dia 36

4 Nylon Multifilament 210 d x 1 x 2 36

5 Nylon Monofilament 0.23 mm dia 56

6 Nylon Multifilament 210 d x 1 x 3 56

37.

It is the further case of the petitioner in W.P. No. 27258 of 2007 that the petitioner-Company submitted its tender on 28.5.2007 to the second

respondent, that the petitioner deposited a sum of Rs. 44 lakhs by way of EMD besides producing a solvency certificate from the State Bank of

India, Nagercoil Branch for a sum of Rs. 4,40,00,000/- as per the terms and conditions of the tender, that as per the tender condition, the

manufacturers of nylon webbings should have production capacity of 600 MT/p.a., that since the petitioner''s unit manufacturing capacity is 282.5

MT/p.a., the petitioner took lease of two other manufacturing units, namely (i) M/s. Netpark at Anandanadarkudi, Nagercoil-629 201,

Kanyakumari District and (ii) M/s. Ajantha Fish Nets, No. 14-C, Government Industrial Estate, Konam, Nagercoil-629 004, having capacity of

752.5 MT and 197.5 MT respectively in compliance of the terms and conditions of the tender, that the manufacturing capacity of the petitioner''s

unit is thus 1235.5 MT which is obviously double the requisite manufacturing capacity of 600 MT, that the petitioner has submitted the tender

along with the two lease agreements entered into between the petitioner and the above lessees, that the second respondent, by letter dated

30.5.2007, informed the petitioner that the Tender Scrutinizing Committee which evaluated the technical bids of the tenderers, decided to depute a

team of officials and required the petitioner to keep the plant and machineries in operating conditions on 2.7.2007, besides requiring the petitioner

to make available all the documents for inspection and verification, that in pursuance of the said letter, the officials visited the manufacturing units of

the petitioner on 2.7.2007, 5.7.2007 and 21.7.2007 respectively and that the Tender Scrutinizing Committee was satisfied with the production

capacity of the petitioner-Company which is about 1235.5 MT.

38.

The petitioner-Company in W.P. No. 27258 of 2007 further states that one of the tenderers, namely M/s. Garware Wall Ropes Limited was

considered for being given the tender work, that the second respondent took sample nets from them indicating consideration of their tender, that

besides the petitioner herein and M/s. Garware Wall Ropes Ltd., there is another tenderer M/s. Kumaran Nets, that the said M/s. Garware Wall

Ropes Ltd. does not possess the requisite technical bid qualification, namely the production capacity of 600 MT of nylon webbings entitling the

second respondent to take sample nets from them, that the petitioner made a letter to the second respondent on 18.7.2007, stating that the said

M/s. Garware Wall Ropes Ltd. lacks the above production capacity, that even before inspecting the manufacturing unit of the said M/s. Garware

Wall Ropes Ltd., the second respondent obtained the sample nets from them and that the same is improper, that only after 18.7.2007 letter of the

petitioner, the second respondent caused inspection of the manufacturing unit of the said M/s. Garware Wall Ropes Ltd., that the action of the

respondents is indicative of the pre-determined approach to help M/s. Garware Wall Ropes Ltd., that the petitioner believes that the official team,

having inspected the premises of M/s. Garware Wall Ropes Ltd., they lack the production capacity of 600 MT per year and submitted report in

that behalf to the second respondent, that the respondents are attempting to reject the tender of this petitioner under one pretext or the other and

that this petitioner cannot be disqualified since they have the production capacity of about 1235.5 MT, which is double the required capacity as

per the Tender Notification.

39.

The further case of the petitioner in W.P. No. 27258 of 2007 is that the respondents are bound to call for the sample nets from the petitioner

for proceeding to open Cover No. 2, namely the price bid, that the respondents are bound by the principle of promissory estoppel, that the

petitioner was not heard till the date of filing of the writ petition, which is in violation of the principles of natural justice and that the conduct and

action of the respondents is arbitrary, whimsical and illegal in not considering the tender of the petitioner-Company though they satisfy the required

production capacity, besides the action of the respondents is offending Articles 14 and 21 of the Constitution of India.

40.

The case of the petitioner in W.P. No. 28485 of 2007 is as follows:

(a) The Government of India, under Rajiv Gandhi Rehabilitation Package for Tsunami victims, has allocated Rs. 110 crores under five categories,

namely nets, handy rechargeable lanterns, heavy duty bicycles, life jackets and insulated ice boxes, etc., of which an amount of Rs. 44 crores has

been allocated for nets (webbings), that the tenders for remaining 4 categories have already been finalised and awarded, that the category of ''nets

(webbings)'' is the only item remaining to be finalised, that the respondents have been dilly-dallying with the tenders without finalising the tender for

nets (webbings) resulting in inordinate delay in the implementation of the programme for which the amount has been earmarked.

(b) The petitioner in W.P. No. 28485 of 2007 is a reputed manufacturer of all kinds of fishing nets, that the petitioner has been in the trade since

1986, that M/s. World Vision India and M/s. Salvation Arym placed orders to the petitioner for supply of fish nets having appreciated the quality

products of the petitioner, that on 12.12.2006, the petitioner obtained tender documents for supply of 1100 MTs of knotted nylon gill nets

(webbings) at a cost of Rs. 15,000/- plus tax, pursuant to the tenders called for by the second respondent to the Tsunami affected fishermen under

the Rajiv Gandhi Rehabilitation Package, that on 4.1.2007, the petitioner submitted the tender along with necessary documents and the EMD of

Rs. 44 lakhs, that in addition to the petitioner, M/s. Garware Wall Ropes Ltd. was the other tenderer which has submitted the tender, that the

eligibility condition prescribed by the second respondent is that the manufacturer of nets (webbings) should have a production capacity of not less

than 1250 MTs per annum for the description of work specified, that the other condition is that the webbing and twines used should conform to

BIS standard and specification, that on 25.4.2007 the third respondent addressed a letter to the petitioner stating that the Tender Award

Committee constituted by the Government has decided to call for a Re-Tender for the nets (webbings), that the EMD deposited by the petitioner

to the tune of Rs. 44 lakhs was returned on 25.4.2007 along with a letter without assigning any reason after a lapse of nearly four months, that the

third respondent called for Re-Tender for supply of 1100 MTs of knotted nylon webbings from the manufacturers of nylon webbings with a

production capacity of not less than 600 MT per annum instead of 1250 MT production capacity fixed in the original tender, that the petitioner

units have a capacity of more than 1250 MT per annum even though the prescribed production capacity pursuant to the Re-Tender has been fixed

at 600 MT, that the petitioner has also submitted a Certificate from the Chartered Accountant, dated 23.5.2007, to the said effect, that on

2.5.2007, the petitioner received the tender documents after payment of Rs. 15,000/- plus taxes as documents charges and on 28.5.2007, the

tender was submitted along with all documents and EMD of Rs. 44 lakhs.

(c) M/s. Garware Wall Ropes Ltd. and Kumaran Nets were the other two tenderers who have submitted their tenders in response to the Re-

Tender called by the third respondent on 2.5.2007, that on 30.5.2007, the third respondent addressed a letter to the petitioner stating that the

Tender Scrutinizing Committee decided to depute a team of officials to inspect the unit on 2.6.2007, that the petitioner made arrangements for

inspection by the said Committee, that on 2.6.2007, the Inspection Team inspected the petitioner unit, that on 5.6.2007, the petitioner made a

representation to the third respondent stating that the said Committee has not inspected the other two leased units of the petitioner, that on

8.6.2007 and 21.6.2007, based on the said representation, the Team inspected the other two units, that the said Committee was satisfied with the

production capacity of not less than 600 MT/p.a. of the petitioner even though the petitioner''s installed production capacity is 1305 MT and

average production capacity is 1044 MT/p.a, which is nearly double the required production capacity in the Re-Tender called for by the third

respondent, that on 13.8.2007, the petitioner preferred W.P. No. 27258 of 2007 before this Court for a mandamus to direct the third respondent

to approve the technical bid of the petitioner in Cover No. 1 in T.D. No. 02, dated 2.5.2007, and to declare the successful tenderer by opening

cover No. 2 consisting the price bid, that the tender submitted by the petitioner consists of two parts, i.e. Cover No. 1 relating to technical bid and

Cover No. 2 relating to the price bid, that on 28.5.2007, the technical bid submitted by the petitioner was opened by the third respondent to verify

the genuineness and eligibility condition of the petitioner-Unit, that it is the bounden duty of the third respondent to open the price bid, that no steps

have been taken to call for the samples and for opening the price bid, that on 16.8.2007, this Court issued notice to the respondents in W.P. No.

27258 of 2007 and the said W.P. is pending.

(d) On 18.7.2007, the petitioner in W.P. No. 28485 of 2007 made a representation to the Chief Minister, Finance Secretary, Government of

Tamil Nadu and the first respondent, pointing out the fact while the third respondent has inspected the units of the petitioner, the same was not

done in respect of M/s. Garware Wall Ropes Ltd., the other bidder, that the petitioner requested the first respondent to depute a technical team to

visit the factory premises of the said M/s. Garware Wall Ropes Ltd., for verification of their manufacturing capacity, that the reduction of the

production capacity has been resorted to in order to accommodate the other tenderers, that in the meanwhile, the third respondent called for

second Re-Tender and if the third respondent is permitted to process the second Re-Tender, the said W.P. in W.P. No. 27258 of 2007 would

become infructuous depriving the opportunity of the petitioner to succeed in the bid, that the third respondent on 21.8.2007, again made an

advertisement in ""The New Indian Express"" calling for second Re-Tender for supply of 1100 MT of double knotted nylon webbings with a

minimum production capacity of 100 MT/p.a. of their own individual capacity, that on 23.8.2007, the third respondent issued a corrigendum

stating that ""Title in Para 1 of Tender Notice dated 21.8.2007 shall be read as ""Re-Tender Notice"" "", fixing 6.9.2007 as last date for submission of

tenders, that the reason for calling for Re-Tender is in order to accommodate their own personnel for supply of double knotted nylon webbings,

that the respondents have been decreasing the production capacity of the suppliers as under in order to accommodate the tenderers of their choice:

Tender Notice dated 4.1.2007 - 1250 MT/p.a

(for 1100 MT of knotted nylon webbings)

Tender Notice dated 28.5.2007 - 600 MT/p.a

(for 1100 MT of knotted nylon webbings)

Tender Notice dated 6.9.2007 - 100 MT/p.a

(for 1100 MT of double knotted nylon webbings)

(e) It is the case of the petitioner in W.P. No. 28485 of 2007 that the sum of Rs. 44 lakhs has been with-held for nearly four months in the original

tender and for nearly three months in the first Re-Tender, that the action of the respondents is with ulterior motive and with only a pre-determined

mind in awarding the contract and that the public interest would suffer and would defeat the social purpose for providing relief to the Tsunami

affected people.

(f) The above stated facts show only vindictive action of the respondents and the same is without any rhyme or reason, besides being arbitrary,

illegal, capricious and contrary to all cannons of principles of natural justice and violative of the mandate prescribed under Articles 14 and 19 of the

Constitution of India and the provisions of the Act and Rules.

41.

A common counter affidavit has been filed by the respondents in both the Writ Petitions (W.P. Nos. 27258 and 28485 of 2007), stating as

follows:

The Writ Petitions are not maintainable in law as the issue under consideration falls in the realm of contract, that it is settled law in matters of

awarding of contract, which is essentially a commercial transaction, the State Government is entitled to choose its own method and arrive at an

appropriate decision. The Government has the freedom to contract by taking its own decision and the scope of judicial review of such decision-

making process is severely circumscribed and restricted, especially when the State has taken the decision to go in for Re-Tender motivated by

paramount public interest. The Tsunami hit the Tamil Nadu coast on 26.12.2004 and caused damages to the life and fishing implements of the

fishermen in the entire coastal Districts of Tamil Nadu, that the Government sanctioned various relief schemes as rehabilitation measure to the

fishermen community for repairing their nets and for replacing fully damaged/lost fishing implements, about 42,000 fishermen were given relief

assistance sanctioned under various Government orders. As a huge amount was available from the total sanctioned relief assistance, the

Government in Order No. 532, Revenue Department, dated 14.8.2006, read with Government Letter of the Revenue Department, dated

22.11.2006, sanctioned a sum of Rs. 110.36 crores for the purchase and supply of nets of 1100 MTs, handy rechargeable lanterns, heavy duty

bicycles, life jackets and insulated ice boxes, with quality, for assistance under the Rajiv Gandhi Rehabilitation Package.

42.

It is further averred in the counter affidavit that the Government, among other things, allocated a sum of Rs. 44 crores out of the total sanction

of Rs. 110.36 crores for supply of nets to the already benefited Tsunami affected fishermen under the above Package, that the total loss of nets,

due to Tsunami, according to actual assessment was 1100 MTs, that it was therefore proposed to purchase and supply 25 Kgs. of Gill Nets to

each beneficiary at a unit cost of Rs. 400/- per Kg, subject to a maximum of Rs. 10,000/- per beneficiary, that the Government, in G.O.Ms. No.

193, Animal Husbandry, Dairying and Fisheries Department, dated 22.11.2006, issued orders constituting Technical Committee, Scrutinizing

Committee and Award Committee for processing the tenders and the Committees for the purchase of nets are as follows:

Sl. No. Name of the Committee Members of the Committee

1 Tender Technical Committee

1.

Spl. Commissioner of Fisheries - Chairman

2.

Director of his representative from CIFNET - Member

3.

Zonal Director or his representative of FSI, Chennai - Member

4.

Joint Director of Fisheries (Marine) - Member Secretary

2 Tender Scrutinizing Committee

1.

Spl. Commissioner of Fisheries - Chairman

2.

Joint Director of Fisheries (Marine, Inland & Research) - Members

3.

Accounts Officer (Fisheries) - Member

4.

Deputy Director of Fisheries (Marine) - Member Secretary

3 Tender Award Committee

1.

Secretary to Government, AHD & F Dept - Chairman

2.

Secretary to Government, Finance Department or his/her

nominee - Member

3.

The Director of Fisheries - Member Secretary

The Tender Technical Committee suggested the following specifications for the knotted nylon webbings for the gill nets to be purchased with

suitable mesh size:

Knotted Gill Nets (only webbings) approved by BIS with the following specifications:

Sl. No. Type of material Twine size Stretched Mesh size in mm

1 Nylon Multifilament 210 d x 1 x 2 30

2 Nylon Monofilament 0.16 mm dia 27

3 Nylon Monofilament 0.16 mm dia 36

4 Nylon Multifilament 210 d x 1 x 2 36

5 Nylon Monofilament 0.23 mm dia 56

6 Nylon Multifilament 210 d x 1 x 3 56

The Committee also recommended that nets with BIS specifications, may be purchased.

43.

It is further averred in the counter that based on the recommendations of the Committee, tenders for purchase of all the above said five

components including nets were called for, that the Tender Notice was published in the leading dailies, that the tenders were invited only from the

manufacturers of nets (webbings) with a production capacity of not less than 1250 MT per annum of above specifications, that the EMD for the

tender was fixed at Rs. 44 lakhs and that the cover system was adopted and the tender document was based on the Act and Rules. The last date

for receipt of tenders was upto 3.00 p.m. on 4.12.2007. Eleven tenders were purchased and only four tenders were received and respondents

have taken all possible steps to process the tender as per the procedure laid down in the Act and as per the conditions mentioned in the tender

document. The tenders were opened at 4.00 p.m. on 5.1.2007. Only the first cover, viz., technical bid was opened. The technical bids were

evaluated by the Tender Scrutinizing Committee on 22.1.2007 and only one tenderer viz. M/s. Garware Wall Ropes Limited was found technically

qualified. The other three tenders, namely M/s.Kassim Nets, M/s. Nirmala Monofil Pvt. Ltd. and M/s. Raj Nylon Exports, were rejected on

technical grounds. The net manufacturing plant of the qualified tenderer viz. M/s. Garware Wall Ropes Ltd., was inspected on 7.2.2007 and based

on the recommendations of the Tender Scrutinizing Committee on the evaluation of the Inspection Report, samples of all the webbings of the

specifications mentioned in the tender document were obtained from the firm and sent to CIPET for testing on 20.2.2007. The test report on the

samples was received from CIPET on 9.3.2007 and the same was evaluated by the Tender Scrutinizing Committee on 12.3.2007. The Committee

recommended to conduct breaking load test of the samples as per the BIS specification by CIPET. Test report on breaking load was received

from CIPET on 23.3.2007 and the same was evaluated by the Scrutinizing Committee on 3.4.2007 and based on the recommendations of the

Committee, the price bid of the technically qualified tenderer was opened on 4.4.2007 and negotiation of rates was done with the tenderer on

10.4.2007. On the recommendations of the Tender Scrutinizing Committee, technical bids and price bids were placed before the Tender Award

Committee meeting for taking a decision on 12.4.2007. The Tender Award Committee took note of the information given by the Scientists

(Experts) from CIFT, Cochin, CIPET, Chennai, stating that there were no BIS specifications for webbings, unlike twines. However, BIS standard

test procedures are available for both webbings and twines. Since BIS standard specifications were not prescribed for webbings, the technical

requirements under this tender cannot be evaluated. In view of the above facts, the Award Committee asked to go for re-tender. The tender was

therefore cancelled and the EMD was returned to the tenderers on 25.4.2007. Thereafter, the Tender Award Committee instructed a re-tender

should be called for the purchase of 1100 MT of nets and the same was done with the following modifications:

1.

Tenders were invited from the manufacturers of nets (webbings) only with a production capacity of not less than 600 MT per annum of the

specifications mentioned above (The Twine size in Sl. No. 5 Nylon Monofilament was changed as 0.24 mm. dia instead of 0.23 mm dia).

2.

BIS specifications were given in the tender document as follows:

. Nylon webbings should be made up of Nylon twines/monofilament yarn of BIS specifications (i.e)

Nylon multifilament (Twine): IS 4401 : 2006

Nylon monofilament : IS 7533 : 2003

. The webbing should be made up of virgin Polyamide (Nylon) twine/yarn.

. Recycled raw material (Nylon) should not be used for making webbings.

3.

The Tender Scrutinizing Committee recommended to fix the production capacity as 600 MTs/annum in view of the fact that only one responsive

bid was received for the first tender in which the production capacity was fixed as 1250 MTs/annum and also considering the uniqueness of the

purchase in terms of volume which needs to be supplied within one year.

Accordingly, the tender notice dated 25.4.2007 inviting tenders was published in leading dailies and the last date for receipt of tenders was fixed as

3.00 p.m. on 28.5.2007. Totally, three tenders were received as follows:

(i) M/s. Garware Wall Ropes Pvt. Ltd., Pune.

(ii) M/s.Kassim Nets, Nagercoil.

(iii) M/s. Kumaran Fish Nets Private Ltd., Nagercoil.

44.

The technical bids were opened at 4.00 p.m. on 28.5.2007 and the manufacturing plants of M/s.Kassim Nets, Nagercoil and M/s.Kumaran

Nets, Nagercoil were inspected on 2.6.2007 and 22.6.2007 and the inspection notes and the technical bids were evaluated on 30.5.2007,

11.6.2007 and 22.6.2007. Samples received from M/s. Garware Wall Ropes Ltd. were sent to CIFT, Cochin on 29.6.2007 for testing to confirm

whether it meets BIS specifications. The test report received from CIFT, Cochin on 11.7.2007 confirmed the same.

45.

While that being the position, a specific complaint dated 19.7.2007 against the production capacity of the said M/s. Garware Wall Ropes Ltd.

was received and it was decided by the Tender Scrutinizing Committee on 24.7.2007 to depute a team of officials to inspect as to whether the said

Company has the production capacity of its own for the descriptions of the works as specified in the tender. The said Company was re-inspected

from 25.7.2007 to 28.7.2007. The inspection team found that the Company did not possess the capacity claimed in the tender document.

Thereafter, the Tender Scrutinizing Committee has evaluated the technical bids, inspection reports of all the tenderers and test reports on the

samples of the said Company. Since no one was found qualified in the evaluation process by the Tender Scrutinizing Committee, the tenders of all

the three tenderers, namely M/s. Garware Wall Ropes Ltd., Pune, M/s.Kassim Nets, Nagercoil and M/s. Kumaran Nets, were rejected. The

Tender Scrutinizing Committee in its meeting held on 9.8.2007, has made the following recommendations:

1.

By experience in the previous two tenders, there were no suitable suppliers even after the reduced production quality of 600 MTs/year as

eligibility criteria.

2.

1100 MTs of Nylon webbings have to be distributed to the fishermen within a timeframe of one year.

3.

To ensure better participation in tender and going by the previous experience, that there is no suitable manufacturer with the production capacity

of 1250 MT/annum and 600 MT/annum, the production capacity may be reduced to 100 MT/annum.

4.

The Government may be addressed to permit the third respondent to go for re-tender under fixed rate contract system and to reduce the

production capacity to 100 MTs/annum (60% monofilament : 40% multifilament) of webbings of specified description in the tender and also to

reduce the time limit to 15 days for inviting tenders, since the tender call is for the third time and all the manufacturers were aware of the supply of

webbings to fishermen.

Therefore, the Government was addressed on the above lines in the letter No. 38116/TPIU/07, dated 9.8.2007 by the third respondent-Director

of Fisheries and the Government in Letter No. 16926/FSI/2007-1, dated 17.8.2007 permitted the third respondent (Director of Fisheries) to go

for re-tender under fixed rate contract system and to reduce the time limit to 15 days. Therefore, the tenders were cancelled on 17.8.2007. The

said M/s. Garware Wall Ropes Pvt. Ltd.''s tender was also cancelled on 17.8.2007-vide third respondent''s letter No. 55055/P1/2007, dated

17.8.2007 and the EMD of Rs. 44 lakhs was returned to it. In view of this, the prayer in W.P. No. 27258 of 2007 has become incapable of being

granted and the same has become infructuous and the said W.P. No. 27258 of 2007 is liable to be dismissed in-limine.

46.

It is the further case of the respondents in the counter that as instructed by the Government in Letter No. 16926/FSIII/2007-1, dated

17.8.2007, re-tender II was called for the purchase of 1100 MTs of nets with the following modifications:

(i) Nylon webbings should be made up of Nylon twines/monofilament yarn of BIS specifications (i.e).

Nylon Multifilament (Twine) : IS 4401:2006

Nylon Monofilament : IS 7533:2003

(ii) The manufacturers shall have their production capacity of webbings in the ratio of 60:40 of monofilament : multifilament respectively.

(iii) The webbing should be made up of virgin Polyamide (Nylon) Twine/Yarn.

(iv) Recycled raw material (Nylon) should not be used for making webbings.

Tender notice inviting re-tenders dated 21.8.2007 was published in the leading dailies and corrigendum was also issued on 23.8.2007. The

eligibility criteria for bidders have been prescribed in the tender notice as follows:

(a) The bidder shall be a registered manufacturer having a minimum individual annual production capacity of 100 MTs of nylon (Polyamide) nets

(Double knotted Nylon webbings) in the ratio of 60% monofilament : 40% multifilament nylon nets (double knotted nylon webbings) of the

specified description in the tender schedule and having experience in the production and marketing of the webbings of the specifications described

in the tender document for a minimum period of three years.

(b) Alliance or agreement of any type with any manufacturer/dealer/distributor dealing with the said nylon webbings like Consortium/lease rent/joint

venture etc. shall be rejected.

(c) The bidders should provide samples in a separate cover of multifilament twines and monofilament yarn for making knotted nylon webbings and

also samples of the webbings of the descriptions specified in the tender document made out of the above indicated twines/yarns along with tender

document.

(d) EMD has been reduced and fixed as Rs. 11 lakhs.

(e) Two cover system will be followed.

(f) Production of production plan has been made mandatory.

Last date for receipt of tenders has been fixed on 6.9.2007 upto 3.00 p.m.

47.

Hence, it is the case of the respondents in the counter that in view of the facts stated by the respondents as above, it reveals that there is no

mala-fide or wilful intention on the part of the respondents to cancel the earlier tender and invite fresh tender as notified on 21.8.2007. There is no

iota of evidence to show that the tender process is arbitrary. It is contended by the respondents in the counter that as per the procedure laid down

in the Act and as per the conditions mentioned in the tender document, the respondents have taken all steps to process the tenders. There is no

undue delay as contended by the petitioner in processing the tenders by the respondents, since as per the tender conditions, the samples of the

technically qualified tender have got to be tested before opening the price bid. The basis for the decision of the Tender Award Committee to go in

for Re-Tender based on its meeting held on 12.4.2007 is that in the absence of BIS specifications for webbings, the quality of the webbings to be

supplied to the fishermen cannot be evaluated and hence, there is no mala-fide intention or delay in processing the tenders, as alleged by the

petitioner. Regarding the contention that the petitioner has entered into a lease agreement with two manufacturing plants, namely M/s.Net Park and

M/s. Ajanta Fish Nets, it is proved beyond doubt on investigation by the respondents that actually, the petitioner has not entered into the lease

agreement with these two plants and the draft lease deed was produced for convenience to believe that it has the required production capacity of

600 MT/per annum specified in the Re-Tender, dated 25.4.2007, but actually the production capacity of the petitioner was less than 600 MT/p.a.

48.

It is the further case of the respondents in the counter that the provisions of Rule 18(2) of the Tamil Nadu Transparency in Tenders Rules were

duly followed. Inasmuch the Re-Tender notified on 25.4.2007 has been cancelled and the EMD was returned, the question of opening the price

bid does not arise. The question of opening the price bid will arise only after the tenderers have qualified themselves for the criteria prescribed for

technical bids. The contention of the petitioner that in order to accommodate the other tenderer, the reduction in production capacity was resorted

to, is false, because the alleged other tenderer, namely M/s. Garware Wall Ropes Ltd., was disqualified on the ground that it lacked the required

production capacity as notified in the tender. The apportioning of the quantity for the supply of nylon webbings will be decided based on the

production capacity to ensure the Department to fulfil its requirement of 1100 MT of nets (webbings) and hence, the contention of the petitioner

that decrease in production capacity is to accommodate the tenderers of choice, is baseless and unfounded.

49.

It is further averred in the counter that the Re-Tender was floated based on the approval of the Government and the decision of the

respondents was a collective one based on facts and figures and therefore, the question of favouring any one does not arise. In all fairness, it is

stated by the respondents that the principles of natural justice was applied for participation of all eligible manufacturers and that the Technical

Tender Scrutinizing Committee evaluated all the bids and since it found that there was no qualified tender, the Re-Tender process was proceeded,

that too after scientific examination of the technical bids and the facts brought out by the inspecting teams of officials. Thus, there is no pre-

determined mind of the respondents. The writ petitioner came to Court with tainted mind and mala-fide intention to circumvent the tender process,

which is intended to benefit the downtrodden Tsunami affected/already benefited fishermen. At any rate, the Writ Petitions are liable to be

dismissed as devoid of merits.

50.

Mr. A.L. Somayaji, learned Senior Counsel appearing for the petitioner in W.P. Nos. 27258 and 28485 of 2007, has vehemently contended

the Government of India under Rajiv Gandhi Rehabilitation Package for Tsunami victims, has allocated Rs. 110 crores under five categories,

namely nets, handy rechargeable lanterns, heavy duty bicycles, life jackets and insulated ice boxes, etc., of which an amount of Rs. 44 crores has

been allocated for nets (webbings), that the petitioner is a reputed manufacturer of all kinds of fishing nets and has been in the trade since 1986. It

is the further contention of the learned Senior Counsel that the petitioner-Company had orders with M/s.World Vision India and M/s. Salvation

Arym for supply of fishing nets, having appreciated the quality of products of the petitioner-Company. Insofar as the eligibility condition, the

learned Senior Counsel submitted that the manufacturer of nets (webbings) should have a production capacity of not less than 1250 MT per annum

and the other condition is that the webbing and twines used should conform to BIS standard and specification. It is the further contention of the

learned Senior Counsel that the Tender Award Committee constituted by the Government, has decided for Re-Tender of the nets (webbings), for

supply of the same 1100 MT, even though the petitioner was having a capacity of more than 1250 MT/p.a., when the prescribed production

capacity pursuant to Re-Tender has been fixed at Rs. 600 MT. The decision to further lower down the capacity as 100 MT from 600 MT for the

same supply of 1100 MT of total knotted webbings, cannot and could not be achieved, as the requirement is 1100 MT. Therefore, the action of

the respondents is against the object and reasons contemplated under the and Tamil Nadu Transparency in Tenders Rules, 2000.

51.

The learned Senior Counsel appearing for the petitioner submitted that the decision-making process as contemplated by the respondents in

going for Re-Tender, is an arbitrary exercise and illegal. At any rate, the second Re-Tender violates the principles of natural justice. The learned

Senior Counsel submitted further that going for second Re-Tender without even finalising the first Re-Tender in order to accommodate their own

persons for supply of double knotted nylon webbings, is violative of Article 14 of the Constitution of India.

52.

A paramount point has been raised by the learned Senior Counsel appearing for the petitioner-Company that calling for second Re-Tender

without finalising the previous one, after opening the technical bids, reflects the pre-determined mind on the part of the third respondent in awarding

the contract to a tenderer of their choice. Further, the delay in finalising the first Re-Tender amounts to defeating the social purpose of providing the

relief to the Tsunami affected fishermen, for which allocation has been specifically made by the Government and the net result is that public interest

would suffer and that without assigning any reason for not opening the price bids after opening the technical bids and not finalising the first Re-

Tender is illegal, arbitrary and violative of Articles 14 and 19 of the Constitution of India.

53.

The learned Senior Counsel has strenuously contended that upto the second Re-Tender, the requirement of the respondents is that 1100 MT

nets (webbings) and they have changed the eligibility criteria from the original Tender/first and second Re-Tenders, which clearly shows the

vindictive attitude on the part of the respondents in finalising the contract and therefore, the second Re-Tender cannot be sustained and the same is

liable to be set aside.

54.

The following citations were relied on by the learned Senior Counsel appearing for the petitioners:

(i) Noble Resources Ltd. Vs. State of Orissa and Another, ;

(ii) 1994 (6) SCC 651 (Tata Cellular v. Union of India) and

(iii) Union of India and Others Vs. Dinesh Engineering Corporation and Another etc., ;

55.

On the other hand, the learned Advocate General appearing for the respondents, submitted that on 26.12.2004, the Tamil Nadu coast has

been hit by the Tsunami causing damage to the life and fishing implements of the fishermen in the entire coastal Districts of the Tamil Nadu State.

The Government sanctioned various relief schemes as rehabilitation measures. About 42,000 fishermen were affected and given the relief

assistance under the various Government Orders. One of the important measures taken by the Government is that orders have been issued on

22.11.2006 sanctioning a sum of Rs. 110.36 crores for purchase and supply of various items, which qualify for assistance under Rajiv Gandhi

Rehabilitation Package, out of which, a sum of Rs. 44 crores has been allotted for purchase and supply of nets to the already benefited Tsunami

affected fishermen under the above Package. The total loss of nets due to Tsunami, according to the actual assessment was 1100 MT. The learned

Advocate General in his submissions, stated that the Government, after constituting the Technical Committee, Scrutinizing Committee and Award

Committee for processing the tenders for the purpose of purchase of nets and according to the Committees'' recommendations and the entire

process of inviting tenders taking decision, and after the publication of the tender notices, the procedure as contemplated under the and the Tamil

Nadu Transparency in Tenders Rules, 2000 have been scrupulously followed by the respondents. The learned Advocate General further submitted

that since BIS standards and specifications were not prescribed for webbings, the technical requirements under the tender cannot be evaluated.

56.

The learned Advocate General, in his submissions, stated that the original Tender and Re-Tenders are all within the powers of the Government

and the procedures contemplated under the provisions of the and the Tamil Nadu Transparency in Tenders, Rules, 2000 have been followed, by

taking into consideration the decisions of this Court as well as the Supreme Court and the Re-Tender process does not suffer from any legal

infirmity. The submissions of the learned Advocate General are four-fold; firstly, the scope of the judicial review in matters falling under the realm of

contract is limited; secondly, the power of the respondents to relax the tender conditions and to call for Re-Tender cannot be interfered with by

Courts of law unless it is patently arbitrary; thirdly, the decision of the authorities to call for Re-Tender has been taken based on paramount public

interest ensuring wider participation, shorter time-frame and expeditious implementation and therefore, the decision-making process by the

respondents is unimpeachable in law and lastly, the cancellation of tender and the decision to call for Re-Tender does not require any opportunity

to be given or reasons to be recorded, as no right accrues to any party at that stage.

57.

The following are the decisions relied on by the learned Advocate General:

(i) M. Vasudevan Vs. The Chief Executive Officer, Chennai Metropolitan Development Authority, D. Jayakumar and Genguva Rajan, ;

(ii) Sterling Computers Limited and Others Vs. M and N Publications Limited and Others, ;

(iii) Directorate of Education and Others Vs. Educomp Datamatics Ltd. and Others, ;

(iv) Master Marine Services Pvt. Ltd. Vs. Metcalfe and Hodgkinson Pvt. Ltd. and Another, ;

(v) Global Energy Ltd. and Another Vs. Adani Exports Ltd. and Others, and

(vi) B.S.N. Joshi and Sons Ltd. Vs. Nair Coal Services Ltd. and Others, .

58.

The following are the relevant paragraphs deducible from the authorities relied by either side:

(i) Global Energy Ltd. and Another Vs. Adani Exports Ltd. and Others, :

9.

In Tata Cellular Vs. Union of India, a three-Judge Bench has explained what is a tender and what are the requisites of a valid tender. It has been

held that the tender must be unconditional and must conform to the terms of the obligation and further the person by whom the tender is made must

be able and willing to perform his obligations. It has been further held that the terms of the invitation to tender cannot be open to judicial scrutiny

because the invitation to tender is in the realm of contract. In Air India Ltd. Vs. Cochin Int., Airport Ltd. and Others, , the same view was

reiterated that the State can fix its own terms of invitation of tender and that it is not open to judicial scrutiny. Whether and in what conditions the

terms of a notice inviting tenders can be a subject-matter of judicial scrutiny, has been examined in considerable detail in Directorate of Education

v. Educomp Datamatics Ltd. 2000 (4) SCC 19.... In appeal, this Court reversed the judgment of the High Court basically on the ground that the

terms of the invitation to tender are not open to judicial scrutiny, the same being in the realm of contract and the Government must have a free hand

in settling the terms of the tender. The courts would not interfere with the terms of the tender notice unless it was shown to be either arbitrary or

discriminatory or actuated by malice. It was further held that while exercising the power of judicial review of the terms of the tender notice, the

court cannot order change in them.

10.

The principle is, therefore, well settled that the terms of the invitation to tender are not open to judicial scrutiny and the courts cannot whittle

down the terms of the tender as they are in the realm of contract unless they are wholly arbitrary, discriminatory or actuated by malice.

(ii) Sterling Computers Limited and Others Vs. M and N Publications Limited and Others, :

12.

At times it is said that public authorities must have the same liberty as they have in framing the policies, even while entering into contracts

because many contracts amount to implementation or projection of policies of the Government. But it cannot be overlooked that unlike policies,

contracts are legally binding commitments and they commit the authority which may be held to be a State within the meaning of Article 12 of the

Constitution in many cases for years. That is why the courts have impressed that even in contractual matters the public authority should not have

unfettered discretion. In contracts having commercial element, some more discretion has to be conceded to the authorities so that they may enter

into contracts with persons, keeping an eye on the augmentation of the revenue. But even in such matters they have to follow the norms recognised

by courts while dealing with public property. It is not possible for courts to question and adjudicate every decision taken by an authority, because

many of the Government Undertakings which in due course have acquired the monopolist position in matters of sale and purchase of products and

with so many ventures in hand, they can come out with a plea that it is not always possible to act like a quasi-judicial authority while awarding

contracts. Under some special circumstances a discretion has to be conceded to the authorities who have to enter into contract giving them liberty

to assess the overall situation for purpose of taking a decision as to whom the contract be awarded and at what terms. If the decisions have been

taken in bona fide manner although not strictly following the norms laid down by the courts, such decisions are upheld on the principle laid down by

Justice Holmes, that courts while judging the constitutional validity of executive decisions must grant certain measure of freedom of ""play in the

joints"" to the executive.

18.

While exercising the power of judicial review, in respect of contracts entered into on behalf of the State, the Court is concerned primarily as to

whether there has been any infirmity in the ""decision making process"". In this connection reference may be made to the case of Chief Constable of

the North Wales Police v. Evans 1982 (3) All.E.R. 141 where it was said that: (p. 144a)

The purpose of judicial review is to ensure that the individual receives fair treatment, and not to ensure that the authority, after according fair

treatment, reaches on a matter which it is authorised or enjoined by law to decide for itself a conclusion which is correct in the eyes of the court.

By way of judicial review the court cannot examine the details of the terms of the contract which have been entered into by the public bodies or the

State. Courts have inherent limitations on the scope of any such enquiry. But at the same time as was said by the House of Lords in the aforesaid

case, Chief Constable of the North Wales Police v. Evans 1982 (3) All. E.R. 141 the courts can certainly examine whether ""decision-making

process"" was reasonable, rational, not arbitrary and violative of Article 14 of the Constitution.

19.

If the contract has been entered into without ignoring the procedure which can be said to be basic in nature and after an objective

consideration of different options available taking into account the interest of the State and the public, then Court cannot act as an appellate

authority by substituting its opinion in respect of selection made for entering into such contract. But, once the procedure adopted by an authority

for purpose of entering into a contract is held to be against the mandate of Article 14 of the Constitution, the courts cannot ignore such action

saying that the authorities concerned must have some latitude or liberty in contractual matters and any interference by court amounts to

encroachment on the exclusive right of the executive to take such decision.

(iii) Master Marine Services Pvt. Ltd. Vs. Metcalfe and Hodgkinson Pvt. Ltd. and Another, :

11.

The principles which have to be applied in judicial review of administrative decisions, especially those relating to acceptance of tender and

award of contract, have been considered in great detail by a three-Judge Bench in Tata Cellular Vs. Union of India, . It was observed that the

principles of judicial review would apply to the exercise of contractual powers by government bodies in order to prevent arbitrariness or

favouritism. However, it must be clearly stated that there are inherent limitations in exercise of that power of judicial review. Government is the

guardian of the finances of the State. It is expected to protect the financial interest of the State. The right to refuse the lowest or any other tender is

always available to the Government. But, the principles laid down in Article 14 of the Constitution have to be kept in view while accepting or

refusing a tender. There can be no question of infringement of Article 14 if the Government tries to get the best person or the best quotation. The

right to choose cannot be considered to be an arbitrary power. Of course, if the said power is exercised for any collateral purpose the exercise of

that power will be struck down. (See para 85 of the Report, SCC para 70.)

12.

After an exhaustive consideration of a large number of decisions and standard books on administrative law, the Court enunciated the principle

that the modern trend points to judicial restraint in administrative action. The court does not sit as a court of appeal but merely reviews the manner

in which the decision was made. The court does not have the expertise to correct the administrative decision. If a review of the administrative

decision is permitted it will be substituting its own decision, without the necessary expertise, which itself may be fallible. The Government must have

freedom of contract. In other words, fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative

sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of Wednesbury principles of

reasonableness but also must be free from arbitrariness not affected by bias or actuated by mala fides. It was also pointed out that quashing

decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure. (See para 113 of the

Report, SCC para 94).

15.

The law relating to award of contract by the State and public sector corporations was reviewed in Air India Ltd. Vs. Cochin Int., Airport Ltd.

and Others, and it was held that the award of a contract, whether by a private party or by a State, is essentially a commercial transaction. It can

choose its own method to arrive at a decision and it is free to grant any relaxation for bona fide reasons, if the tender conditions permit such a

relaxation. It was further held that the State, its corporations, instrumentalities and agencies have the public duty to be fair to all concerned. Even

when some defect is found in the decision-making process, the court must exercise its discretionary powers under Article 226 with great caution

and should exercise it only in furtherance of public interest and not merely on the making out of a legal point. The court should always keep the

larger public interest in mind in order to decide whether its intervention is called for or not. Only when it comes to a conclusion that overwhelming

public interest requires interference, the court should interfere.

(iv) 1994 (6) SCC 651 (Tata Cellular v. Union of India):

89.

In G.B. Mahajan and others Vs. The Jalgaon Municipal Council and others, the concept of reasonableness in administrative law came to be

dealt with elaborately by one of us, Venkatachaliah, J. (as he then was). In paragraphs 37 to 41 the Court observed thus:

It was urged that the basic concept of the manner of the development of the real estate and disposal of occupancy rights were vitiated by

unreasonableness. It is a truism, doctrinally, that powers must be exercised reasonably. But as Prof. Wade points out:

The doctrine that powers must be exercised reasonably has to be reconciled with the no less important doctrine that the court must not usurp the

discretion of the public authority which Parliament appointed to take the decision. Within the bounds of legal reasonableness is the area in which

the deciding authority has genuinely free discretion. If it passes those bounds, it acts ultra vires. The court must therefore resist the temptation to

draw the bounds too tightly, merely according to its own opinion. It must strive to apply an objective standard which leaves to the deciding

authority the full range of choices which the legislature is presumed to have intended. Decisions which are extravagant or capricious cannot be

legitimate. But if the decision is within the confines of reasonableness, it is no part of the court''s function to look further into its merits. ""With the

question whether a particular policy is wise or foolish the court is not concerned; it can only interfere if to pursue it is beyond the powers of the

authority""....

In the arguments there is some general misapprehension of the scope of the ''reasonableness'' test in administrative law. By whose standards of

reasonableness that a matter is to be decided? Some phrases which pass from one branch of law to another - as did the expressions ''void'' and

''voidable'' from private law areas to public law situations - carry over with them meanings that may be inapposite in the changed context. Some

such thing has happened to the words ''reasonable'', ''reasonableness'' etc. In Tiller v. Atlantic Coast Line Rail Road Co. 318 US 54 :(1942) 87 L

Ed. 610 , Justice Frankfurter said:

A phrase begins life as a literary expression; its felicity leads to its lazy repetition; and repetition soon establishes it as a legal formula,

undiscriminatingly used to express different and sometimes contradictory ideas.

Different contexts in which the operation of ''reasonableness'' as test of validity operates must be kept distinguished. For instance as the arguments

in the present case invoke, the administrative law test of ''reasonableness'' as the touchstone of validity of the impugned resolutions is different from

the test of the ''reasonable man'' familiar to the law of torts, whom English law figuratively identifies as the ''man on the Clapham omnibus''. In the

latter case the standards of the ''reasonable man'', to the extent such a ''reasonable man'' is court''s creation, is in a manner of saying, a mere

transferred epithet. Lord Radcliffe observed : (All ER p.160)

By this time, it might seem that the parties themselves have become so far disembodied spirits that their actual persons should be allowed to rest in

peace. In their place there rises the figure of the fair and reasonable man. And the spokesman of the fair and reasonable man, who represents after

all no more than the anthropomorphic conception of justice, is, and must be, the court itself....

See Davis Contractors Ltd. v. Fareham U.D.C. (1956 (2) All.E.R. 145 : 1956 AC 696 : (1956) 3 WLR 37).

Yet another area of reasonableness which must be distinguished is the constitutional standards of ''reasonableness'' of the restrictions on the

fundamental rights of which the court of judicial review is the arbiter.

The administrative law test of reasonableness is not by the standards of the ''reasonable man'' of the torts law. Prof. Wade says:

This is not therefore the standard of ""the man on the Clapham omnibus "". It is the standard indicated by a true construction of the Act which

distinguishes between what the statutory authority may or may not be authorised to do. It distinguishes between proper use and improper abuse of

power. It is often expressed by saying that the decision is unlawful if it is one to which no reasonable authority could have come. This is the essence

of what is now commonly called ""Wednesbury unreasonableness"", after the now famous case in which Lord Greene, M.R. expounded it.

90.

Referring to the doctrine of unreasonableness, Prof.Wade says in Administrative Law (supra):

The point to note is that a thing is not unreasonable in the legal sense merely because the court thinks it is unwise.

91.

In Food Corporation of India Vs. M/s. Kamdhenu Cattle Feed Industries, it was observed thus : (SCC p.76, para 7)

In contractual sphere as in all other State actions, the State and all its instrumentalities have to conform to Article 14 of the Constitution of which

non-arbitrariness is a significant facet. There is no unfettered discretion in public law : A public authority possesses powers only to use them for

public good. This imposes the duty to act fairly and to adopt a procedure which is ''fairplay in action''.

92.

In Sterling Computers Limited and Others Vs. M and N Publications Limited and Others, this Court observed thus : (SCC p.455, para 12)

In contracts having commercial element, some more discretion has to be conceded to the authorities so that they may enter into contracts with

persons, keeping an eye on the augmentation of the revenue. But even in such matters they have to follow the norms recognised by courts while

dealing with public property. It is not possible for courts to question and adjudicate every decision taken by an authority, because many of the

Government Undertakings which in due course have acquired the monopolist position in matters of sale and purchase of products and with so

many ventures in hand, they can come out with a plea that it is not always possible to act like a quasi-judicial authority while awarding contracts.

Under some special circumstances a discretion has to be conceded to the authorities who have to enter into contract giving them liberty to assess

the overall situation for purpose of taking a decision as to whom the contract be awarded and at what terms. If the decisions have been taken in

bona fide manner although not strictly following the norms laid down by the courts, such decisions are upheld on the principle laid down by Justice

Holmes, that courts while judging the constitutional validity of executive decisions must grant certain measure of freedom of ''play in the joints'' to

the executive.

93.

In Union of India and others Vs. Hindustan Development Corpn. and others, this Court held thus : (SCC p.515, para 9)

...the Government had the right to either accept or reject the lowest offer but that of course, if done on a policy, should be on some rational and

reasonable grounds. In Erusian Equipment and Chemicals Ltd. Vs. State of West Bengal and Another, this Court observed as under : (SCC p.75,

para 17)

When the Government is trading with the public, ""the democratic form of Government demands equality and absence of arbitrariness and

discrimination in such transactions"". The activities of the Government have a public element and, therefore, there should be fairness and equality.

The State need not enter into any contract with anyone, but if it does so, it must do so fairly without discrimination and without unfair procedure.

94.

The principles deducible from the above are:

(1) The modern trend points to judicial restraint in administrative action.

(2) The court does not sit as a court of appeal but merely reviews the manner in which the decision was made.

(3) The court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be

substituting its own decision, without the necessary expertise which itself may be fallible.

(4) The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract. Normally

speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than not,

such decisions are made qualitatively by experts.

(5) The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body

functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of

Wednesbury principle of reasonableness (including its other facts pointed out above) but must be free from arbitrariness not affected by bias or

actuated by mala fides.

(6) Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure.

Based on these principles we will examine the facts of this case since they commend to us as the correct principles.

151.

In the above two cases, we are obliged to interfere on the ground of arbitrariness and violation of the principle of natural justice confining

ourselves to the doctrine of judicial restraint, however, by the application of permissible parameters to set right the decision-making process.

(v) Union of India and Others Vs. Dinesh Engineering Corporation and Another etc., :

15.

Coming to the second question involved in these appeals, namely, the rejection of the tender of the writ petitioner, it was argued on behalf of

the appellants that the Railways under Clause 16 of the Guidelines was entitled to reject any tender offer without assigning any reasons and it also

has the power to accept or not to accept the lowest offer. We do not dispute this power provided the same is exercised within the realm of the

object for which this clause is incorporated. This does not give an arbitrary power to the Railways to reject the bid offered by a party merely

because it has that power. This is a power which can be exercised on the existence of certain conditions which in the opinion of the Railways are

not in the interest of the Railways to accept the offer. No such ground has been taken when the writ petitioner''s tender was rejected. Therefore,

we agree with the High Court that it is not open to the Railways to rely upon this clause in the Guidelines to reject any or every offer that may be

made by the writ petitioner while responding to a tender that may be called for supply of spare parts by the Railways. Mr. Iyer, learned Senior

Counsel appearing for EDC drew our attention to a judgment of this Court in Sterling Computers Limited and Others Vs. M and N Publications

Limited and Others, which has held: (SCC p.455, para 12)

Under some special circumstances a discretion has to be conceded to the authorities who have to enter into contract giving them liberty to assess

the overall situation for purpose of taking a decision as to whom the contract be awarded and at what terms. If the decisions have been taken in

bona fide manner although not strictly following the norms laid down by the courts, such decisions are upheld on the principle laid down by Justice

Holmes, that courts while judging the constitutional validity of executive decisions must grant certain measure of freedom of ''play in the joints'' to

the executive.

16.

But then as has been held by this Court in the very same judgment that a public authority even in contractual matters should not have unfettered

discretion and in contracts having commercial element even though some extra discretion is to be conceded in such authorities, they are bound to

follow the norms recognised by courts while dealing with public property. This requirement is necessary to avoid unreasonable and arbitrary

decisions being taken by public authorities whose actions are amenable to judicial review. Therefore, merely because the authority has certain

elbow room available for use of discretion in accepting offer in contracts, the same will have to be done within the four corners of the requirements

of law, especially Article 14 of the Constitution. In the instant case, we have noticed that apart from rejecting the offer of the writ petitioner

arbitrarily, the writ petitioner has now been virtually debarred from competing with EDC in the supply of spare parts to be used in the governors by

the Railways, ever since the year 1992, and during all this while, we are told the Railways are making purchases without any tender on a

proprietary basis only from EDC which, in our opinion, is in flagrant violation of the constitutional mandate of Article 14. We are also of the

opinion that the so-called policy of the Board creating monopoly of EDC suffers from the vice of non-application of mind, hence, it has to be

quashed as has been done by the High Court.

(vi) B.S.N. Joshi and Sons Ltd. Vs. Nair Coal Services Ltd. and Others, .

69.

...Whether an employer has power of relaxation must be found out not only from the terms of the notice inviting tender but also the general

practice prevailing in India. For the said purpose, the court may consider the practice prevailing in the past. Keeping in view a particular object, if

in effect and substance it is found that the offer made by one of the bidders substantially satisfies the requirements of the conditions of notice inviting

tender, the employer may be said to have a general power of relaxation in that behalf. Once such a power is exercised, one of the questions which

would arise for consideration by the superior courts would be as to whether exercise of such power was fair, reasonable and bona fide. If the

answer thereto is not in the negative, save and except for sufficient and cogent reasons, the writ courts would be well advised to refrain themselves

in exercise of their discretionary jurisdiction.

(vii) M. Vasudevan Vs. The Chief Executive Officer, Chennai Metropolitan Development Authority, D. Jayakumar and Genguva Rajan, :

8.

Learned Counsel for the petitioner/appellant then submitted that the eligibility requirement has been relaxed by the first respondent just to suit the

third respondent. In this connection we asked the learned senior counsel whether there were any rules prescribing the eligibility qualification and he

informed us that there appeared to be none. In the absence of any rules it is open to the authorities to change the eligibility requirements and this

Court cannot interfere in this connection. In Sterling Computers Limited and Others Vs. M and N Publications Limited and Others, it was held by

the Supreme Court vide paragraph 12 as follows:

Under some special circumstances a discretion has to be conceded to the authorities who have to enter into contract giving them liberty to assess

the overall situation for purpose of taking a decision as to whom the contract be awarded and at what terms. If the decisions have been taken in

bona fide manner although not strictly following the norms laid down by the courts, such decisions are upheld on the principle laid down by Justice

Holmes, that courts while judging the constitutional validity of executive decisions must grant certain measure of freedom of ''play in the joints'' to

the executive.

9.

In this case the first respondent on a consideration of the overall situation decided to relax the eligibility requirements, and in our opinion it

cannot be said that it did not act bona fide in this connection.

10.

It must be understood that the contract in question was not a contract for some highly specialised work such as setting up a highly technical

factory or establishment. It was only a contract for collection of parking fee which cannot be said to be a very highly specialised work. Hence in

this situation the eligibility requirement can certainly be relaxed as it would not have much effect on the contract involved.

11.

At any event it is not for this Court to interfere in such administrative decisions and the Court must exercise judicial restraint as held in a

Division Bench decision of this Court in Rama Muthuramalingam, State Propaganda Committee Member Vs. The Deputy Superintendent of Police

and Others, .

(viii) Noble Resources Ltd. Vs. State of Orissa and Another, :

15.

It is trite that if an action on the part of the State is violative the equality clause contained in Article 14 of the Constitution of India, a writ

petition would be maintainable even in the contractual field. A distinction indisputably must be made between a matter which is at the threshold of a

contract and a breach of contract; whereas in the former the court''s scrutiny would be more intrusive, in the latter the court may not ordinarily

exercise its discretionary jurisdiction of judicial review, unless it is found to be violative of Article 14 of the Constitution. While exercising

contractual powers also, the government bodies may be subjected to judicial review in order to prevent arbitrariness or favouritism on its part.

Indisputably, inherent limitations exist, but it would not be correct to opine that under no circumstances a writ will lie only because it involves a

contractual matter.

59.

I have given my careful consideration to the submissions made by the learned Counsel on either side and also given due consideration to the

various rulings of the Supreme Court and this Court and the provisions of the and the Tamil Nadu Transparency in Tenders Rules, 2000. I have

also perused the materials and the records placed before this Court.

60.

It is seen that the first Tender Document which contains the ""description of works"", dated 21.12.2006 (hereinafter referred to as ''the first

tender'') issued by the Government of Tamil Nadu, Fisheries Department, provided as follows:

For and on behalf of the Governor of Tamil Nadu, sealed tenders are invited by the Special Commissioner of Fisheries, Government of Tamil

Nadu, Administrative Office Buildings, Teynampet, Chennai 6 ONLY FROM THE MANUFACTURES OF NETS (WEBBINGS) WITH A

PRODUCTION CAPACITY OF NOT LESS THAN 1250 METRIC TONNES PER ANNUM for the description of works specified

hereunder and as per the specifications, terms and conditions mentioned in this tender document.

Description of works

FOR THE SUPPLY OF 1100 METRIC TONNES OF KNOTTED GILL NETS (ONLY WEBBINGS) APPROVED BY BIS WITH THE

FOLLOWING SPECIFICATIONS:

S. No. Type of Material Twine size Stretched Mesh size in mm

1 Nylon Multifilament 210/1/2 30

2 Nylon Monofilament 0.16 mm dia 27

3 Nylon Monofilament 0.16 mm dia 36

4 Nylon Multifilament 210/1/2 36

5 Nylon Monofilament 0.23 mm dia 56

6 Nylon Multifilament 210/1/3 56

Other conditions:

Webbings and Twines used should be of BIS Standards and specifications.

61.

Again, the Government of Tamil Nadu, Department of Fisheries issued a Tender Document which contains the ""description of works"", dated

25.4.2007 (hereinafter referred to as ''the first re-tender'') provided as follows:

For and on behalf of the Governor of Tamil Nadu, sealed tenders are invited by the Director of Fisheries, Government of Tamil Nadu,

Administrative Office Buildings, Teynampet, Chennai 6 ONLY FROM THE MANUFACTURES OF NYLON WEBBINGS WITH A

PRODUCTION CAPACITY OF NOT LESS THAN 600 METRIC TONNES PER ANNUM for the description of works specified hereunder

and as per the specifications, terms and conditions mentioned in this tender document.

Description of works

FOR THE SUPPLY OF 1100 METRIC TONNES OF KNOTTED NYLON WEBBINGS AS PER THE FOLLOWING

SPECIFICATIONS:

S. No. Type of Material Twine size Stretched Mesh size in mm

1 Nylon Multifilament 210 d x 1 x 2 30

2 Nylon Monofilament 0.16 mm dia 27

3 Nylon Monofilament 0.16 mm dia 36

4 Nylon Multifilament 210 d x 1 x 2 36

5 Nylon Monofilament 0.23 mm dia 56

6 Nylon Multifilament 210 d x 1 x 3 56

1.

Nylon webbings should be made up of Nylon twines/monofilament yarn of BIS specifications (i.e)

Nylon Multifilament (Twine) : IS 4401 : 2006

Nylon Monofilament : IS 7533 : 2003

2.

The webbing should be made up of virgin Polyamide (Nylon) twine/yarn.

3.

Recycled raw material (Nylon) should not be used for making webbings.

62.

Once again, the Government of Tamil Nadu, Department of Fisheries issued a Tender Notice which contains the ""description of works"", dated

21.8.2007 (hereinafter referred to as ''the second re-tender'') provided as follows:

For and on behalf of the Governor of Tamil Nadu, sealed tenders are invited for the supply of 1100 MTS of double knotted nylon nets (webbings)

from the manufacturers only under Fixed Rate Contract System by the Director of Fisheries, Chennai-6.

63.

The above said tenders were meant for supply of 1100 MT double knotted nets (webbings) only to the already benefited Tsunami affected

fishermen of the Tamil Nadu showing the place of execution as 13 coastal Districts of Tamil Nadu. All the above said three tender notifications

contained two parts, namely (i) the technical bids and (ii) price bid.

64.

It is to be noted that the eligibility criteria for the bidders providing a condition in the second re-tender dated 21.8.2007 provides the following

conditions:

a) The bidder shall be a registered manufacturer having a minimum individual annual production capacity of 100 MTs of nylon (Polyamide) nets

(Double knotted Nylon webbings) in the ratio of 60% monofilament : 40% multifilament nylon nets (Double knotted Nylon webbings) of the

specified description in the tender schedule and having experience in the production and marketing of the webbings of the specifications described

in the tender document for a minimum period of 3 years.

b) Alliance of agreement of any type with any manufacturer / dealer / distributor dealing with the said nylon webbings like Consortium / lease /

rent/joint venture etc. shall be rejected.

c) The bidders should provide samples in a separate cover of multifilament twines and monfilament yarn for making knotted nylon webbings and

also samples of the webbings of the descriptions specified in the tender document made out of the above indicated twines / yarns along with tender

document.

65.

Admittedly, the coastal Tamil Nadu was hit by Tsunami on 26.12.2004, which caused havoc to the life and fishing implements of the fishermen

in the entire coastal Districts. As the damage caused is heavy, the Government has taken various rehabilitation measures to the fishermen for

repairing their nets for rejuvenating their lost fishing implements. It is also to be seen that about 42,000 fishermen were given the relief assistance

sanctioned under various Government Orders. The Government of Tamil Nadu, in G.O.Ms. No. 193, Animal Husbandry, Dairying and Fisheries

Department, dated 22.11.2006, has sanctioned a sum of Rs. 110.36 crores for purchase and supply of the following, to the already benefited

Tsunami affected fishermen, which qualify for assistance under ""Rajiv Gandhi Rehabilitation Package"":

(i) Nets (webbings) - 1100 MTs

(ii) Handy rechargeable lantern.

(ii) Heavy duty bicycles.

(iii) Life jackets.

(iv) Insulated ice boxes.

A sum of Rs. 44 crores out of the total sanction of Rs. 110.36 corres, has been allocated for the supply of nets (webbings) to the already benefited

Tsunami affected fishermen under the above said Rajiv Gandhi Rehabilitation Package. The total loss of nets, due to Tsunami, was actually

assessed as 1100 MTs. Therefore, the Government has proposed to purchase and supply 25 Kgs. of Gill Nets worth about Rs. 10,000/- to each

beneficiary. Accordingly, the Government in G.O.Ms. No. 193, Animal Husbandry, Dairying and Fisheries Department, dated 22.11.2006, issued

orders constituting three Committees, namely (i) Technical Committee, (ii) Scrutinizing Committee and (iii) Award Committee, which comprised of

the following officials, as seen from Annexure-II to the G.O:

1.

TECHNICAL COMMITTEE:

(a) Net

1.

The Special Commissioner, Chairman of the Committee.

2.

Director or his representative from CIFNET

3.

Zonal Director or his representative of FSI, Chennai.

4.

Joint Director (Marine)-Member Secretary.

(b) Ice Box

1.

The Special Commissioner, Chairman of the Committee.

2.

Director or his representative from MPEDA.

3.

Director or his representative from CIFT, Cochin.

4.

Director, South Indian Fisheries Federation Society, Trivandrum.

5.

Joint Director (Marine)-Member Secretary.

(c) Rechargeable Lantern

1.

The Special Commissioner, Chairman of the Committee.

2.

Director or his representative of TNMB

3.

Representative from ELCOT

4.

Director or his representative of Mercantile Marine Department

5.

Joint Director (Marine)-Member Secretary.

(d) Heavy Duty Bicycles

1.

The Special Commissioner, Chairman of the Committee.

2.

Director or his representative from the Department of Adi Dravida Welfare.

3.

Director or his representative from Department of Industries and Commerce.

4.

Joint Director (Marine)-Member Secretary.

(e) Life Jacket:

1.

The Special Commissioner, Chairman of the Committee.

2.

Director or his representative from CIFNET.

3.

Director or his representative of Mercantile Marine Department.

4.

Joint Director (Marine)-Member Secretary.

2.

SCRUTINIZING COMMITTEE:

1.

The Special Commissioner, Chairman of the Committee.

2.

Joint Directors (Marine, Inland and Research).

3.

A.O. of Fisheries Department.

4.

Deputy Director (Marine)-Member Secretary.

3.

AWARD COMMITTEE:

1.

Special Commissioner of Fisheries, Chairman

2.

Secretary to Government, Animal Husbandry, Dairying and Fisheries Department.

3.

Secretary to Government or his/her nominee, Finance Department.

66.

There is no dispute about the procedure in the publication of the tender documents/notifications as contemplated under the and the Tamil Nadu

Transparency in Tenders Rules, 2000. It is also not in dispute that there were three tender notifications, initially, inviting tender dated 21.12.2006

from the manufacturers of webbings with a production capacity of 1250 MTs per annum, thereafter, with 600 MT per annum as per the first re-

tender dated 25.4.2007, and thereafter by second re-tender dated 21.8.2007 having a minimum individual annual production capacity of 100

MTs. The assessment and the testings were as per the Committees'' recommendations, which are stated to have been done scrupulously and the

samples were received from the CIPET and the tenders were evaluated by the Scrutinizing Committee. The manufacturing plant of the petitioner-

Garware Wall Ropes Ltd., was inspected on 7.2.2007. The Committee recommended to conduct the ""breaking load test"" of the samples as per

the specification by the CIPET and the test report on breaking load was received from CIPET in respect of the petitioner-Garware Wall Ropes

Ltd. on 23.3.2007 and the same was evaluated by the Tender Scrutinizing Committee on 3.4.2007. It is also seen that based on the

recommendations of the Committee, the price bid of the technically qualified tenderer was opened on 4.4.2007 and negotiation of rates was done

with the tenderer on 10.4.2007. As per the recommendations of the Tender Scrutinizing Committee, technical bids and price bids were placed

before the Tender Award Committee in its meeting held on 12.4.2007 and the Tender Award Committee took note of the information given by the

scientists (experts) from CIFT, Cochin and CIPET, Chennai, stating that there were no BIS specification for webbings, unlike twines. However,

the BIS test procedure is available for both webbings and twines and since the BIS specifications were not prescribed for webbings, the technical

requirements under this tender cannot be evaluated. Therefore, the Award Committee recommended to go in for re-tender and the tender dated

21.12.2006 was cancelled.

67.

The first re-tender was called on 25.4.2007. In the first re-tender, the supply was restricted to 1100 MT of knotted nylon webbings, from the

manufacturers of nets (webbings) with a production capacity of not less than 600 MT per annum and the nylon webbings should be made up of

Nylon twines/monofilament yarn of BIS specification, namely Nylon Multifilament (Twine) : IS 4401 : 2006 and Nylon Monofilament : IS

7533:2003. In this first re-tender, the Tender Scrutinizing Committee recommended to fix the production capacity as 600 MTs/annum in view of

the fact that only one responsive bid was received for the first tender in which the production capacity was fixed as 1250 MTs/annum, considering

the uniqueness of the purchase in terms of volume which needs to be supplied within one year. Accordingly, the re-tenders were published in the

leading dailies on 25.4.2007.

68.

It is to be stated that in the above said first re-tender dated 25.4.2007 the procedural aspects are not all disputed by the parties, as the same

were contemplated by the provisions of the Tamil Nadu Transparency in Tenders Act, 1998 and the Tamil Nadu Transparency in Tenders Rules,

2000.

69.

Totally, three tenders were received from the petitioners herein, namely M/s.Garware Wall Ropes Pvt. Ltd., Pune (petitioner in W.P. No.

28827 of 2007) and M/s.Kassim Nets, Nagercoil (petitioner in W.P. Nos. 27258 and 28485 of 2007), apart from one M/s.Kumaran Fish Nets

Private Ltd., Nagercoil, which has not come before this Court. The manufacturing plants of M/s.Kassim Nets, Nagercoil and M/s.Kumaran Nets,

Nagercoil were inspected on 2.6.2007 and 22.6.2007 respectively. The samples which were sent to CIFT, Cochin were confirmed on 11.7.2007

for the BIS specifications.

70.

In the meanwhile, a complaint was received questioning the production capacity of the writ petitioner-M/s.Garware Wall Ropes Pvt. Ltd. A

team of officials were deputed by the Tender Scrutinizing Committee to assess the veracity of the complaint and the plant of M/s.Garware Wall

Ropes Pvt. Ltd. was re-inspected, and the said team found that the petitioner-M/s.Garware Wall Ropes Pvt. Ltd. did not possess the capacity

stated in the first re-tender document dated 25.4.2007, namely the production capacity of not less than 600 MT/p.a. Thereafter, it is seen that the

Scrutinizing Committee has evaluated the technical bids, inspection reports of all the tenderers and the test reports on the samples and since no one

was found qualified in evaluation process by the Tender Scrutinizing Committee, the tenders of all the three tenderers including the petitioner-

M/s.Garware Wall Ropes Pvt. Ltd. were rejected.

71.

It is further seen that on that background, the Tender Scrutinizing Committee, in its meeting held on 9.8.2007, has made certain

recommendations, namely that, by experience in the previous two tenders, there were no suitable suppliers even after the reduced production

quantity of 600 Mts/year as eligibility criteria; 1100 MTs. of nylon webbings have to be distributed to the fishermen within a timeframe of one year;

to ensure better participation in tender and going by the previous experience, that there is no suitable manufacturer with the production capacity of

1250 MT/annum and 600 MT/annum, the production capacity may be reduced to 100 MT/annum and that the Government may be addressed to

permit the third respondent-Director of Fisheries to go for re-tender under Fixed Rate Contract System and to reduce the production capacity to

100 MTs/annum (60% monofilament : 40% multifilament) of webbings of specified description in the tender and also to reduce the time limit to 15

days for inviting tenders, since the tender call is for the third time and all the manufacturers were aware of the supply of webbings to the ""already

benefited Tsunami affected fishermen"". Hence, the second re-tender stood cancelled on 17.8.2007 and the EMDs were returned.

72.

The various conditions as seen from the earlier tenders (tender dated 21.12.2006 and the first re-tender dated 25.4.2007) and the experience

as well as the requirement and the time period, have all been taken into account. Therefore, the respondents have proceeded to call for the second

re-tender dated 21.8.2007 with due publication in the dailies and hereagain, the procedural aspects are not in dispute.

73.

The second re-tender dated 21.8.2007 prescribed certain specific eligibility criteria, taking note of the earlier experience with the technical

bids, inspection report as well as the test reports and they prescribed certain conditions, namely that (i) the bidder shall be a registered

manufacturer having a minimum individual annual production capacity of 100 MTs of nylon (Polyamide) nets (Double knotted Nylon webbings) of

the specified description in the tender schedule and having experience in the production and marketing of the webbings of the specifications

described in the tender document for a minimum period of three years; (ii) alliance of agreement of any type with any

manufacturer/dealer/distributor dealing with the said nylon webbings like consortium/lease/rent/joint venture etc. shall be rejected and (iii) the

bidders should provide samples in a separate cover of multifilament twines and monofilament yarn for making knotted nylon webbings and also

samples of the webbings of the descriptions specified in the tender document made out of the above indicated twines/yarn along with tender

document.

74.

The above reasonings were based on the previous bitter experience with the tenderers/manufacturers, the required annual production capacity,

which emanated the respondents to go in for re-tenders or not. Logical conclusions have been arrived at by the respondents and this Court has to

iron out the creases in the said conclusion as to whether there is any arbitrariness or mala-fide exercise or the tender process is actuated by any

malice and this Court has to further delve upon as to whether the re-tender was necessitated only due to the ineligibility of the tenderers, it is only

inevitable to achieve the Government''s object to give benefit to the mass-affected fishermen of the coastal Districts of the Tamil Nadu under the

national calamity/havoc Tsunami. The capacity of the petitioner-M/s.Garware Wall Ropes Ltd., is not as per the requirement of the tender

document. It is still worse the case of the petitioner-Kassim Nets that they did even come nearer to the requirement of the tender document. The

respondents have taken an inexorable decision to go in for second re-tender, taking into consideration the information placed before the

Committees.

75.

Since there was a complaint against the petitioner-M/s.Garware Wall Ropes Ltd., a team of three officials, namely DRO, GM from TNFDC, a

head of the fish net manufacturing plant and Technician working in the fish net manufacturing plant of TNFDC, inspected the plant of the petitioner-

M/s.Garware Wall Ropes Ltd. Though the petitioner-M/s.Garware Wall Ropes Ltd. claimed that it had 110 machines in the big factory at Wai, it

had only shown 15 machines from which the webbings for the specified descriptions in the tender can be produced.

76.

In the case of Kassim Nets, it is seen that the production capacity as submitted in its tender document is only 420 MT per annum. To meet the

tender requirement of 1250 MT production capacity of webbings, the petitioner has entered into a consortium type of agreement with 15 other

manufacturers from Tamil Nadu Nadu and Karnataka and showed that as consortium as the combined production capacity as 4,524 MT per

annum which is against the tender conditions. Since there are no BIS specifications for webbings, the Tender Award Committee has decided to go

in for retenders in its meeting held on 12.04.2007. Further, it is seen that the petitioner''s averment in the affidavit that it is having the required

production capacity of 1250 MT per annum on its own, is wrong and the petitioner has given a statement contrary to the consortium type of

agreement with 15 other manufacturers and therefore, the production capacity has been shown wrongly only for the purpose of this writ petition.

Therefore, in the absence of such production capacity of its own as per the requirement of the tender notification, it has no valid ground to contest

the matter. Further, in the re-tender notification dated 25.04.2007 the production capacity has been reduced to 600 MT per annum was arrived

based on the previous experience and only one responsive bid was received in the first tender call and after detailed discussions to ensure quick

and quality procurement of nets (webbings) and more responsive participation and competitive rates, the respondent has decided to go for re-

tender. Also, as per the evaluation of technical bid and to confirm the veracity of the details furnished in the document, physical inspection of the

plants of the tenderers was made. It was from the documentary evidence the petitioner has produced in support of his claim that it has taken two

net manufacturing plants, viz., Net Park and Ajanta Fish Nets on lease. Also, according to the respondent, certain discrepancies were found in the

documentary evidence which led to inspection of the plant to ascertain whether lease has been effectively entered into. During inspection of the

plant on 02.06.2007, the petitioner did not produce any documentary evidence before the inspection team to show that it has really entered into

lease agreement which will be effective from 1st April 2007 onwards with other two companies. One more important aspect of the matter is that

one of the lessees i.e. Ajanta Fish Nets is functioning in the SIDCO Industrial Estate at Nagercoil and hence, a report from the General Manager,

SIDCO, Nagercoil was obtained to ascertain whether the above firm has really been taken on lease by the petitioner. The General Manager,

SIDCO informed that the firm is still run as a proprietary unit by one Thangaraj, the real owner. Therefore, the respondent has come to the

conclusion that the petitioner has not entered into lease agreement with the above firm but the draft lease deed produced by it is only for

convenience sake and to make the respondent believe that he has the required production capacity of 600 Mts per annum specified in the tender

document of the re-tender call dated 25.04.2007.

77.

It is further seen that during the first inspection of the petitioner plant, it did not produce the documents for taking lease of the plants. But,

during second inspection on 08.06.2007 which was based on its request, it has produced some documents to show that it has paid the lease rent,

etc. to the lessee. But, on verification of the documents, it was found that they have been fabricated to mislead the respondent. Refundable deposit

and monthly lease rent have not been paid in order to have the lease come into effect as per the terms of reference in the lease deed. Since the

lease of two other net manufacturing firms has not come into force during the time of submission of re-tender, it is clear that the petitioner''s claim

for average production capacity of 1044 MT per annum is not at all based on any valid document Therefore, the respondent has concluded that

the petitioner is not having the required production capacity as per the tender notification. The reported lease agreement was done only for the

sake of convenience and self-serving for arriving at the required production capacity of 600 MT per annum and this conclusion of the respondent

appears to be reasonable particularly in the absence of required production capacity and the petitioner has, in no way, convinced on the aspect of

specification of the required tender conditions. Therefore, looked at from any angle, I am of the considered view that the petitioner''s claim and the

challenge made therein are not at all based on the proper claim made by the petitioner. Accordingly, in the absence of required production capacity

with proper quality and standard and on evaluation of the technical bid as per the criteria, the respondent has come to the conclusion that the

petitioner has not fulfilled the tender specification and this stand taken by the respondent for re-tender based on recommendations of the

Committee, keeping in mind the need for quick and immediate supply of fishing nets, is in no way infirmed.

78.

Thus, it can be seen that neither the petitioner-M/s.Garware Wall Ropes Ltd. nor the petitioner-Kassim Nets was proved eligible tenderers

with the required annual capacity. It is evident that a decision has been arrived at as per the expert Committee''s opinion exclusively constituted for

the purpose of exploring the possibility of getting an ''outstanding tenderer'' for the ''already benefited Tsunami affected'' fishermen.

79.

The decision of the authorities to call for the re-tender(s) is based on the paramount public interest which prevails among other things being

equal, and to ensure wider participation by the tenderers. The object sought to be achieved for supply of the fishing implements, particularly the

webbings to the Tsunami affected fishermen, the expeditious implementation of the rehabilitation measures, besides the production capacity with

proper mesh size being indicated, etc., have all been re-silted by the experts in their sample analysis. As there is no material reasons actuated by

malice or any mala-fide intention to gain out of the rehabilitation measure(s) for the social cause and when the petitioners do not possess the

required capacity of production, the reasons for taking such a re-course of re-tender, cannot be found fault with, as there is ''great and greater

public interest'' involved in the tender process for the Tsunami affected fishermen. The democratic Government being a public-oriented agency, in

all fairness, took into consideration the various aspects in a transparent manner, to achieve its avowed object of implementation of supply of fishing

nets to the Tsunami affected fishermen and this is the omnipotent reason for the Government to go in for a better participation of the tenderers with

BIS specifications, by calling for re-tender(s). Thus, it is evident from the foregoing that there is no arbitrariness in the re-tender(s) process.

80.

I have given my anxious and careful consideration to the various decisions relied on by either side and the principles enunciated therein.

81.

It is relevant to note that the respondents have scrupulously followed the provisions of the with the Tamil Nadu Transparency in Tenders Rules,

2000, in particular, Rule 27 relating to the process of tender evaluation to be confidential until the award of the contract is notified.

JUDICIAL REVIEW/RESTRAINT:

82.

To examine the principle laid down by the Supreme Court in Tata Cellular case and the scope of judicial review/restraint, the underlying

principles are:

(i) The administrative action of the respondents in this case cannot be interfered with by this Court in view of the modern trend points to judicial

restraint, as this Court is not sitting as a Court of appeal but merely, reviews the manner in which the decision was made.

(ii) The Court does not have the expertise to correct the administrative decision and if a review of the administrative decision is permitted, it will be

substituting its own decision, without the necessary expertise which itself may be fallible.

(iii) The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract.

(iv) The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body

functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of

Wednesbury principle of reasonableness, but must be free from arbitrariness not affected by bias or actuated by mala-fides.

(v) By way of judicial review, the Courts cannot examine the details of the terms of the contract which have been entered into by the public bodies

or the State. Courts have inherent limitations on the scope of any such enquiry.

83.

While applying the above principles, it is seen that in the absence of any arbitrariness not affected by bias or actuated by mala-fides, and when

there is no material placed before this Court to establish that there is arbitrariness, the decision-making process appears to be proper, besides the

same being in conformity with the law laid down by this Court and the Apex Court. Taking note of the fact that if any decision at this stage will

cause heavy administrative burden on the Government exchequer and leads to increased and unbudgeted expenditure, the tender notifications

cannot be quashed at this re-tender stage. In the circumstances, taking note of the rehabilitation from Tsunami affected in the coastal areas of the

State of Tamil Nadu and the object sought to be achieved at the earliest, which cannot be stalled by any mala-fide approach of the petitioners and

if any such action is permitted, it will definitely impose heavy administrative burden not only on the Government, but also deprive the very benefit of

the scheme to reach the Tsunami affected fishermen, which is a natural calamity in the world, which has to be rehabilitated as fast as the thunder-

lights reach the earth soon, which in this case, admittedly, has been belated for one reason or the other at the instance of one party or the other.

84.

Therefore, I do not find any arbitrariness or unreasonableness or any material actuated by malice. I have also perused the various decisions of

the Supreme Court and considering the judicial restraint in the matter, I have no reason to interfere with the public contract, that too which is at the

nascent stage. The scope of judicial review being very limited under Article 226 of the Constitution of India.

85.

Power of relaxation:

(i) The Supreme Court has cautioned that only in rarest of rare cases, that too when there is mala-fide on the face of it, then and then only the

exercise of power under Article 226 can be made. In the absence of any mala-fide being complained of by the petitioners, I do not propose to

relax the tender conditions, as the invitation to tender is in the realm of contract, especially when the provisions of the Tamil Nadu Transparency in

Tenders Act, 1998 and the Tamil Nadu Transparency in Tenders Rules, 2000 have been followed with proper perspective and the respondents

have acted as ""beacon light"" to wipe out the obstacles of the fishermen in getting their nets twined, who suffer even for a one-square meal a day for

eking out their livelihood.

(ii) As stated by the Supreme Court in its judgment reported in B.S.N. Joshi and Sons Ltd. Vs. Nair Coal Services Ltd. and Others, , whether an

employer has power of relaxation must be found out not only from the terms of the notice inviting tenders, but also the general practice prevailing in

India. For the said purpose, the Court may consider the practice prevailing in the past and keeping in view a particular object, if in effect and

substance, it is found that the offer made by one of the bidders substantially satisfies the requirements of the conditions of notice inviting the tender,

the employer may be said to have a general power of relaxation in that behalf and when once such power was fair, reasonable and bona-fide, and

if the answer thereto is not in the negative, save and except for sufficient and cogent reasons, the Writ Courts would be well advised to refrain

themselves in exercise of their discretionary jurisdiction. It is seen that the offer made by one of the better specialised conditions of notice inviting

tenders and keeping in view the object sought to be achieved effectively and in substance, it is found that the offer made by the parties is based

upon the requirement of the production capacity per annum, as stated in the impugned tender notifications, the power of relaxation is available with

the Government, which is at liberty to issue re-tender according to the whims and fancies of the needs of the ''already benefited Tsunami affected

fishermen'' who expect the implementation of the G.O. Furthermore, there is no arbitrary exercise of power by the respondents, in relaxing the

production capacity from 1250 to 100 MT per annum.

86.

Articles 14/19 of the Constitution:

(i) It is not the case of the petitioners that they have been discriminated against or there is any violation of principles of natural justice enshrined

under Articles 14 and 19 of the Constitution of India. From the inception of original tender dated 22.11.2006 till the stage of second re-tender

dated 21.8.2007, it appears that there was initially one person, with the subsequent tenderers following suit, and all of them were taken into

consideration. There has also been a wider participation and the respondents have acted in an impartial and unbiased manner.

(ii) There is no power of this Court to act as an appellate authority by substituting its opinion in respect of selection made for entering into such

contract. But, once the procedure adopted by an authority for purpose of entering into a contract is held to be against the mandate of Article 14 of

the Constitution, the Courts cannot ignore such action saying that the authorities concerned must have some latitude or liberty in contractual matters

and any interference by Court amounts to encroachment on the exclusive right of the executive to take such decision.

87.

Decision-making process:

The decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than not, such

decisions are made qualitatively by experts. Normally, while exercising the power of judicial review, in respect of the Government contracts

entered into for and on behalf of the State, primarily, it has to be seen as to whether there has been any infirmity in ""the decision-making process"".

The Courts can certainly examine whether ""decision-making process"" is reasonable, rational, arbitrary and violative of the principles of law. In this

case, in my view, the ""decision-making process"" has been properly exercised after taking note of the recommendations of several committees, with

great caution, keeping in mind the fulfilment of the rehabilitation measures of the Government both at the Centre and the State.

88.

Public interest:

Taking note of the public interest as well as the Government''s rehabilitation scheme which aims to implement the same faster for getting proper

purchase of the materials and supply to the needy fishermen and considering the object of the Government, the respondents have given due

consideration for wider participation of the tenderes and are ensuring to get the things done at the earliest by getting quality fishing nets with BIS

specifications mentioned in the tender schedules and hence, they reduced the production capacity by three tender processes within a period of

three years and if the manufacturers are in a position to supply quality nets, the same shall reach the ""already benefited Tsunami affected fishermen

expeditiously.

89.

The principles laid down by the Supreme Court in Sterling Computers case, Tata Cellular case, Global Energy case and B.S.N. Joshi & Sons

case are all guiding factors while deciding a contract of this nature and in the matter of judicial scrutiny, the power of relaxation and the scope of

interference in the Government contract has been carefully analysed in these judgments and I have given due consideration to the same.

90.

In view of what has been stated above, keeping in mind, the paramount public interest and taking note of the natural calamity which devastated

the coastal district of Tamil Nadu hit by Tsunami and thousands of fishermen have been affected. Therefore, the State of Tamil Nadu has taken as

a rehabilitation measure to provide benefits to the Tsunami-affected fishermen by providing fishing nets and other implements for which they have

now invited and processed tender documents. Two of its earlier tender processes have given some experience and they have analysed the quality

and standard of fishing nets (webbings) and the required production capacity within the time limit stipulated in order to give speedy relief measures

and therefore, they have taken a decision based on the Committee''s recommendations and analysed the pros and cons of the importance of the

measures to the Tsunami affected fishermen and accordingly, a decision has been arrived at and concluded to go for a re-tender process with a

required production capacity, specification and quality. In the absence of any arbitrariness or mala fides and when the decision especially in the

matter of the power of the respondent to relax which is not actuated with malice and when there is no discrimination and the terms of invitation to

tender cannot be open to judicial scrutiny since the invitation to tender is in the realm of contract and the Government must have freedom in matters

such as this and the decision of the Government must be tested not only by the Wednesbury principle of reasonableness but also should be free

from arbitrariness not affected by bias or actuated by mala fides, this Court is not all inclined to interfere in the tender process when the decision-

making process was in accordance with the various analysis and recommendations by the two Committees constituted by the Government.

Therefore, I have no reason to interfere with their decision especially under Article 226 of the Constitution of India and there is no merit

consideration to quash the impugned tender notification which may impose heavy burden on the administration and may lead to increased and un-

budgeted expenditure to the Government besides making the Tsunami affected fishermen languish for yet another indefinite period to get their due

relief and the rehabilitation measures may be defeated in case if this Court is inclined to interfere with the impugned tender notification.

In fine, there being no merit, the Writ Petitions which deserve no consideration are dismissed. No costs. Consequently, connected Miscellaneous

Petitions are closed.

After the judgment was pronounced, the learned Counsel for the petitioners submitted that in view of the decision of this Court, the petitioners may

not be in a position to participate in the re-tender. In view of this submission, the petitioners are permitted to apply for re-tender and the

respondents are directed to issue tender schedules to the petitioners.