High CourtsSingle Bench(2021) 07 KAR CK 0015

D Mahesh Kumar vs Managing Director Bangalore Metro Rail Corporation Ltd & Others

Karnataka High Court · Decided on 9 July 2021

HON’BLE JUDGES
Alok Aradhe, J
RESULT
Dismissed
CASE NUMBER
Review Petition No. 146 Of 2020 In Civil Miscellaneous Petition No. 226 Of 2017

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

12 paragraphs · 211 words

Alok Aradhe, J

1.

This review petition is filed seeking review of the order dated 02.04.2019 passed by this court in C.M.P No.126/2017, by which this court had

dismissed the petition under Section 11(6) of the Arbitration and Conciliation Act, 1996 inter alia on the ground that admittedly, the licence agreement

between the parties was not signed and was dismissed on the following grounds:

I have considered the submissions made by learned counsel for the parties. Admittedly, the licence agreement between the parties was not signed.

Therefore, the bid document did not form part of the licence agreement and in the absence of any licence agreement, there was no arbitration clause

between the parties. In the absence of arbitration clause between the parties, the petitioner could not seek appointment of an Arbitrator under Section

11(5) of the Arbitration and Conciliation Act, 1996. However, the petition is disposed of with liberty to the petitioner to take recourse to such remedy

as may be available to him under law.

2.

After hearing learned counsel for the parties, I find that the order dated 02.04.2019 passed in C.M.P No.126/2017 does not suffer from any error

apparent on the face of the record warranting interference of this court.

In the result, the petition is dismissed.