O R D E R
Per : Justice Rakesh Kumar Jain (oral)
This appeal is directed against the order dated 30.11.2021 passed by the ‘National Company Law Tribunal, New Delhi (hereinafter referred as to ‘the Adjudicating Authority) by which an application bearing Company Application No. IB – 913/ND/2019 filed by the Appellant for the resolution of an amount of Rs.2,56,19,630/-, has been dismissed.
Shorn of unnecessary details, the Adjudicating Authority has recorded its finding in Para 15 and 16 of the impugned order that the Appellant has already received the money of the work executed for the Respondent. In this regard, reference has been made vide letter dated 05.07.2014 which was written by the Appellant on its letter pad and even Annexure A4 shows the receipt of full and final payment with an endorsement that nothing is pending, duly signed by the Appellant. The Adjudicating Authority has also found that in the letter dated 20.10.2014, the Appellant has said as under:
“We would like to inform you that all work related to the above reference all work have been completed. We have received all dues against the work done. You are requested to allow us to take out our all tools & plants and issue instruction for issuance of non-returnable Gate Passes.”
The Adjudicating Authority has also recorded the finding in para 16, which read as follows:
“16.The respondent has also brought on record copy of letter dated 20.11.2014 which reads as under: - “Ref:- LOI dated 2.10., additional SOW dated 6.8.12 & dated 21.07.14 Sub : Removal of all tools & plants We would like to thank for co-operation and help and help for removing all material from site. We hereby confirm that our all material has been removed from the site and nothing is pending.” Copy of letter by applicant dated 14.06.2014 addressed to the Project Manager of respondent company which reads as under: -
“Ref. LOI dated 02.10.2010, additional SOW dated 6.8.2012 Sub : Security release We would like to confirm that all security amount Rs. 20,95,667.00 (Rupees twenty lac ninety-five thousand six hundred sixty-seven only) adjusted against our advance payment received of construction work Cloud project (1st RA Bill to 23 RA/final invoice) has been received. Nothing is pending.”
Faced with these observations, counsel for the Appellant has submitted that though a letter has been written by the Appellant but factually the money has not been paid. He has argued on the instruction received in court from one of the Director of the Appellant that letter has been written under duress because the Appellant was to remove the tools and plant from the premises of the Respondent.
On the other hand, counsel for the Respondent has submitted that the Appellant has not come to this court with clean hands because he did not disclose that he had earlier filed a civil suit before the Hon’ble Delhi which was dismissed for want of court fee. The order dated 26.03.2019 passed by the Hon’ble Delhi High Court is reproduced as under:
“Learned Counsel for the plaintiff states that he has not received any information from his client regarding the court fee.
The suit was filed in December 2017 without payment of court fees. The Court repeatedly adjourned the matter to enable the plaintiff to pay the necessary court fees. The same is not forthcoming.
The Suit is dismissed in default.
Pending applications, if any, also stand dismissed.”
It is further submitted by Respondent that the Appellant has tried to seek recovery of the amount through civil suit and then turned to the provisions of the Code for the purpose of Resolution of the same amount but the Appellant itself has already received the amount in question which is evident from Annexure A4.
We have heard counsel for the parties and after examining the record, are of the considered opinion that there is hardly any merit in the present appeal because there is an admission on the part of the Appellant in the form of letter dated 20.10.2014 that he had already completed the work in question and received the money. Rather through the Letter dated 20.10.2014, the Appellant had requested the Respondent to allow them to remove tools and plant from the premises which was ultimately allowed.
In such circumstances, it cannot be presumed that the Respondent has not made the payment to the Appellant otherwise, the Appellant being a company would not have written this kind of letter like the one dated 20.10.2014 to aver that they have received all the payments for the work done.
No other point has been raised.
In view of the aforesaid facts and circumstances, the appeal is found to be devoid of any merit and the same is hereby dismissed. No order as to costs.