AI Structured Summary
Not yet generated for this judgment
Judgment
(Per : Rajnish R. Vyas)
Heard learned counsels for the respective parties.
Innocuous prayer is made in this petition for direction to the Debt Recovery Tribunal to decide the Interim Application and Securitization Application filed by the petitioner within a time bound period.
The parties are ad idem that due to non-availability of Presiding Officer at Debt Recovery Tribunal, Nagpur, the matter is now being taken up by Debt Recovery Tribunal, At Aurangabad.
Considering the difficulty likely to be faced by the litigants, we pass following order:
O R D E R
The Interim Application No. 829/2025(Annexure -C) be decided within 15 days from placing of the matter before the Debt Recovery Tribunal At Aurangabad.
ii) The Securitization Appeal No. 407/2022 (Annexure – B) be decided within six weeks from placing of the matter before the Debt Recovery Tribunal At Aurangabad.
iii) Status-quo as regard auction or possession of the properties granted shall continue till decision of Interim Application.
The petition is disposed of in the aforestated terms.