AI Structured Summary
Not yet generated for this judgment
Judgment
The present petition has been filed under Sections 11(5) and 11(6) of Arbitration & Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) and seeks appointment of Sole Arbitrator to adjudicate the disputes between the parties arising out of work order No. BPTP/SF/PSS/37D/13/WO-49.
Earlier, on the basis of joint request, the parties were referred to mediation. The parties, however, could not reach any settlement as would be evident from report dated 22.09.2026, received from Delhi High Court Mediation and Conciliation Centre.
As per the aforesaid work order, the petitioner was awarded the work of construction of D.G. Room at the respondent‟s Group Housing Project, namely, Park Serene Spacio, Sector-37D, Basai, Gurugram (Haryana). The amount claimed is Rs.8,10,798/- (towards amount allegedly deducted on laying plain cement concrete [PPC]), Rs.5,00,000/- (towards amount illegally deducted on laying charges of quantity of RMC used) and Rs.1,69,261/-(towards retention money). The relevant clause dealing with Settlement and Disputes and Arbitration is „clause-R‟ which reads as under:-
“R. Settlement of disputes and arbitration:
That, all or any disputes, controversy, claim or differences of any kind whatsoever between the parties to this Contract relating to or arising out of or concerning or touching this Contract including their respective rights and obligations contained herein or the breach, termination, or relating to interpretation and validity of any provision herein, such differences, disputes shall be first settled amicably by mutual discussion and negotiations failing which the same shall be settled through Arbitration.
The Arbitration shall be governed by the Arbitration & Conciliation Act 1996 or any statutory amendments/modifications thereof for the time being in force. The Arbitration proceedings shall be held at New Delhi and shall be conducted by a Sole Arbitrator to be appointed by the Managing Director of M/s BPTP Limited on written request from either party or whose decision shall be final and binding upon the parties. The Contractor hereby confirms that he/it shall have no objection to the appointment of the Sole Arbitrator even if the person so appointed as a Sole Arbitrator is an employee or Advocate of the Owner or is otherwise connected to the Owner and the Contractor confirms that notwithstanding such a relationship/ connection, the Contractor shall have no doubts as to the independence or impartiality of the said Sole Arbitrator. The language to be used in the Arbitration proceeding shall be English and decision of the Sole Arbitrator including but not limited to award shall be final and binding on the parties. The Arbitrator shall decide his fees and the cost of the Arbitration proceedings shall be borne equally by both the parties.
That, the parties to this Contract also agree that in case, the Sole Arbitrator to whom the dispute is originally referred for adjudication is being transferred or vacates his office for any reason or is unable to act or continue as Arbitrator for any reason then in that eventuality, the Managing Director of BPTP Limited shall appoint any another person to act as Sole Arbitrator and such person shall be entitled to proceed with the Arbitration proceedings from the stage at which it was left by its predecessor.
That, the parties to this Contract also agree that no party shall be entitled to commence or maintain any suit or legal proceeding concerning a dispute arising from or in relation to this Contract in any Court of Law and seek any relief, (interim relief or otherwise) or injunction which will prevent the continuation of the Work in any manner under this Contract under any circumstances whatsoever. The Work shall continue if the Owner so desires through the Contractor or any other Contractor appointed by the Owner during arbitration proceedings, and no payment shall be withheld by the Owner on account of such proceedings except to the extent which may be in dispute.
This Contract will be governed in accordance with the laws of India. That, subject to arbitration provision herein, the Courts at New Delhi shall have exclusive jurisdiction with respect to all the matters arising out of this Contract.”
It needs to be highlighted that on one earlier occasion, the petitioner had filed a petition seeking same relief and this Court, while disposing of such petition [ARB.P. 33/2025], had appointed Arbitrator vide order dated 11.09.2025. During the pendency of the arbitration proceedings before the learned Sole Arbitrator, an application was filed from the side of respondent alleging that the various different disputes, emanating from different work orders had been clubbed together and the learned Sole Arbitrator, vide order dated 08.05.2026, held as under:-
“17.This Tribunal is of the considered opinion that having regards to the totality of the aforenoted facts and pleadings on record, the claims pertaining to the work orders other than Work Order no. BPTP/SSF/S37D/PSS/ 14/WO-88 dated 03 .03.2015 are beyond the scope of the present arbitral reference and adjudication of the disputes arising out of remaining work orders are not within the jurisdiction of this Tribunal.
18.In the result this Tribunal finds that the claim no. l & 8 which pertain to work order 88 dated 03.03.2015 only are covered within the scope of the present reference whereas the other claims pertaining to remaining five work orders are beyond the jurisdiction of this Tribunal.
19.In view of this Claimant is required to amend his Statement of Claim by confining his claims to the work order 88 dated 03.03.2015 only. As regards other claims arising out of the remaining work orders for which separate notice under Section 21 dated 01.04.2026 has been issued, the Claimant may take appropriate remedy, in accordance with law. Let the amended Statement of Claim be filed by the Claimant within four weeks with advance copy to the Respondent, who may file his Statement of Defence within the next four weeks with copies to the Claimant.”
It is in view of the abovesaid findings given by the learned Sole Arbitrator that the petitioner is now before this Court with request to appoint arbitrator in relation to work order No. BPTP/SF/PSS/37D/13/WO-49. The petitioner has invoked the arbitration afresh by giving notice dated 01.04.2026 under Section 21 of the Act.
During course of the arguments, learned counsel for respondent stated that they would have no objection to the appointment of Sole Arbitrator by this Court.
In view of the above and with the consent of the parties, the petition stands disposed of with the following directions:-
The disputes between parties concerning said work order are referred to arbitration.
ii) Ms. Manya Dudeja, Advocate [Mobile No. 9650656033] is appointed as Sole Arbitrator to adjudicate the same.
iii) The arbitration will held under the aegis of Delhi International Arbitration Centre, New Delhi (DIAC) and would be governed by the Rules of DIAC. The fee of the Arbitrator shall be fixed as per fee schedule under DIAC (Administrative Cost and Arbitrator’s fees) Rules 2018.
iv) The learned Arbitrator is requested to furnish a declaration in terms of Section 12 of the Act prior to entering into the reference.
All the rights and contentions of the parties are left open for adjudication by the learned Arbitrator.
vi) The parties shall approach DIAC within two weeks from today.
