High CourtsDivision Bench(2009) 03 DEL CK 0290

Delhi Development Authority vs Tantia Construction Company

Delhi High Court · Decided on 23 March 2009

HON’BLE JUDGES
Vipin Sanghi, J · Mukul Mudgal, J
RESULT
Dismissed
CASE NUMBER
FAO (OS) 197 of 1999 and C.M. No. 2328 of 1999

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

17 paragraphs · 1,122 words

Mukul Mudgal, J.—This appeal challenges the order of the learned Single Judge dated 08.03.1999, by which order the objections to the award dated 09.08.1996 were dismissed and the award was made a Rule of the Court. The order dated 30.08.1999 passed in this appeal stipulated that the arguments shall be confined to Claim Nos. 2, 3(C) and 3(D) and the item of escalation on Claim Nos. 2, 3(C) and 3(D) under Claim No. 7. It appears that the mention of Claim No. 3(D) was a typographical error in the order dated 30.8.1999, as there is no claim 3(D) awarded by the learned Arbitrator. There was Claim No. 3(d) made for "Reinforcement for RCC Walls � Rs. 7,71,050/-", but this Claim was disallowed by the learned Arbitrator, and it has attained finality. All the aforesaid claims arose on a fundamental premise that the water level only upto a level of 210 mts stood accounted for under the contract and since the water level rose above 210 mts, the work executed by the contractor was entitled to be considered as work carried out in sub-soil for which payment should have been made as per Delhi Schedule of Rates (DSR), 1985. For this claim the respondent-claimant relied upon Clause 13 of the agreement. The learned Arbitrator has recorded as a finding of fact that the appellant had taken the level as per condition No. 27 (at page 89 of the agreement) and found the water level to be more than 210 mts which was also recorded. The details of claim Nos. 2, 3(c) and 7, in so far as they are relevant are as follows:

Claim No. 2 This claim was made for a sum of Rs. 22 lakhs by way of extra and substituted items. It was claimed that:

(i) Earth work in excavation

(ii) Laying of CC

(iii) Laying of RCC pipes

(iv) Laying of stone soiling etc.

were executed in or under water or liquid Claim No. 3(C) This claim was also made for carrying out the work of centering and shuttering for foundation footing and mass concrete in sub-soil water level condition for Rs. 11,000/- and for carrying out RCC work in a raft by Rs. 1,14,418.92.

Claim No. 7 was made towards escalation payable under Clause 10(cc) of the contract, inter alia, in relation to works carried out in sub-soil conditions.

2.

The appellant had sought to rely upon Clause 73 of the agreement and on that basis had argued that the contractor/respondent was not entitled to claim anything extra over and above the rates provided in the schedule of quantities for execution of the work in or under water on account of pumping and bailing out of water by any method of lowering of sub-soil water level during the execution of work.

3.

It is agreed between the parties that since Claim Nos. 3 & 7 are dependent upon the reasoning contained in Claim No. 2, the decision on the Claim No. 2 will govern the pleas in respect of Claim Nos. 3 & 7 as well.

4.

Having heard learned Counsel and given our due consideration, we are of the view that Clause 13 clearly shows that if the sub-soil water level rises upto 210 meters, no extra payment was to be made, but if it rose beyond 210 meters, then payments was to be made as per DSR 1985. Clause No. 13 reads as follows:

13.

As per the soil investigation, water table has been found at 209 mtr. as per the benchmark. No payment for working under the sub soil condition will be made if the water table rises to 210.0 mtr. during the execution of the work. If it rises above that level i.e. 210.00 mtr., payment for excavation etc. will be governed by the item of working under sub-soil as per DSR 1985.

5.

Clause 73 of the contract reads as follows:

73.

Nothing extra over and above the rates provided in the schedule of quantities for execution in/or under water shall be paid for pumping and bailing out water i/c by any method lowering of sub-soil water level during execution of work.

6.

In our view Clause 13 secifically deals with the situation where the water table rises above 210 mts during the execution of the work. In that situation the Contractor is entitled to payment for excavation etc for working under sub-soil conditions as per DSR 1985. Clause 73 only puts a limitation on extra charging for pumping and bailing out the water or lowering of water including by any method lowering of sub-soil water level during execution of work. This only means that if the water table is below 210 mts, the Contractor would not be entitled to claim anything extra over and above the rates provided for in the schedule of quantities for execution of the work, including for pumping and bailing out water by any method of lowering the sub-soil water level during the execution of the work. This Clause cannot be interpretated to mean that if the water level rises above 210 mts, the Contractor would not be entitled to claim payment for excavation etc at the rates applicable for carrying out sub-soil items of work as per DSR 1985. Both Clauses 13 and 73 have to be harmoniously construed and we see no contradiction in that. If the interpretation of the appellant were to be accepted, Clause 13 would be rendered nugatory, which could not have been the intention of the parties. In our view the arbitrator correctly considered the above provisions and as the appellant itself had found that the water level is more than 210 meters, awarded the amount to the respondent-claimant. The interpretation given by the learned Arbitrator to the agreement Clauses is reasonable and plausible. That is another reason not to interfere with the same.

7.

No doubt the learned Single Judge had not analyzed the above proposition but the conclusion of the learned Single Judge is correct and since we have ourselves analyzed the clauses, we find no merit in the challenge to the award of Claim No. 2. On the same basis claim No. 3(C) as awarded by the Arbitrator as also escalation on claim Nos. 2 and 3(c) awarded under Claim No. 7 cannot be faulted. Accordingly we dismiss the present appeal.

8.

The Registry is directed to release the amount deposited in this Court to the respondent along with interest accrued thereon by 08th May, 2009. In case the respondent is able to satisfy that the amount received by it does not satisfy the decretal amount, it is open to the respondent to recover the balance amount in execution after taking into account the amount withdrawn from this Court.