High CourtsSingle Bench(2019) 01 DEL CK 0243

Engineering Projects (India) Ltd vs Guru Gobind Singh Indraprastha University

Delhi High Court · Decided on 17 January 2019

HON’BLE JUDGES
Rajiv Shakdher, J
RESULT
Disposed Off
CASE NUMBER
Original Misc. Petition (MISC.)(COMM.) 24 Of 2019

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

10 paragraphs · 201 words

I.A. No.652/2019

1.

Allowed, subject to just exceptions.

O.M.P.(MISC.)(COMM.) 24/2019

2.

Issue notice.

3.

Ms. Sahani accepts notice on behalf of the respondent. Learned counsel for the respondent says that she does not wish to file a reply to the petition.

4.

The prayer made in this petition is for extension of time in respect of arbitration proceedings. The record shows that the Arbitrator was appointed by this Court vide order dated 30.5.2017 passed in Arb. P. No.317/2017. The record further shows that the arbitration proceedings commenced only on 4.5.2018.

5.

It appears that after arbitration proceedings commenced,with the consent of the parties, extension of time was granted by the learned Arbitrator by a further period of six months. Evidently, the extended period has also come to an end i.e. on 3.1.2019.

6.

I am informed by the counsel for the parties that the matter is at the stage of arguments.

7.

According to me, for the moment, extension by another six (6) months should suffice given the stage at which the proceedings are presently positioned. It is ordered accordingly. The period of six (6) months will commence from 3.1.2019.

8.

The captioned petition is disposed of in the aforementioned terms.