High CourtsSingle Bench(2026) 10 BOM CK 6427

Aram Nagar Meena Redevelopment Private Limited vs Aram Nagar Meena Co-op. Housing Society Limited & Ors.

Bombay High Court · Decided on 15 October 2026

HON’BLE JUDGES
Gauri Godse, J
RESULT
Disposed Of
CASE NUMBER
Interim Application No. 3414 of 2026 in Commercial Suit No. 22 of 2026 WITH Interim Application (L) No. 20706 of 2026 in Commercial Suit No. 22 of 2026 WITH Interim Application No. 5 of 2026 in Commercial Suit No. 1 of 2026
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

55 paragraphs · 5,941 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

BASIC FACTS:

1.

The dispute in both suits concerns the development agreement dated 10th December 2021, executed by Aram Nagar Meena Co-operative Housing Society Limited (‘Society’) in favour of Aram Nagar Meena Redevelopment Private Limited (‘Developers’). The society filed Commercial Suit No. 1 of 2026 for a declaration that the development agreement and the power of attorney were validly terminated and prayed for a decree cancelling the development agreement and power of attorney. The society also prayed for an injunction restraining the developer from claiming any right as a developer in respect of the society’s property and from carrying out any redevelopment pursuant to the terminated agreement.

2.

The developer filed Commercial Suit No. 22 of 2026 to challenge the termination notice and prayed for a declaration that the development agreement and the power of attorney are valid, subsisting and binding upon the parties. The developer further prayed for specific performance of the development agreement. In the alternative, the developer prayed for Rs. 350,00,00,000/- (Rupees Three Hundred and Fifty Lakhs only) towards compensation and damages. After the society executed a fresh development agreement, the developer amended the suit to challenge the subsequent development agreement in favour of the third-party developer (“new developer”) and also made the new developer a party defendant in the developer’s suit.

3.

The developer filed Interim Application No. 3414 of 2026 seeking a stay on the implementation of the society's termination notice and an injunction restraining the society from engaging any other developer or contractor.

4.

The new developer filed Interim Application(L) No. 20706 of 2026 seeking modification of the interim relief granted in the developer’s suit on 9th March 2026; the new developer also prayed for permission to execute further documents necessary for redevelopment of the society under the development agreement dated 9th January 2026. The society filed Interim Application No. 5 of 2026 in its suit seeking an injunction restraining the developer from interfering with the redevelopment process and from claiming to be the developer of the society’s property. The society also prayed for permission to appoint a new developer or a contractor to carry out development of the suit property. The society also prayed for an injunction restraining the developer from interfering with the society’s possession over the suit property.

5.

In view of the administrative order, both the suits were listed before this court, and all three applications were heard together. The subject matter of both suits is the redevelopment agreement for the land along with Building No. 3, standing thereon, comprising a stilt plus 7 floors with 28 flats. On 13th August 2018, MHADA had issued a notice to the society as the building was in a dilapidated condition. The society therefore initiated the redevelopment process and obtained an NOC on 11th October 2018 for height clearance from the Airport Authority of India. Accordingly, the society submitted a proposal to MHADA on 29th May 2019. MHADA executed a registered lease deed dated 1st August 2019 in respect of the society’s land for a term of 90 years, commencing from 1st March 1994. MHADA also executed a registered sale deed dated 1st August 2019 in favour of the society in respect of the said building. The society was called upon to pay the premium in four instalments under the redevelopment permission under Regulation 33(5) of the Development Control and Promotion Regulation, 2034 (‘DCPR 2034’).

6.

MHADA issued a notice to vacate to the society on 18th November 2020 and also directed disconnection of the Mahanagar Gas connection. Pursuant to the redevelopment proposal submitted by the society, the Executive Engineer of MHADA issued a consent letter dated 5th February 2021. Thereafter, the society issued a public advertisement dated 6th March 2021, inviting offers from developers to carry out the redevelopment process. Accordingly, the society accepted the developer’s proposal, and the parties executed the development agreement on 10th December 2021. On the same day, the society also executed a power of attorney in favour of the developer. The developer and the society exchanged various e-mails and correspondence regarding the redevelopment process and permissions.

7.

The society issued a termination letter dated 23rd November 2024, to which the developer responded and contended that the developer had not defaulted and that the pro-rata FSI was not yet approved for utilisation in the layout, which was an impediment. The developer contended that the society had instructed it not to proceed until the pro-rata FSI approval was granted, so it could obtain an increased area. Hence, the developer challenged the termination notice. On 31st March 2025, the society filed the suit seeking declaration that the development agreement and Power of Attorney are validly cancelled. In view of the society's termination notice, the developer filed the suit for declaration and specific performance. The facts and controversy in both suits are similar; hence, this judgment decides all three applications.

SUBMISSIONS ON BEHALF OF THE DEVELOPER:

8.

Learned counsel for the developer submitted that after the society issued an advertisement inviting offers from developers, the society requested MHADA to reduce the premium as per the Government Resolution dated 14th January 2021 and prayed for four instalments to pay the premium. MHADA issued the demand letter dated 20th July 2021, informing the amount calculated up to 31st December 2021 along with interest/penalty as per the circular dated 15th July 2020. The developer thereafter issued a revised offer letter dated 30th August 2021. However, although the society accepted the revised offer by its resolution dated 9th September 2021, it subsequently terminated the agreement.

9.

By letter dated 1st December 2021, the society informed MHADA that it was unable to pay the premium as per the offer letter and requested utilisation of the pro-rata FSI and VP quota to the tune of 2119.60 square meters and 5283.07 square meters, respectively. The society again requested utilisation of pro- rata FSI and VP quota by letter dated 8th December 2021. On 10th December 2021, the society executed the development agreement and a power of attorney in favour of the developer. As requested by the society, MHADA had permitted consumption of additional built-up area towards pro-rata FSI.

10.

Thereafter, the society issued a letter dated 18th August 2023, stating that the society’s property falls within the layout with substantial pro-rata built-up area and is also surrounded by slums. Accordingly, the society requested an additional built-up area of 4650 square meters to make the proposal financially feasible. On 1st February 2024, the society issued a letter to the developer requesting that the redevelopment process be expedited. The society informed the developer that the 25% premium must be paid by 31st October 2024 and the demolition work must be completed by 31st December 2024. Accordingly, the society informed the developer that the Bhumi Poojan must take place on 14th January 2025. On 21st September 2024, the developer informed the society that the MHADA offer letter was valid till 30th December 2024 and that the developer would pay the first instalment of premium on or before that date. The developer also informed the society that once the premium is paid and the plans are approved, the individual PAAA agreement would be executed, and thereafter, the entire demolition would be undertaken.

11.

On 1st October 2024, the society informed the developer that the final action date, as per MHADA’s offer letter, was 30th December 2024. The society also stated that, for almost three years after payment of the initial premium amount, no progress was made, and that the developer must pay the premium by 31st October 2024 and not 30th December 2024. The society, vide e-mail dated 24th October 2024, intimated the developer that in the meeting held on 19th October 2024, the developer left the meeting, leaving the members confused, and the meeting was not concluded. Another email dated 24th October 2024 was addressed on behalf of the society, tendering an apology for the incident on 19th October 2024. However, the society thereafter issued a termination letter.

12.

Learned counsel for the developer submitted that the developer’s offer letter dated 15th March 2021 clearly indicated that the area of the flats to be handed over without pro-rata FSI was 750 square feet, and with pro-rata FSI, it was 950 square feet. Learned counsel for the developer relied on the society’s general body resolution dated 9th September 2021 and submitted that, at the time of execution of the development agreement, the developer changed its name from Parinee Reality Pvt. Ltd to Aram Nagar Meena Redevelopment Pvt. Ltd.

13.

Learned counsel for the developer submitted that the society had undertaken to self-redevelop the building; however, it abandoned its plan as it was unable to pay the premium and had requested a reduction in premium. After the society accepted the developer's offer on 4th April 2021, MHADA issued a demand letter dated 20th July 2021 to the society. The said demand letter was in response to the society’s request letter dated 23rd March 2021 asking for instalments in payment of premium. The built-up area utilisation set out in the said demand letter is the same as offered in MHADA’s original offer letter dated 4th November 2019, and the said letter only reduced the premium amount by 50%. However, the society was not satisfied with the quantum of FSI permitted under MHADA’s offer and had requested for additional FSI. The society thereafter accepted the developer’s revised offer and the completion of the project in 30 months from the date of handing over of the building to the developer.

14.

The society again sent letters dated 1st December 2021 and 8th December 2021 to MHADA and requested utilisation of pro-rata FSI and VP quota. This letter clearly indicates that the society wanted a total built-up area of 7402.67 square meters; however, MHADA did not approve it. MHADA issued an offer letter dated 30th December 2021 in response to the society’s request and permitted consumption of additional built-up area of 2826.04 square meters towards pro-rata FSI; however, it was still not sufficient as requested by the society. The society again requested MHADA by letter dated 18th August 2023 for additional built-up area of 4650 square meters. The society made the request on the ground that its property falls in a layout which has substantial pro-rata built-up area and the property was surrounded by slums.

15.

Learned counsel for the developer therefore submitted that the society's conduct clearly indicates that, even after twenty months of execution of the development agreement, the society was desirous of more area to be consumed in the redevelopment process. The society wanted more FSI because the members would get a flat of 950 square feet instead of 750 square feet. As per the development agreement, the members would get a larger area of up to 1250 square feet if MHADA approves fungible FSI, pro-rata FSI, and full FSI out of the VP quota. Hence, the society repeatedly requested extra FSI from MHADA, and it was difficult for the developer to get the plans approved as there was no clarity whether the society was satisfied with the available FSI. However, despite making repeated requests to MHADA for additional FSI, the society called upon the developer to start the work by imposing deadlines.

16.

As per clause 10.5 of the development agreement, the project was to be completed in 39 months plus a grace period of 6 months, that is, a total of 45 months from the vacation date. As per clause 7.1 of the development agreement, 45 months must be calculated as per clause 7.2 which defines the ‘vacation date’, that is, the date when the society grants license to the developer to enter the vacated building for the redevelopment process. Hence, clause 10.5, which fixes the timelines, must be read with clauses 7.1 and 7.2. Learned counsel for the developer submits that the vacation date as agreed in the development agreement has not yet taken place; hence, the completion period has yet to begin. The developer has always shown willingness to pay the premium before 30th December 2024, as per MHADA’s letter, and to perform the Bhumi Pujan as requested by the society and execute PAAA agreements after demolition. The society’s insistence on paying the first instalment of the premium before 31st October 2024 was unreasonable. Hence, no default can be attributed to the developer.

17.

The email dated 24th October 2024, sent on behalf of the society, clearly records an apology to the developer for the incident in the general body meeting held on 19th October 2024. The members of the society were disrespectful towards the director of the developer; hence, he had left the meeting. The said email sent on behalf of the society also expressed confidence that the matter would be resolved and requested a meeting with the developer. However, within 4 days of sending the said email, the society resolved to terminate the development agreement. The reasons for termination are unfounded and baseless. The society approved the developer’s revised offer of 750 square feet without pro-rata FSI and 950 square feet with pro-rata FSI on 8th September 2021, as provided in the development agreement. The society made a baseless allegation that the developer wanted to transfer the rights to a third party. The developer regularly paid the rent; however, the society’s secretary refused to accept it after July 2024. The developer was also ready to furnish a bank guarantee; however, it was mutually agreed that the said amount must be used to pay the premium. Accordingly, the developer issued a detailed explanation and informed that the society had instructed them not to proceed until the pro-rata FSI was approved.

18.

Even the recent letter dated 17th December 2025 issued by MHADA offers only 5427.54 square meters, which does not meet the society’s requirement of 7402.67 square meters. The developer has spent Rs. 3,38,81,888/- on the redevelopment process. The development agreement provides a qualified termination under clause 21. The society never issued the cure notice as per clauses 21.1 to 21.3. The developer has committed no contractual breach. The real reason for termination is the incident of 19th December 2024, which cannot be a valid ground to terminate the agreement. As per clause 4(a) of the development agreement, the society was under an obligation to first grant the license to enter the property, which never took place. Hence, under Sections 51 and 52 of the Indian Contract Act, without complying with the reciprocal conditions under the development agreement, the society cannot terminate the contract by alleging breach by the developer. The developer is therefore entitled to protect its rights under the development agreement as prayed in the interim application.

19.

According to the learned counsel for the developer, the developer always showed readiness and willingness to complete the project, and, cooperated fully for the purpose of layout utilization as desired by the society. Learned counsel for the developer relied upon the terms and conditions of the agreement and the pleadings in the plaint to support his submissions that the termination was premature and invalid. Although the society never granted the license to enter the property, the developer has performed his part of the contract and paid substantial amounts towards reimbursement of expenses, hardship compensation, rent, shifting charges, brokerage charges, and legal fees. Given the confusion regarding approval of the pro-rata FSI and the VP quota FSI, the developer could not take further steps. Since the society repeatedly requested MHADA to approve the additional FSI, it also extended the time for completion of the project, as evidenced by the various letters issued by the society to the developer, including the letter dated 10th September 2024. Accordingly, under Section 63 of the Indian Contract Act, the time for performance of the developer’s obligation stood extended.

20.

Meanwhile, the society initiated proceedings to appoint a new developer. Accordingly, the society filed a suit seeking a declaration that the termination of the development agreement and the power of attorney was valid. Learned counsel for the developer therefore submits that the termination was without any valid reason and therefore the developer is entitled to an injunction to protect the rights created in its favour by the society under the development agreement.

SUBMISSIONS ON BEHALF OF THE SOCIETY:

21.

Learned counsel for the society submitted that the option to make payment towards the premium was subject to the terms and conditions of the contract; however, the developer made no payments, and the non-payment of instalments showed the developer's unwillingness and incapacity. The developer failed to keep the commitments; hence, the members lost confidence in the developer. As clause 10.2 of the development agreement 10 months time was provided for obtaining IOD. Clause 7.1 and 7.2 provided for the necessary compliances and timelines. However, the developer failed to comply with the commitments.

22.

Despite multiple letters, the developer failed to pay 25% of the total premium. In view of the incident that occurred in the meeting held on 19th October 2024, the members lost all confidence in the developer. Hence, the general body of the society resolved to terminate the agreement. Although the society did not issue a cure notice, the earlier letters to the developer requiring compliance with the contract terms and conditions were sufficient notice to enable the developer to cure the defaults. Hence, the fact that no cure notice was issued cannot be a ground to declare the termination invalid. In the suit filed by the society, this Court observed that there is no restriction on executing a fresh development agreement. The developer had not taken any steps to challenge the termination notice. Hence, the fresh development agreement in favour of the new developer was validly executed, and the developer has no right to challenge it. Hence, the developer is not entitled to any interim relief as prayed. In view of the valid termination of the development agreement and the power of attorney, no right, title, or interest in favour of the developer subsists. The members are suffering hardship due to the delay in completing the redevelopment process. Hence, the society is entitled to the interim relief as prayed in the society’s suit.

23.

Learned counsel for the society submitted that the loss of trust and faith in the developer is based on the developer's default. In view of the breach committed by the developer and with no hope of completion of the project, the developer is not entitled to prevent the society from self-redevelopment or completing the redevelopment project through another developer. The members of the society are out of possession, and thus they cannot be left at the mercy of the developer. He therefore submits that the developer's repeated defaults, and the society's lack of trust and confidence in the developer, are valid grounds to terminate the development agreement and complete the redevelopment project through other means. To support his submissions, learned counsel for the society relied on this Court's decision in Swashray Co-op Housing Society Vs Shanti Enterprises1.

SUBMISSIONS ON BEHALF OF THE NEW DEVELOPER:

24.

Learned counsel for the third-party developer relied upon the order dated 24th April 2025 passed by this court in the society’s suit. He submitted that the developer challenged the termination notice only in August 2025. Pursuant to the development agreement executed in favour of the new developer, he has already paid Rs. 16,00,00,000/- to the society. The developer can always be compensated in terms of money; hence, the developer is not entitled to any interim relief in the suit to challenge the validly terminated development agreement.

ANALYSIS AND CONCLUSIONS:

25.

The dates and events before and after the execution of the development agreement referred to in the above paragraphs are not disputed. It is also undisputed that the society requested MHADA to approve pro-rata FSI and VP quota and sought to avail the benefit of additional FSI. Before inviting proposals from prospective developers, the society had already started the redevelopment process by obtaining NOC from the Airport Authority of India and submitting a proposal to MHADA. MHADA issued a notice to vacate, and most of the members had already vacated before execution of the development agreement. The society published the advertisement calling for proposals at the stage of premium payment, as per the offer letter issued by MHADA. After accepting the developer’s proposal, the society had requested MHADA to approve pro-rata FSI and VP quota.

26.

The record shows that even after execution of the development agreement, the society had reiterated its request for pro-rata FSI and VP quota. In response to the society’s request, MHADA had issued an offer letter for additional built-up area. However, the society was not satisfied and again addressed a letter to MHADA for additional built-up area. There was various correspondence between the society’s office bearers and the developer regarding the redevelopment process. According to the developer, the further process of approval of the plan and securing an IOD could not take place as the society was making attempts for additional FSI and there was no clarity about utilisation of the FSI for finalising the plans for approval and obtaining IOD. It is undisputed that, even after accepting the developer’s proposal and executing the development agreement, the society reiterated its request to MHADA for additional FSI.

27.

It is necessary to refer to the relevant terms and conditions of the contract. Clause 7.1 of the development agreement provides that the developer may be granted a license to enter the suit property within 30 days of the developer's notice to vacate, subject to securing IOD and duly approved plans. Prima facie, it appears that because the society requested additional FSI, the plans were not finalised; hence, IOD was not obtained. Since IOD and approval of plans remained pending, notice to vacate could not have been issued. It thus appears that the remaining process also remained pending. Clause 7.1 records that members had already vacated the flats. Under clause 7.2, the developer was to make payments after the notice to vacate. There appears to be no dispute that the developer made the reimbursement under clause 3.4. Although the occasion to issue notice to vacate did not arise, the developer made payments towards hardship compensation, shifting charges and brokerage as pleaded in paragraph 25 of the plaint.

28.

As per MHADA’s offer letter dated 30th December 2021, MHADA offered two options for payment of the premium. Option (i) allowed instalments, with the last instalment due within three years, which expired on 30th December 2024. Option (ii) provided a 50% reduction, subject to furnishing an undertaking, and the validity of option (ii) was up to 31st December 2021. Option (i) also provided for applying interest for delayed payment. Accordingly, by letter dated 21st September 2024, the developer submitted all explanations and showed willingness to comply with the terms and conditions. However, despite issuing letter dated 10th September 2024, calling upon the developer to make payment before 31st October 2024, complete demolition before 31st December 2024, and perform Bhumi Pujan on 14th January 2025, the society, on 28th October 2024, resolved to terminate the contract and issued a termination notice dated 23rd November 2024. However, the termination notice does not deal with the new timelines granted by the society.

29.

One grievance raised by the society concerned the developer's failure to furnish a bank guarantee. The developer contended that the parties had mutually agreed that the said amount would be used to pay the premium. However, as per clause 4(a) of the development agreement, the bank guarantee was to be furnished simultaneously with the society granting license to enter the property. As discussed above, the grant of license was subject to the developer's notice to vacate after securing IOD and approved plans. Hence, there is no substance in the grievance regarding not furnishing bank guarantee. Thus, there is substance in the reliance placed by the learned counsel for the developer under Sections 51 and 52 of the Contract Act that when there are reciprocal promises under the contract, delay in completion of contract cannot be solely attributed to the developer. Prima facie, there is substance in the developer’s contention that the finalisation of plans remained pending because the society was pursuing the approval of additional FSI and there was no clarity on how much FSI was to be utilised; hence, the plans were not finalised, and IOD was not obtained.

30.

Considering the society’s conduct of reiterating the request for additional FSI and extending the timelines as recorded in the letter dated 10th September 2024, the developer’s explanation sounds logical and believable that the finalisation of plans remained pending because there was no clarity on how much FSI was to be utilised. Therefore, it appears that all the further process remained pending. Hence, prima facie, the delay cannot be attributed to the developer. I see no valid ground for the society to lose confidence in the developer. From the email dated 24th October 2024 sent to the developer on behalf of the society, it appears that only due the incident of 19th October 2024, the society contended that the members lost confidence in the developer. The email not only tenders apology to the developer but also expresses confidence and trust in the developer. Hence, the decision of this court in Swashray Co-op Housing Society would not be of any assistance to the society’s arguments.

31.

Under the terms and conditions of the contract, the developer was entitled to cure defects and remove obstacles in the redevelopment process. The parties agreed to follow the termination process in clause 21 of the development agreement. All the contingencies provided for termination are subject to issuing a cure notice. The termination notice by the society is based on general allegations of non-compliance without any cure notice and without dealing with the timelines already extended by the society. The society has provided no explanation for passing a resolution on 28th October 2024 to terminate the contract before the expiry of the time extended by the society, for taking further steps as per the timelines informed by the society. In view of the extension of the time for completion of the project, as evidenced by the various letters issued by the society to the developer, including the letter dated 10th September 2024, the time for performance of the developer’s obligation stood extended as provided under Section 63 of the Indian Contract Act.

32.

Once the parties agree under the contract to follow a process for termination, a party cannot unreasonably terminate the contract without offering any explanation for not following the agreed process. Thus, prima facie, the termination notice breaches clause 21 of the development agreement and does not appear valid. Hence, prima facie, the new development agreement in favour of the new developer is executed during the subsistence of the first development agreement. Hence, the developer would be entitled to protect its rights under the development agreement. The reliance placed by the new developer on the Order dated 24th April 2025 in the society’s suit would not render the development agreement in favour of the new developer valid. The said order only recorded the submission of the learned counsel for the developer that the termination was not challenged as the developer was in dialogue with the society. The society’s counsel had disputed the said submissions; hence, this court further observed that there was no impediment in proceeding to appoint a fresh developer.

33.

The developer filed the suit on 14th August 2025. It appears that the society executed the new development agreement in favour of the new developer on 9th January 2026. However, it was not disclosed in the court. This court passed an order dated 9th March 2026 directing that the defendants shall not execute any development agreement or any other agreement.

34.

The society has filed the suit for declaration that the development agreement and power of attorney are validly terminated. The society has further prayed for cancellation of the development agreement and power of attorney. According to the society, the members have suffered prejudice and hardship as they have vacated their flats. However, the members vacated the flats well before execution of the development agreement. Hence, the same cannot be a ground attributable to any default of the developer. The society had already started the self-redevelopment process. However, it was unable to pay the premium, and at that stage, the society decided to appoint a developer.

35.

The society’s reiteration of its request for approval for the pro-rata FSI and VP quota, even after execution of the development agreement, cannot be ignored. As discussed above, because the society requested additional FSI from MHADA, prima facie, it appears to be a valid and justifiable reason for not finalising the plans for approval and securing IOD. The developer's arguments have substance: there was no clarity on whether the society accepted the additional FSI offered by MHADA, and the society’s persistence in seeking additional FSI from MHADA delayed finalising the plans for obtaining IOD. The developer's revised offer included the area both without and with the pro-rata FSI. Thus, when the society was not satisfied with the available additional FSI and intended to seek further FSI, the abrupt action taken to terminate the contract is not justified. The termination of the contract therefore cannot be accepted as a valid termination at this preliminary stage. Hence, the society has failed to prove any prima facie case and balance of convenience.

36.

However, the society is likely to suffer hardship as the members are dishoused. The society has contended that the members have lost confidence in the developer and wants to complete the development process through the new developer and has already executed the agreement. Although the agreement in favour of the new developer is challenged, considering the hardship likely to be caused to the members, the society can be granted permission to compete the redevelopment process through the new developer, subject to conditions. So far as hardship is concerned, it was the society’s decision to vacate even before the development agreement was executed and vacating the flats is not in compliance with any terms and conditions of the contract. The interim prayers made by the society would amount to granting final relief in the suit. The blanket injunction prayed for by the society for permission to appoint a new developer or carry out self-redevelopment cannot be granted without securing or protecting the developer's rights.

37.

The developer has prayed for ₹350 crores towards compensation and damages, in the alternative to grant specific performance of the development agreement. If the developer succeeds in proving that the termination was invalid, the developer can be compensated in terms of money. Given that the redevelopment process was initiated on the ground that the building was dilapidated and MHADA had issued a notice to vacate, the society's prayer for completion of the redevelopment process can be granted by securing the developer's interests. Hence, to strike a balance, the society can be permitted to complete the redevelopment process through the new developer, provided the society secures the claim amount for damages prayed for by the developer and deposits in this court the amount already paid and spent by the developer pursuant to the development agreement.

38.

The developer’s claim for compensation is Rs. 350 crores. The quantification of the claim for compensation is a matter of evidence in the trial. Under the contract, the area to be allotted to the members is specified; however, because the society requested additional FSI from MHADA, the developer’s offer, with and without the additional FSI, is part of the record. Under clause 6 of the development agreement, except the members’ area, the balance area was agreed to belong to the developer, subject to the other terms and conditions of the contract. The plan is not yet approved; the issue of approval of additional FSI by MHADA is still not settled; hence, at this stage, it is not possible to determine the area the developer was likely to receive at its disposal under the contract. The developer has pleaded the likely area that would have received at its disposal and the likely profits that would have been earned. The developer has in the alternative prayed for directing the society to earmark and reserve a suitable portion to secure and protect the developer’s claim.

39.

Hence, considering the strong prima facie case made out by the developer, to strike a balance, the developer’s claim can be secured by directing the society and the new developer to deposit the amount expended by the developer pursuant to the development agreement. The amounts expended are specifically pleaded in the plaint. The plans are not yet approved; however, the society and the developer can be directed to submit the particulars in this court after the plans are approved and also deposit 25% of the amounts that would be received from the free sale component. Considering the likely profits that would be earned by the developer as specifically pleaded in the plaint and the interim application, 25% of the receivables is reasonable to secure the developer’s claim.

40.

Hence, for the reasons recorded above, the interim applications are disposed of by passing the following order:

a)

The society, i.e. the plaintiff in Suit No. 1 of 2026 and defendant no. 1 in Commercial Suit No. 22 of 2026, is permitted to complete the redevelopment process through the new developer, i.e. defendant no. 2 in Commercial Suit No. 22 of 2026, subject to the following conditions:

(i)

The society, i.e. the plaintiff in Suit No. 1 of 2026 and defendant no. 1 in Commercial Suit No. 22 of 2026 and the new developer, i.e. defendant no. 2 in Commercial Suit No. 22 of 2026, shall deposit in this court an amount of Rs. 3,38,81,888/- within four weeks from today.

(ii)

The society, i.e. the plaintiff in Suit No. 1 of 2026 and defendant no. 1 in Commercial Suit No. 22 of 2026 and the new developer, i.e. defendant no. 2, in Commercial Suit No. 22 of 2026, shall file an undertaking within two weeks from today, stating that the copy of the approved plan and the area statement as per the approved plan shall be placed on record of this court along with an affidavit within two weeks from the date of approval of the plan and serve a copy of the same to the advocate for the plaintiff in Commercial Suit No. 22 of 2026.

(iii)

The new developer, i.e. defendant no. 2, in Commercial Suit No. 22 of 2026, shall file an undertaking within two weeks from today, stating that 25% of the consideration amount that would be received from the free sale component shall be deposited in this court within four weeks of receiving the amount and file a copy of the agreement in this court along with an affidavit and serve a copy of the same to the advocate for the plaintiff in Commercial Suit No. 22 of 2026.

b)

Failure to file the affidavits as directed above and/or any breach of the above conditions shall automatically result in cancellation of the permission granted in terms of clause (a) hereinabove.

c)

The amounts so deposited in this court, as per the directions above, shall be invested in fixed deposits in any nationalised bank and shall remain invested until disposal of the suits or until further directions are issued by this court.

d)

The amounts so deposited in this court, as per the directions above, shall be subject to the outcome of the suits.

41.

The interim applications are disposed of in the above terms.

There shall be no order as to costs.

Footnotes

  1. 1.2023: BHC-OS: 13075