High CourtsSingle Bench(2020) 09 DEL CK 0947

Dahej Standby Jetty Project Undertaking vs Petronet LNG Limited

Delhi High Court · Decided on 30 September 2020

HON’BLE JUDGES
C. Hari Shankar, J
RESULT
Disposed Of
CASE NUMBER
O.M.P.(MISC.)(COMM.) 194/2020 & I.A. 8016/2020, I.A. 8017/2020

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

8 paragraphs · 145 words

O.M.P.(MISC.)(COMM.) 194/2020

1.

This is a petition under Section 29(A)(4) and (6) of the Arbitration and Conciliation Act, 1996 seeking extension of the time available with the learned Arbitral Tribunal, presently seized of the disputes between the parties, to complete the proceedings and render award by a period of nine months commencing 4th September, 2020.

2.

Mr. Karun Mehta, learned counsel appearing for the respondent, has no objection.

3.

Accordingly, the prayer in the petition is allowed.

4.

The time available with the learned Arbitral Tribunal to complete the proceedings and render the award stands extended by a period of nine months commencing 4th September, 2020.

5.

The petition stands disposed of in the above terms.

I.A. 8016/2020 and I.A. 8017/2020 in O.M.P.(MISC.)(COMM.) 194/2020

1.

In view of the disposal of O.M.P.(MISC.)(COMM.) 194/2020, these applications do not survive for consideration and are disposed of accordingly.