High CourtsSingle Bench(2021) 06 DEL CK 0105

ATC Telecom Infrastructure Private Limited vs Orion Security Solutions Private Limited

Delhi High Court · Decided on 28 June 2021

HON’BLE JUDGES
C. Hari Shankar, J
RESULT
Disposed Of
CASE NUMBER
Original Miscellaneous Petition (I) (COMM.) No. 193, 194, 195 Of 2021, Miscellaneous Application No. 7585, 7586, 7594, 7595, 7598, 7599 Of 2021

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

57 paragraphs · 914 words

C. Hari Shankar, J

IA No. 7594/2021 in OMP (I) (COMM.) No. 194/2021 (for exemption)

IA No. 7598/2021 in OMP (I) (COMM.) No. 195/2021 (for exemption)

IA No. 7585/2021 in OMP (I) (COMM.) No. 193/2021 (for exemption)

1.

Exemptions are allowed, subject to all just exceptions.

2.

The applications stand disposed of accordingly.

IA No. 7595/2021 in OMP (I) (COMM.) No. 194/2021 (for exemption)

IA No. 7599/2021 in OMP (I) (COMM.) No. 195/2021 (for exemption)

IA No. 7586/2021 in OMP (I) (COMM.) No. 193/2021 (for exemption)

1.

Subject to the petitioners filing notarised affidavits, process fees and the requisite welfare stamps, within a period of one week from today,

exemptions are granted for the present.

2.

The applications stand disposed of accordingly.

OMP (I) (COMM.) No. 194/2021

OMP (I) (COMM.) No. 195/2021

OMP (I) (COMM.) No. 193/2021

1.

These three petitions raise interconnected issues.

2.

Vide agreements dated 12th February, 2019 and 23rd June, 2020, M/s Orion Security Solutions Private Limited (“Orionâ€, in short) agreed to

provide operation and maintenance services and surveillance services in respect of the tower sites of M/s ATC Telecom Infrastructure Private

Limited (“ATCâ€​ in short) in the state of Maharashtra.

3.

Disputes have arisen between the parties in respect of these agreements.

4.

The operation and maintenance services agreement dated 23rd June, 2020 admittedly expired by efflux of time on 30th June, 2021. The surveillance

agreement dated 12th February, 2019 has been terminated by the respondent vide termination notice dated 25th May, 2021 w.e.f. 30th June, 2021. As

such, both the agreements would come to an end on 30th June, 2021.

5.

OMP (I) (COMM.) 194/2021 and 195/2021 have been filed by ATC against Orion under Section 9 of the Arbitration and Conciliation Act, 1996

(“the 1996 Act†in short) for a direction to the respondent to hand over, to the petitioner, all the sites and operational assets of the petitioner and

not to disrupt the operation of the sites/E-Communication Towers in any manner whatsoever.

6.

OMP (I) (COMM.) No. 193/2021, on the other hand, has been filed by Orion against ATC, for restraining the ATC from encashing Bank

Guarantees No. 003GT01192210001 for ₹ 25,00,891 and Bank Guarantee No. 003GT02192460003 for₹ 35,05,900 /-, both issued by HDFC Bank Ltd.

Greater Kailash-I and Bank Guarantee No. 316020706647-SP for ₹ 25,00,000/-issued by Standard Chartered Bank, New Delhi, furnished by Orion to

ATC.

7.

Of these three Bank Guarantees, Mr. Sharma, learned counsel for the petitioners, submits that Bank Guarantee No.003GT01192210001 for₹

25,00,891 and Bank Guarantee No. 003GT02192460003 for ₹ 35,05,900 /- have already been encashed and that Bank Guarantee No. 316020706647-

SP, issued by the Standard Chartered Bank is not traceable. Even if it is traced, he makes a submission on behalf of his client that, subject to Orion

handing over vacant and peaceful possession of the tower sites to ATC on or before 30th June, 2021 and ensuring that their personnel do not disrupt

the petitioner from operating the said tower sites, his client would not invoke the third Bank Guarantee issued by Standard Chartered Bank.

8.

Mr. Joby Verghese, learned Counsel for Orion is agreeable to this suggestion.

9.

Learned Counsel for the parties also submit, ad idem, that an Arbitrator may be appointed by this Court to arbitrate all the disputes between the

parties, so that a speedy resolution thereof is attained.

10.

In view of these submissions, these petitions stand disposed of in the following terms and with the following directions:

(i) Orion shall hand over, to ATC, peaceful and vacant possession of the towers at the 425 sites forming subject matter of OMP (I) (Comm) 194/2021

and 26 sites forming subject matter of OMP (I) (Comm) 195/2021 on or before 30th June, 2021.

(ii) Orion shall ensure that they and their personnel do not interfere with the operation of the aforesaid telecom sites by ATC.

(iii) ATC shall stand injuncted from invoking Bank Guarantee No. 316020706647 issued by the Standard Chartered Bank, New Delhi. This shall,

however, remain subject to the outcome of the orders/award to be passed by the learned Arbitrator in the arbitral proceedings.

(iv) No orders are being passed in respect of Bank Guarantee No.003GT01192210001 for ₹ 25,00,891/- and Bank Guarantee No. 003GT02192460003

for ₹ 35,05,900/- as these Bank Guarantees are stated to already have been encashed by ATC and the prayer in that regard in OMP (I) (Comm)

193/2021 has been rendered infructuous. However, the rights of Orion, in respect of the said Bank Guarantees shall remain alive for being urged in the

arbitral proceedings.

(v) The disputed amount involved in these proceedings is stated to be in excess of ₹ 17,00,00,000/-. Accordingly, this Court requests Hon’ble Ms

Justice G. Rohini, former Chief Justice of this Court, to arbitrate on the disputes. The contact details of the learned Arbitrator are as under:

Mobile Nos.8527027027 & 8826000333 Email ID: justicegrohini@gmail.com

(vi) The Arbitrator shall file the requisite declaration under Section 12 of the Arbitration and Conciliation Act, 1996 within a week of entering on

reference;

(vii) The learned Arbitrator shall be entitled to charge fees in accordance with the Fourth Schedule to the 1996 Act.

11.

This Court makes it clear that it has not expressed any opinion one way or the other on the disputes between the parties. All rights and contentions

shall remain open to be urged in the arbitral proceedings and the parties shall abide by the outcome thereof.

12.

With these directions all the three petitions stand disposed of.