Tribunals and CommissionsSingle Bench(2022) 10 RERA CK 0647

Deepak Gupta vs M/s Purearth Infrastructure Limited

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 10 October 2022

HON’BLE JUDGES
Ajay Kumar Kuhar, Member
CASE NUMBER
Com/20/09/2022

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

11 paragraphs · 346 words
1.

Adv. Simran Soni appeared on behalf of the Complainant.

2.

Ld. Counsel for the Complainant has submitted that originally shop was booked by Mr. Deepak Gupta in the Central Square Project, Bara Hindu Rao. Later on he gifted the Shop to his son Sh. Karan Gupta, who is presently out of country. Sh. Karan Gupta has executed power of attorney in favour Sh. Deepak Gupta to file complaint.

3.

Ld. Counsel has placed on record the documents issued by the Respondents M/s Purearth Infrastructure Limited showing that pursuant to the request made by Sh. Deepak Gupta in favour of Sh. Karan Gupta they have made necessary changes in the record.

4.

Attorney can not file complaint in his name. Therefore complaint has to be in the name of Karan Gupta (through attorney Deepak Gupta). Let necessary correction be made by Complainant and amended Memo of Parties be filed within one week.

5.

Ld. Counsel has also clarified that originally the booking amount was Rs. 1,08,95,860/-but they have paid a sum of Rs. 1,15,03,990/- as the promoter had sought further deposits on account of car parking space.

6.

The Complainant is seeking refund of the paid amount for the reason that there is considerable delay in giving the possession, as the project was started in year 2006.

7.

The Ld. Counsel further submitted that apart from this the Respondents are insisting upon the Complainant to seek change of user from “flatted factory” to “commercial” which entail further expenses for Respondents. Further the Respondents are also charging common area maintenance charges despite non-delivery of possession.

8.

Issue notice to the Respondents to file reply by 25.11.2022 with copy served on the Complainant. Complainant may file rejoinder, if he wishes by 05.12.2022 with copy served on the Respondents.

9.

Complainant shall file complete legible set of documents within one week.

10.

Office is also directed to report whether the project Central Square Project, Bara Hindu Rao by M/s Purearth Infrastructure Limited is registered with this Authority or not.

11.

Matter be listed on 14.12.2022 (Wednesday) at 11:00 a.m.