Judgment
This Order disposes of the Application filed by Bimal Kumar & Ors. (hereinafter referred to as “Applicants”) on 20.10.2022 under Section 35 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as "RE(RD) Act, 2016") read with Rule 33(1) of the Delhi Real Estate (Regulation and Development) (General) Rules 2016 (hereinafter referred to as "Rules") seeking investigation into the affairs of the Respondent Company and La Tropicana Resident Welfare Association (hereinafter referred to as ‘LTRWA’ or ‘the Association’) alleging collusion and mismanagement of project funds.
The applicants are allottees of five different units in the project which was launched much prior to the year 2007 and promised to be completed in the year 2010. However, till date neither the project is complete nor the Respondents have refunded the money paid by the Applicants inspite of repeated requests.
The project was proposed to be developed on land admeasuring approximately 6.80 hectares allotted by Delhi Metro Rail Corporation Limited (DMRC) out of 37.30 hectares allotted to DMRC by Land & Development Office, Ministry of Urban Development (L&DO).
The Applicants, being family members, purchased five penthouses with the following details:
| Allottee Name | Tower & Unit | Area (Sq. Ft.) | Total Consideration Paid (Rs.) |
|---|---|---|---|
| Bimal Kumar | T17-702 PH | Approx. 9,550 | 6,04,28,743.90 |
| Rahul Gyanchandani | T20-702 PH | Approx. 9,550 | 6,03,01,508.22 |
| Rohit Gyanchandani | T17-701 PH | Approx. 9,550 | 6,04,28,743.90 |
| Manoj Kumar | T20-701 PH | Approx. 9,550 | 6,03,01,508.22 |
| Murlidhar Gyanchandani | T20-V2 | Approx. 9,615 | 5,74,59,850.73 |
Each Complainant paid Rs. 60,00,000/- at the time of booking and subsequently paid the entire sale consideration by 12.05.2012, with additional amounts paid in 2014 as demanded by the Respondents.
The Applicants have alleged collusion between the Respondents and the Residents Welfare Association i.e., LA Tropicana Residents Welfare Association (hereinafter referred as “LTRWA”). It has been alleged that the Association is taking decisions detrimental to the interests of allottees unilaterally without consulting them, and have entered into a Memorandum of Understanding (hereinafter referred to as “MoU”) with the Respondents. The Applicants have also alleged that the decisions taken by the LTRWA are adversely affecting bilateral agreements entered into between the Respondents and the allottees.
The Applicants submitted specific averments and alleged that in May 2015, representatives claiming to act on behalf of LTRWA approached them and collected Rs. 67,300 from each Complainant, representing that they were working to protect and advance the interests of the allottees.
The Applicants have alleged that after collecting these amounts, the representatives of LTRWA disappeared without taking any meaningful action to protect allottees' interests or provide any services for which the money was collected. The Applicants further contend that the Respondents entered into a MOU dated 30.04.2019 and a subsequent Addendum dated 27.10.2020 with LTRWA without obtaining knowledge, consent, or approval from the actual allottees of the project.
It has been alleged that these Agreements between the Respondents and LTRWA resulted in compromising the legitimate legal rights of the allottees and created arrangements that were detrimental to their interests.
The Applicants asserted that LTRWA has been functioning as a puppet organization of the Respondents, deliberately acting to defeat legitimate claims of allottees in exchange for apparent consideration of Rs. 45 crore and other undisclosed benefits.
The Applicants have sought investigation into the working of the LTRWA and signing of MoU between Respondents and LTRWA. Specifically, the Applicants have requested for the following reliefs under Section 35 of the RE(RD) Act, 2016:
a. Call for complete records of working of Respondent Company and LTRWA since 2015;
b. Conduct investigation into working of LTRWA and Respondent's management regarding execution of MOU dated 30.04.2019 and Addendum dated 27.10.2020;
c. Investigate circumstances of MOU execution and whether allottees' consents were obtained;
d. Call for books of accounts since 2007 and investigate utilization of funds received from allottees;
e. Investigate reasons for 15 years delay in project completion;
f. Determine if there are changes in building plans and whether allottees' consents were obtained for changing them; and:
g. Any other relief deemed fit by the Authority.
The main averments and submissions made on behalf of the respondents are as follows:
a. The LTRWA is not a party to the complaint, causing mis-joinder of parties as Complainants are a LTRWA member and reliefs concern LTRWA functioning.
b. Applicants failed to disclose that they filed a petition under sections 212, 213, 221 & 223 of the Companies Act, 2013 before NCLT seeking similar reliefs including company investigation and asset freezing. The petition remains pending.
c. This Authority lacks jurisdiction over LTRWA functioning matters. The National Consumer Disputes Redressal Commission (NCDRC) held vide order dated 16.12.2022 that LTRWA members cannot approach this Authority.
d. Delays in implementing the project resulted from inter-governmental disputes and regulatory issues. DMRC allotted the project land to Respondents in 2004 for Rs. 194 crore giving possession in 2005. The Master Plan changes in 2007 requiring EWS flats necessitated plan revisions.
e. A three-year ownership dispute arose when North Delhi Municipal Corporation (Nr.DMC) claimed land ownership versus L&DO and which got resolved only in 2019 after Hon’ble High Court of Delhi’s intervention. The building plans were finally approved thereafter.
f. The Respondents completed 12 of 21 towers with 213 allottees receiving No Objection Certificate and 104 families residing.
g. The Respondent Company’s accounts are publicly available on MCA website and allegations against officials lack supporting documents.
We have heard the arguments of the Ld. Counsels of both the parties and considered the provisions under the RE (RD), Act 2016.
ANALYSIS AND FINDINGS
The statement of objects and reasons of the Act points that the Act has been established for regulation and promotion of the real estate sector and to ensure sale of plot, apartment, building etc. in an efficient and transparent manner and to protect the interest of the consumers in the real estate sector. It is to ensure greater accountability towards the customers, consumers and to reduce frauds and delays, the Act has been promulgated. It seeks to establish symmetry of information between the promoter and purchaser, transparency of contractual conditions, set minimum standards of accountability, and a fast-track dispute resolution mechanism.
Before consideration of the issues, it is necessary to go through the relevant provisions in the Act and rules made there under which state the powers of the Authority.
Section 35 of the RE (RD), Act 2016 gives power to the Authority to call for information and conduct investigations. The text of this Section is reproduced below for ready reference:
“35.Powers of Authority to call for information, conduct investigations.—(1) Where the Authority considers it expedient to do so, on a complaint or suo motu, relating to this Act or the rules or regulations made thereunder, it may, by order in writing and recording reasons therefor call upon any promoter or allottee or real estate agent, as the case may be, at any time to furnish in writing such information or explanation relating to its affairs as the Authority may require and appoint one or more persons to make an inquiry in relation to the affairs of any promoter or allottee or the real estate agent, as the case may be.
(2)Notwithstanding anything contained in any other law for the time being in force, while exercising the powers under sub-section (1), the Authority shall have the same powers as are vested in a civil court under the Code of Civil Procedure, 1908 (5 of 1908) while trying a suit, in respect of the following matters, namely:— (i) the discovery and production of books of account and other documents, at such place and at such time as may be specified by the Authority; (ii) summoning and enforcing the attendance of persons and examining them on oath; (iii) issuing commissions for the examination of witnesses or documents; (iv) any other matter which may be prescribed.”
Rule 22 of the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016 specifies certain additional powers which have been conferred upon the Authority. This Rule reads as follows: -
"22.Additional powers of Authority. - (1) In addition to the powers specified in clause (iv) of sub-section (2) of section 35, the Authority shall exercise the following additional powers, -
(a)require the promoter, allottee or real estate agent to furnish in writing such information or explanation or produce such documents within such reasonable time, as it may deem necessary;
(b)requisitioning, subject to the provisions of sections 123 and 124 of the Indian Evidence Act, 1872 (1 of 1872), any public record or document or copy of such record or document from any office.
(2)The Authority may call upon such experts or consultants from the fields of economics, commerce, accountancy, real estate, competition, construction, architecture, law or engineering or from any other discipline as it deems necessary, to assist the Authority in the conduct of quality audit or of any inquiry or proceedings before it.
(3)The Authority may in the interest of the allottees, inquire into the payment of amounts imposed as penalty, interest or compensation, paid or payable by the promoter, in order to ensure that the promoter has not, -
(a)withdrawn the said amounts from the account maintained under sub- clause (D) of clause (1) of sub-section (2) of section 4; or
(b)used any amounts paid to such promoter by the allottees for that real estate project for which the penalty, interest or compensation is payable, or any other real estate project, or
(c)recovered the amounts paid as penalty, fine or compensation from the allottees of the relevant real estate project of any other real estate project."
Section 35 of the Act deals with the power of the Authority to call for information and conduct investigations into allegations against any promoter, allottee or agent.
At the outset, this Authority addresses the fundamental challenge raised by the Respondents regarding jurisdiction and maintainability of the present complaint. The Respondents have contended that this Authority lacks jurisdiction over matters concerning LTRWA functioning and that LTRWA members cannot approach this Authority based on the National Consumer Disputes Redressal Commission's order dated 16.12.2022.
However, this Authority notes that the issue of jurisdiction and maintainability has been elaborately handled and decided in affirmative by its order dated 13.03.2024. The said order has conclusively determined that this Authority possesses the requisite jurisdiction to entertain and adjudicate upon complaints of the nature filed herein. The jurisdictional challenge, having been previously decided, cannot be re-agitated in the present proceedings. Accordingly, this complaint is maintainable before this Authority.
The Applicants have prayed calling for complete records of working of both the Respondent Company and LTRWA since 2015. This Authority observes that while such relief appears to be within the scope of powers available under the Act, the exercise of such powers must be predicated upon substantial material and evidence that justifies such intervention.
Upon careful perusal of the complaint and supporting documents, this Authority finds that the Applicants have made allegations and assertions without concrete documentary evidence or material facts substantiating their claims of collusion or improper conduct. The power to call for records is an extraordinary remedy that should not be exercised merely on the basis of suspicion or unsubstantiated allegations and subjective opinion of the Complainant.
The Applicants have specifically sought investigation into the working of LTRWA officials and the Respondent Company’s management regarding the execution of the MoU dated 30.04.2019 and Addendum dated 27.10.2020, along with investigation into the circumstances of such execution and whether allottees' consents were obtained.
This Authority has carefully considered the reliefs sought by the Applicants in light of the materials placed on record. While the Applicants have made serious averments regarding alleged collusion and improper execution of agreements, they have not provided any credible evidence to substantiate these claims. The complaint primarily contains bald assertions and allegations without supporting documentation, witness statements, or other corroborative material that would justify invoking the investigative powers under Section 35 of the RE(RD) Act, 2016.
Section 35 of the Act confers wide discretionary powers upon this Authority to conduct investigations. However, such powers, being extraordinary in nature, must be exercised judiciously and only when there exists prima facie material warranting detailed investigation. Mere allegations or unsubstantiated averments cannot serve as the foundation for ordering comprehensive investigations that may have far reaching consequences for all concerned parties.
At this stage, investigation concerning the MoU, Addendum executed between Respondents and LTRWA is not expedient. We note that MOUs between Respondents and LTRWA have been considered and accepted by NCDRC and High Court as well.
The Applicants have sought calling of books of accounts since 2007 and investigation into utilization of funds received from allottees.
This Authority finds that the Applicants have not provided sufficient prima facie material that would justify directing production of detailed books of accounts spanning such an extensive period. The allegations regarding fund utilization remain unsubstantiated and appear to be based on conjecture rather than concrete evidence.
The Project having been duly registered on 16.03.2022 with an approved timeline for completion, any investigation into the reasons for delay or enquiry into the accounts of the promoter prior to such registration lacks justification. The Authority's investigative powers under Section 35 would more appropriately be confined to examining post-registration acts and conduct, thereby precluding retrospective scrutiny of pre-registration matters which fall outside the statutory ambit of regulatory oversight.
The fundamental principle governing quasi-judicial proceedings is that extraordinary powers must be exercised on the basis of credible material and not merely based on unsubstantiated allegations. The investigative powers under Section 35 of the RE(RD) Act, 2016, while broad, are discretionary and must be employed judiciously to maintain the balance between protecting allottees' interests and ensuring fair treatment to promoters.
In view of the above findings and reasoning, this Authority hereby declines the reliefs sought by the Applicants at this stage for the reasons elaborated above.
The application is disposed of accordingly.