Judgment
The petitioner-Asset Reconstruction Company India Ltd., has approached this Court with the following relief:-
''''Civil Writ Petition under Articles 226/227 of the Constitution of India praying for issuance of a writ in the nature of Certiorari for quashing the
Impugned Final Notice/Order dated 26.12.2017 (Annexure P-1) issued/passed by Respondent No.2-The Project Director, National Highway
Authority of India, thereby directing the respondent No.3-M/s Kiran Overseas Exports Limited to remove its movable/immovable properties from
the alleged encroachment on National Highway No.1 (Now National Highway No.44) before 5.1.2018, without adjudicating the legal rights of the
Petitioner-Financial Institution that physical possession of the secured assets/properties of M/s Kiran Overseas Exports Limited is with the
Petitioner-Financial Institution under the provisions of SARFAESI Act, 2002 vide possession notice dated 19.9.2017 pursuant to order dated
18.8.2017 passed by this Hon''ble High Court in CWP No.16366 of 2016 thereby directing the District Magistrate, Sonepat, Haryana, to take
physical possession of the mortgage properties by giving effect to the order dated 08.02.2016 passed by District Magistrate Sonepat under
Section 14 of the SARFAESI Act, 2002.
AND
For issuance of a writ in the nature of mandamus for issuance of appropriate directions to Respondent No.2 to keep in abeyance the
implementation of the Impugned Order/Notice dated 26.12.2017 (Annexure P-1) till the final adjudication of the legal rights of the petitioner
Company and till the final adjudication of the present writ petition in the interest of justice.
AND
For issuance of any other appropriate writ, order or direction, which this Hon''ble Court may deem fit and property in the facts and circumstances
of the case in the interest of justice.''''
Mr. V.K. Sachdeva, learned counsel appearing on behalf of the petitioner-Company submits that the petitioner-Company is the assignee of
Industrial Development Bank of India Ltd. (IDBI), Punjab National Bank and Union Bank. The Assigner-Banks vide their respective Sale Deeds
of Assignment dated 30.06.2008, 15.09.2008 and 22.12.2008 assigned all the rights, title and interest over the dues recoverable from respondent
No.3- Kiran Overseas Exports Ltd., with underlying securities. Thereafter, the petitioner had invoked the provisions of SARFASESI Act, 2002
for taking over the possession and the matter reached upto the office of District Magistrate in a proceedings initiated under Section 14 of the
SARFAESI Act. The order of possession was recalled by the District Magistrate, Sonepat constraining the petitioner to approach this Court vide
CWP No.16366 of 2016 and this Court vide its comprehensive order dated 18.08.2017, quashed the impugned order therein and allowed the
writ petition with a direction to the District Magistrate, Sonepat to give effect to the order dated 08.02.2016 i.e. first order passed by the District
Magistrate, Sonepat, for taking over the possession, and also to submit a compliance report to the Registrar Judicial of this Court. As per report of
Naib Tehsildar dated 19.09.2017 (Annexure P-4), the possession had been taken on 19.09.2017. Thereafter, a public notice dated 23.09.2017
(Annexure P- 5) with regard to taking over the possession was published in the newspaper. The bids were also invited in pursuance to the E-
Auction Notice dated 24.11.2017 (Annexure P-6). The auction slated for particular date could not be materialized and therefore, vide
corrigendum notice dated 15.12.2017 (Annexure P-8), the auction date was extended to 04.01.2018 i.e. today. The petitioner-Company
received the notice dated 26.12.2017 (Annexure P-1) on 27.12.2017, indicating that the borrower of erstwhile banks had encroached the land
belonging to the National Highway. All efforts were made to ascertain the actual and alleged encroachment by the borrower viz-a-viz the
notification purportedly issued under Section 3 and 3(G) of the National Highways Act, but did not yeild any result. Even a representation dated
29.12.2017 (Annexure P-9) to the E-auction notice dated 26.12.2017 (Annexure P-1) had been submitted to the National Highway Authority,
but of no avail and there is likelihood that the petitioner-company shall be dispossessed without affording any opportunity of hearing, much less,
ascertainment of alleged encroachment which according to the petitioner is none.
After hearing learned counsel for the petitioner and perusing the averments made in the petition and without expressing any opinion on the merits
of the controversy, we dispose of the writ petition by directing respondent No.2/Project Director, National Highway Authority of India, A- 3,
UGF, Pushpanjali Enclave, Pitampura, New Delhi, to take a decision on representation dated 29.12.2017 (Annexure P-9) or any other relevant
documents, which petitioner may produce, after affording an opportunity of hearing, to belie allegations in the impugned notice dated 26.12.2017
(Annexure P-1) by passing a speaking order in accordance with law.
Let this exercise be undertaken within a period of one month from the date of the receipt of the certified copy of this order. It is expected that
respondent No.2 shall not take the action as contemplated in notice dated 26.12.2017 (Annexure P-1).