High CourtsSingle Bench(2015) 09 MAD CK 0216

Den Erfolg Switchgears (P) Ltd. vs Tamil Nadu Transmission Corporation Ltd. and Others

Madras High Court · Decided on 2 September 2015

HON’BLE JUDGES
M.M. Sundresh, J
RESULT
Allowed
CASE NUMBER
Writ Petition Nos. 27484, 27485 of 2015, M.P. Nos. 1 and 2 of 2015

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

14 paragraphs · 1,275 words

M.M. Sundresh, J—The petitioner is one of the tenderer in two projects. The particulars governing the two tenders, which are not in dispute, are as under:

There is no office at the given petitioner''s address, only a residence is available.

There is no office at the given petitioner''s address, only a residence is available.

2.

As per Rule 20 of the Tamil Nadu Transparency in Tenders Act 2000, 30 days time admittedly has been given governing both tenders. It is not in dispute that both the tenders are in excess of Rs. 2 Crores and thus, there is compliance of Rule 20.

3.

Now the grievance of the petitioner, as rejected by the respondents, is that though he has not participated in the pre-bid meeting governing both cases, by way of a clarification and amendment, a new clause has been introduced, by which along with single phase, for the first time, three phase was also included. In the other case, the KVA has been reduced from 500 to 400. Now, the specific case of the petitioner is that by the said introduction made for the first time on 24.08.2015, the petitioner is unable to comply with as it involves a new product, apart from variation of costs involved.

4.

Insofar as W.P. No. 27484 of 2015 is concerned, the dispute is with regard to the extension of time pursuant to the decision taken by the respondents from single phase to three phase. Insofar as W.P. No. 27485 of 2015 is concerned, the dispute is with regard to the extension of time pursuant to the decision taken by the respondents from 500 KVA to 400 KVA.

5.

The learned senior counsel for the petitioner in both cases submitted that Rule 20 read with Rule 17 has to be applied afresh for the said introduction of three phase, meaning thereby 30 days time from 24.08.2015 will have to be granted. It is the sum and substance of the submission made by the petitioner.

6.

The learned senior counsel for the petitioner submitted that the decision made by introducing 400 KVA would also have a bearing on the costs. He also submitted that apart from the costs, specification will also be different. Since the same is introduced afresh, the contentions raised in W.P. No. 27484 of 2015 would also apply to the case in W.P. No. 27485 of 2015.

7.

The learned Advocate General appearing on behalf of the respondents submitted that Rule 20 has been complied with and hence, no interference is required. Since the petitioner does not question the power of the respondents in invoking Rule 17, resultantly, it will amount to extension of time granted. As the time granted exceeds 30 days under Rule 20 and in view of the fact that the petitioner has not participated in the pre bid meeting, the clarification issued is binding on him, especially, when the other tenderers have not made out any grievance. In other words, the learned Advocate General submitted that the amendment made under Rule 17 would relate back to the date of notification and therefore, there is sufficient compliance. The request made by the petitioner, if granted, would amount to varying terms of the notification and this Court shall not exercise the power under Article 226 of the Constitution of India by extending the said time. It was further submitted that the petitioner cannot be aggrieved, since the amendment is not new, but in addition to the one that is existing (i.e.) single phase. Reliance has also been made on a judgment of the Hon''ble Supreme Court made in Sorath Builders Vs. Shreejikrupa Buildcon Limited and Another, (2009) 2 JT 673 : (2009) 4 SCALE 1 : (2009) 11 SCC 9 : (2009) 2 SCR 893 : (2009) 3 UJ 1426 .

8.

The facts narrated above are not in dispute. While it is true that the amendment does not modify or take away the original specification of single phase, it thus introduced a new specification viz., three phase. The mere fact that three phase has been introduced for the first time on 24.08.2015 would show that a tenderer can either opt for single phase or three phase or both, as the case may be. This Court is not willing to go into the said issue. Such an amendment will not take away the right of the petitioner either to choose single phase or three phase or both, as the case may be. Similar is the case qua 500 KVA or 400 KVA.

9.

Merely because the petitioner has not participated in the pre bid meeting, his right to opt anyone of the option cannot be taken away. The question for consideration is, whether the said clause having been introduced by way of clarification by exercising power under Rule 17 for the first time on 24.08.2015, the same would relate back to the date of notification or not.

10.

This Court is of the view that the clarification having been introduced by exercising power under Rule 17, it has to operate prospectively. The petitioner cannot be expected to be prepared and anticipate that such an amendment would relate back to the date of notification. The element of fairness required from an instrumentality of State also does not pave way for such an interpretation. Merely because an alternative option is available, it will not make a tenderer to step back. This Court cannot go into the advantage or disadvantage of single phase or three phase, 500 or 400 KVA, which fact is to be decided by the respondents. Similarly, it is for a tenderer to decide to offer any one of the two options available. When once a new specification is introduced, it has to be applied prospectively. The fact that the other tenderers have not come before this Court or made a request to the respondents seeking more time cannot be a ground to non suit the petitioner. Thus this Court is of the view that the petitioner is entitled for 30 days time to be reckoned at least from 24.08.2015 and 29.08.2015 respectively. Looking from a different angle, it can be said what the petitioner seeks is only a sufficient opportunity. 30 days time to be reckoned cannot be made from the point of view of the petitioner alone, but to be given on the interpretation of the rules based upon the decision taken by the respondents on the touch stone of Article 14, which takes in itself a sweep an element of fairness.

11.

The decision relied upon by the learned Advocate General in Sorath Builders Vs. Shreejikrupa Buildcon Limited and Another, (2009) 2 JT 673 : (2009) 4 SCALE 1 : (2009) 11 SCC 9 : (2009) 2 SCR 893 : (2009) 3 UJ 1426 does not have application to the case on hand. What the petitioner seeks is only an opportunity to participate. There is no contract involved between the parties. This Court is primarily concerned with the fair procedure that is to be adopted by the respondents. The facts involved in the said case are different. It was with respect to the contract entered between the parties. Thus, this Court is of the considered view that the decision has no application to the present case.

12.

Accordingly, the orders impugned are hereby set aside and consequently, the Writ Petitions are allowed with a direction to the respondents to extend the time limit so as to enable the petitioner to give his tenders with respect to the three phase for a period of 30 days to be reckoned from 24.08.2015 and 29.08.2015. No costs. Consequently, the connected miscellaneous petitions are close.