Tribunals and CommissionsFull Bench(2021) 11 NCLAT CK 0042

Anand Murti vs Soni Infratech Pvt Ltd & Anr

National Company Law Appellate Tribunal · Decided on 22 November 2021

HON’BLE JUDGES
M. Venugopal, Member (J) · V.P. Singh, Member (T) · Dr. Alok Srivastava, Member (T)
RESULT
Dismissed
CASE NUMBER
Company Appeal (AT) (Insolvency) No. 1507 of 2019

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

402 paragraphs · 4,740 words

V. P. Singh, Member (T)

1.

This Appeal was filed against the order of the Adjudicating Authority passed on 22nd November 2019, whereby the petition filed under Section 7 of the Insolvency and Bankruptcy Code, 2016 was admitted, and Interim Resolution Professional Mr Bhim Sain Goyal was appointed.

The Appellant  had filed  the  Application  IA  No.1115  of 2020  for modification of the order dated 26th February 2020.

2.

The sequence of events clarifying the development during the Appeal is given in the form of a chart, which is as under:

17th  December 2019

CA/AT/1507    of    2019

filed against the order of the              Adjudicating Authority    dated    22nd November 2019

The learned Adjudicating Authority  has  admitted the  petition  filed  under Section 7 of the code by the impugned order.

19th December 2019

The  interim  stay  order was    passed    by    this Appellate           Tribunal

restraining                 the

Constitution                of Committee of Creditors.

31st January 2020

Based          on          the submissions      of      the Appellant that he will be filing               settlement terms/plan disclosing all material particulars with regard to the completion of  the  Project,  sources from which the Appellant will  be  arranging  funds for   completion   of   the Project   and   the   time frame  within  which  the possession  can  be  given to    the    allottees,    this Appellate           Tribunal provided  15  days   with further orders to resume CIRP, if no settlement is filed in 15 days.

17th February 2020

RP was directed to file a status report.

26th February 2020

This  Appellate  Tribunal passed   an   order   that CIRP     is     related     to Housing              Project. Therefore,     since     the settlement  agreement  is not       all-encompassing interim   directions   was modified, and order was passed,       IRP       shall proceed       with       CoC formation.

05th March 2020

Civil Appeal 1928 of 2020 filed    Hon'ble    Supreme Court against the order of the    Appellate    Tribunal dated     26th        February 2020.   Hon'ble   Supreme Court   passed   an   order that    "in    view    of    the statement   made   by   Sri Shyam   Devan,   learned senior counsel appearing for the Appellant that the Appellant                would approach    the    National Company  Law  Appellate Tribunal, New Delhi with the       Application       for modification     of     order

dated  26.2.2020  on  the ground  that  settlement plan    filed    on    13th

February  2020  covers

all the allottees.

We        permit        the Appellant to move such an     application     for modification.      There would   be   liberty   to approach this court in case  such  Application is not allowed.

The      aforementioned Application   shall   be filed within a period of one  week  from  today. There shall be interim stay  of  the  impugned order  for  a  period  of two weeks from today."

19th March 2020

The learned Counsel for the Appellant made a statement that settlement plan takes care of all the allottees as the Appellant has settled with Respondent No. 2 and provides for a plan regarding the completion of the Project. It is pointed out that 72% to 75% of the Project has been completed, and funds have been arranged from private sources to complete the Project as per the proposed settlement terms filed on 13.2.2020.

Based on the statement of the Appellant's Counsel IRP was directed to submit a status report providing the details regarding the allottees; who want possession of flat; allottees who have committed a default and; allottees who wanted a refund of the money.

21st September 2020

Objection against settlement plan was invited.

25th February 2021

Based on the status report, this Appellate Tribunal issued a direction to submit a revised proposed settlement plan within two weeks so that they can decide whether reverse Insolvency Resolution Process will be adopted or CIRP be restored?

19th March 2020

The  learned  Counsel  for the   Appellant   made   a

statement                 that settlement plan takes care of all the allottees as the Appellant has settled with Respondent No. 2 and provides for a plan regarding the completion of the Project. It is pointed out that 72% to 75% of the Project has been completed, and funds have been arranged from private sources to complete the Project as per the proposed settlement terms filed on 13.2.2020.

Based  on  the  statement of       the       Appellant's Counsel IRP was directed  to submit a status report providing the details regarding the allottees; who want possession of flat; allottees who have committed a default and; allottees who wanted a refund of the money.

21st September 2020

Objection             against settlement     plan     was invited.

25th February 2021

Based    on    the    status report,    this    Appellate Tribunal       issued       a direction   to   submit   a revised              proposed settlement   plan   within two  weeks  so  that  they can     decide     whether reverse           Insolvency

Resolution   Process   will be  adopted  or  CIRP  be

restored?

Appellant had filed the Application IA No.1115 of 2020 for modification of the order dated 26th February 2020.

3.

In  this  IA,  Appellant  has  stated  that  it  had  filed  the  settlement terms/plan detailing the Plan disclosing all materials particulars with regard to completion of the housing project, so if the Appellant is allowed to work upon his detailed proposal, then all the allottees will get the house. Therefore, in such circumstances, Appellant has settled the matter with Respondent No.2 and has filed a Settlement Terms/Plan in regard to the completion of the Project.

4.

It is further added that if the IRP is allowed to go ahead with the constitution of the Committee of Creditors and carry on the CIRP, then the Appellant, despite having settled the matter with respondent No.2 and having a plan for completion of the Project, will have to hand over the management of the Project. At present, the Applicant/Appellant has completed about 70-75% of the infrastructure project. He has arranged the funds/private financer to complete the Project as per the Appellant's proposed Settlement Term/Plan on 13th February 2020.

5.

Given the above, Appellant requested to modify the order dated 26th February 2020 in the light of the order dated 05th March 2020 passed by the Hon'ble Supreme Court in CA No. 1928/2020.

6.

Interveners/Non-Applicants had filed objections against the Application for modification of order dated 26th February 2020, registered at Diary No.21937 dated 14th September 2020. In the said objections, the objector has stated that the Application filed by the Appellant is against the interest of Home Buyers/Financial Creditors and the very object and purpose of the IBC and allowing the present Application tantamount to abuse/misuse of provisions of IBC.

7.

The objector contends that the said settlement agreement proposed by the Appellant was not encompassing all the home buyers, and considering the miseries of the home buyers this Appellate Tribunal had passed order dated 26th February 2020 to modify the interim order dated 19th December 2019 to stay the CIRP, thereby directing the IRP to go ahead with the constitution of Committee of Creditors and carry forward with the CIRP of the Corporate Debtor.

8.

Thereafter, the Appellant had challenged the said order before the Hon'ble Supreme Court and made a misleading statement that the Tribunal has failed to consider the settlement agreement/plan filed by the Appellant. However, Hon'ble Supreme Court did not intervene with the order passed by this Tribunal. Still, it directed the Appellant to file a modification application given the settlement plan encompassing all the allottees.

9.

Given the order of the Hon'ble Supreme Court, the Appellant has filed the modification application. Appellant made the statement before the Hon'ble Supreme Court that the settlement plan on 13th February 2020 covers all the allottees. Before proceeding further, it is necessary to give a snapshot of the settlement plan submitted by the Appellant dated 13th February 2020. The relevant portion of the settlement plan is reproduced as under:

"Phase-I comprising 12 towers (T1-T12) and Phase-II comprising of 4 Towers (T13-T16).

Tower-wise details of sold/unsold units alongwith its area are as under:

Tower No.

Total Area

Sold Area

Balance

Total Unit

No. of Unit Sold

Balance Unit

T 1

92570

92570

0

56

56

0

T 2

90250

90250

0

56

56

0

T 3

110832

110832

0

56

56

0

T 4

110832

110832

0

56

56

0

T 5

129680

121360

8320

54

52

2

T 6

110832

110832

0

56

56

0

T 7

129988

117366

12622

56

52

4

T 8

97084

87326

9758

40

37

3

T 9

29990

24292

5698

10

8

2

T 10

29990

24211

5779

10

8

2

T 11

29990

20622

9368

10

7

3

T 12

29990

24125

5865

10

8

2

Total

992028

934618

57410

470

452

18

Tower-wise cost to be incurred and receivable from sold/unsold area is as under:

Tower No.

No. of

Total Sold

Balance amount

Receivable From

Total receivable

Const- ruction

Flats

Flats

receivable

Unsold

cost to

from sold

Flats

be

Flats

incurred

T 1

56

56

8.03

0.00

8.03

2.679

T 2

56

56

9.14

0.00

9.14

2.606

T 3

56

56

11.71

0.00

11.71

3.383

T 4

56

56

11.70

0.00

11.70

3.826

T 5

54

52

16.96

4.58

21.53

4.615

T 6

56

56

10.82

0.00

10.82

3.911

T 7

56

52

12.46

6.94

19.40

4.454

T 8

40

37

15.67

5.37

21.03

2.325

T 9

10

8

6.16

3.13

9.29

1.452

T 10

10

8

4.72

3.18

7.90

1.452

T 11

10

7

6.50

5.15

11.65

1.450

T 12

10

8

4.36

3.23

7.59

1.450

Common Area cost to be incurred

19.1518

Commer-

cial

6.30

6.30

-

EWS

1.05

1.05

-

Total

470

452

118.222

38.926

157.148

52.726

(vi) Proposed Plan

The Project is near to completion and almost 70% of the construction is completed. The management is committed to the buyers and has therefore proposed a resolution plan to complete the Project and seeks support from all the customers.

The key concern of the home buyers of Orion Galaxy are:

(a) Restart of construction work of Project and completion thereof at the earliest;

(b) Payment of dues of DGTCP and others.

To redress concerns of unit buyers, the Company offered the following revival plan:

Management   of   the Project

The Project will be managed as per the    directions    of    the    Hon'ble Tribunal  under  the  supervision  of IRP.

Construction   of   the Project

Existing  Contractor  has  agreed  to continue the construction work and have     shown     faith     with     the management.

Funding

(i)   The  Total  Cost  to  complete  the Phase-I  of  the  Project  122.28 Crores.

(ii)   The Project can be run through receivable from sold and unsold area  of  the  Project  of  Phase-I. The  total  receivable  from  the Sold and unsold area of Phase-I is Rs.157 Crores.

(iii)  The  Promoter  will  also  arrange initial    funds    to    start    the construction    of    the    Project. Where   ever   there   is   liquidity crunch    the    Promoter    shall arrange funds.

Delivery   &   Quality commitment

a)   No additional charges

b)   There will be no changes in area

c)   There will be no changes in specification

d)   Quality    of    work    shall    be maintained as committed.

e)   Approach road will be provided before completion of the Project.

f)    EDC/IDC will be charged as per actual demand by DTCP.

Development          & Delivery Schedule

Delivery  schedule  -  application  of OC

a)   T8-T12 - 6 months +/- 2 month

b)   T1-T4 - 12 months +/- 2 month

c)    T5-T7 - 15 months +/- 2 month Construction   of   Phase   2   to   be started by end of 12 months to raise further  fund  as  the  booking  of  the second phase is not yet done.

Customer payments

Demand  will  be  raised  as  per  the CLP plan as per the existing BBA

Refund   in   case   of cancellation           of booking

If   there   is   any   refund   against cancellation  of  flat  by  any  home buyer  then  we  shall  consider  to refund the same after handing over the possession to the home buyers who want to take the possession of

the flat in the Project.

Delay Compensation

No   claims   against   the   previous delays.  Delay  compensation  shall only be paid if there is delay as per the  resolution  plan  implementation

as    per    the    Hon'ble    Tribunal direction/order.

Utilization             of customer funds

Proposed mechanism

The  developer  shall  utilize  the funds in the completion of Tower T1-T12   as   per    the   tabular representation   above   in   the following manner:

(i)     70% of total collection shall be used     for     construction     till Application of OC.

(ii)    30% of total collection shall be used   for   payment   of   EMI, Salary and other project related expenses.

The     proposed     mechanism     of

utilization  of  funds  received  from customers is enclosed as Annexure BB

Repayment   of   New Fund

Payment  of  interest  of  fresh  loan shall be made from 30% collection.

Repayment             of Edelweiss

Repayment  of  Loan  to  Edelweiss shall be made from the surplus of T1

-T12  and  after  commencement  of

construction of Phase-2.

Customer commitment

Customer commitments

·    EDC/IDC  shall  be  payable  as

per actual demand by DTCP.

·    Customer shall pay car parking charges when demanded.

·    Customer   shall   pay   the   past overdues  within  45  days  from the start of the construction.

·    The  customer  shall  pay  all  the statutory dues like GST, VAT or any   other   taxes   or   levies   as imposed by the Government.

Approvals/consent from customers

·    Change  in  plans  of  T8-T12  and phase 2 if any

·    Any other permission required by Government  authorities  or  any legal entity for the Project.

Customer cases

·    All the cases/complaint of all the types  including  RERA  shall  be withdrawn /settled by the home buyers immediately to smoother the movement and active efforts

of promoters.

10.

It  is  important to mention  that  in  the  settlement  plan dated  13th February 2020, there is no mention of the consent of the allottees in respect of the said settlement plan.

11.

It is pertinent to mention that after filing the First Settlement Plan dated 13th February 2020, the Appellant filed a revised settlement plan dated 15th March 2021 in compliance with this Tribunal's order dated 25th  February 2021. Appellant has stated that:

"That in compliance of the order of Hon'ble Appellate Tribunal dated 25.02.2021; the Appellant is hereby submitting the Revised Resolution Plan clearing the ambiguity as directed by this Hon'ble Bench along with the affidavit by the Promoter.

That the IRP has obtained the clarification on the costing of the projects from the independent Architect and Audit company "Qonquest". The "Qonquest" has submitted the latest report to the IRP confirming the total costs required in the project tower wise.

That the ECL Finance has given its approval about further financing the Project, based on the personal guarantee of Promoter and accordingly submitted its Provisional approval to IRP.

That Promoter has planned to infuse Rs.5 Crore to immediately start the Project.

The Promoter is in discussion with the M/s Indsao and few more contractors who has shown faith and willing to complete the balance construction work under the Promoter which will be finalized in few days.

That in order to more clarity on the funds utilization the Promoter has annexed a plan for the proper utilization of funds and its planning to maximize the uses in order to complete the projects in time as per the Resolution plan.

(c) Planning of the Promoter to execute the Project

Since in Phase-I of the Project, where 94% area is sold out and 70% of construction is completed, therefore, the Promoter is planning to complete the Phase-I on priority basis.

Further, the Promoter wants to star Phase-II of the Project where only 12% of area is sold only after completion of Phase-I or when atleast 75% units will be booked. Since there are only 22 units booked and allotted in Phase-II and the Company has collected only initial booking amount of Rs.3.67 crores, therefore, the Promoters is planning to either request the customers of Phase-II to wait to restart of the construction or may refund the amount by selling those units to other buyers.

(iv) Cost to Complete the Phase-I and Proposed Planning of Funds

As per the estimation of the Promoter, balance cost of construction of Phase-I is approx 52.73 crores. However, as per the report of independent Architect and Audit Company "Qonquest" submitted by the IRP, the balance cost of construction of Phase-I is approx Rs.71.21 crores and on the conservative basis, even if we consider the balance cost of construction is Rs.71.21 crores, the total balance cost to complete the Phase-I of the Project will be Rs.122.28 crores as per the following details:

(B) Proposal/Planning of Promoter to complete Phase-I of the Project

The Promoter wants to deliver the units in T1-T12 of Phase-I of the Project in three stages in time bound manner.

Particulars

Tower

Time

Stage-I

T8-T12

Within 6-9 months

Stage-II

T1-T4

Within 12-15 months

Stage-III

T5-T7

Within 15-18 months

To complete the construction and completion of Phase-I of the Project, it is required some initial infusion of funds to mobilize and restart the construction in full swings, so that the confidence of home buyers can be restored in the Project and on the existing promoters. In order to regain the confidence of home buyers, the promoters are ready to infuse 20 crores in the Project in the following manner:

i. Infusion of further 15 crores by taking interim finance from Edelweiss on the basis of personal guarantee of the existing Promoter. The Edelweiss has issued the Loan approval of Rs.15 Crore to the Ld IRP, the copy of the Approval Letter of the loan is marked and annexed as Annexure-D.

ii. Infusion of Rs.5 crores to mobilize and restart the construction. The Promoter has given the letter to IRP stating of infusion of Rs.5 crores which is annexed as Annexure-E."

12.

It is further necessary to mention that the IRP has submitted the status report on aspects of the revised Plan dated 26th March 2021 (Diary No. 26426). IRP has stated that:

"1. CONSTRUCTION STATUS

The Project is approximately 70% complete, but the work is about 80% complete in Tower-8, and this tower has maximum unsold inventory. Tower 9-12 has just 10 flats in each tower. The Plan submitted by the Applicant to take Tower 8-12 in stage-1 is logical, and this stage can be completed within 6-9 Months. Some Plumbing and Electrical work is done in Tower 1-13, and the remaining Plumbing and Electrical work can be carried out in all the remaining towers, side by side, while completing construction of Tower 8-12.

According to discussions with the technical consultants, architects and contractor, the Project of Phase-1 (Tower 1-12) can be completed within the total period of 18 Months, provided the funds flow is continued. This period is extendable by 3 Months for making Application for 'occupancy certificate' and obtaining approvals before delivery of flats.

3.

Funds Flow

The Applicant has considered 100% inflow of funds at the completion of every stage of construction, which is practically not possible. After analysing that 86 Homebuyers (19%) in Phase-I have not yet submitted their claims, I have observed that the corporate debtor will not get more than 90% of balance dues from Homebuyers, and in case of unsold flats, the corporate debtor will not get more than 60% after sale of flats, until the Project is completely delivered. Keeping in view the above assumptions, I have changed the inflow and usage of funds, as per Annexure-II.

In my report dated 22.02.2021, I have reported that the balance dues receivable by the corporate debtor are Rs.120.38 crore. The Balance dues are overstated by Rs.2.48 crore on account of IFMS increased from Rs.50 per SQFT in the BBA, to Rs.75 per SQFT, due to increase in maintenance liabilities of corporate debtor increased from 2 years earlier to 5 years now, by change in Govt. policy. IFMS dues are in the nature of security from the allottees, and cannot be used for construction activities thus reducing the available funds for construction by another Rs.4.8 crore.

Further the Applicant verbally informed me that he has commitments of giving special rebate of an aggregate value of Rs.1.25 crore approximately, to some homebuyers who paid their instalments in advance when construction activities were going on.

In view of the above, the balance dues receivables from the Homebuyers are Rs.111.85 crore. I further submit that many homebuyers/their lawyers visited my office/checked over phone, and I made their information of 'payment made' and 'the balance dues' available to them.

4.

HOMEBUYERS CONCERNS:-

The homebuyers opposing the 'Proposed Settlement Plan' have expressed their concerns relating to the Plan (Annexure-III), as below:-

1.

The Applicant is not a trustworthy person, and he can run away after selling the 'Unsold Flats'.

2.

The Applicant cannot be trusted with the quality of construction and timely delivery, and hence he should be a 'Financial Investor' only to complete the Project. If there is any problem in 'Funds Inflow', the Applicant should give an affidavit that he will bring additional funds.

3.

The Plan talks about the 'Approach Road' but it does not say that the land will be bought to build the approach road, which the Applicant promised to the Homebuyers.

4.

The Plan is not clear about the payment of EDC/DC charges. Whether Homebuyers will pay as per BBA or as per demand by DTCEP

5.

On page 23, under the head 'Utilization of Customer Funds', 30% of total collection shall be used to pay EMI etc, what EMI means in this Plan.

6.

On page 24, under the head 'Approvals, consent from customers', it is mentioned that 'change in plans of T8-T12 and Phase-2, if any. The construction of 'Tower 8-12 is scheduled to commence immediately, and the customers are not concerned with Phase-2, than what is the purpose of this condition.

7.

On page 24, under the head 'Customer Cases', there is a condition to withdraw all cases/complaints shall be withdrawn/settled by the Homebuyers immediately. This condition is unfair until the flats are delivered to the homebuyers.

8.

The Homebuyers has shown concern on the 'Balance Dues receivable' by the corporate debtor. I have addressed their concern by sharing their information with them/their lawyers.

9.

The Homebuyers has a major concern that the approval of Proposed Settlement Plan' will result into 'No action against the Applicant for preferential/undervalued transactions. The funds required to complete the Project should be inducted as 'Reverse of preferential/undervalued transactions'.

5.

CONTRACTOR'S CONCERNS:-

Indsao Infratech informed that he had discussions with the Applicant and is ready to restart construction immediately. He further requested that as an 'Operational Creditor', he has submitted a claim of Rs.2.33 Crore and requested that he shall be paid Rs.12.50 Lakh per month from his claim amount (Annexure-IV), which he will reinvest in the completion of Tower 1-Tower 12.

6.

ECL FINANCE LIMITED

Mr Chirayush Agarwal, an officer of Edelweiss (Secured Creditor) visited my office and informed me that his Company supports the 'Revised Settlement Plan'."

13.

It is pertinent to mention that the existing Promoter was originally landowners of the land on which the Project "Orion Galaxy" is situated and had entered into the development agreement with erstwhile promoters of the Company to develop the project "Orion Galaxy". However, due to various reasons, the Project could not be completed by the erstwhile promoters on time, and as a result, the existing Promoter took control of the Project in 2017 and finally got complete control of the Company after 31.10.2019 when the existing Promoter purchased 100% shares of the Company after the order of NCLT, New Delhi in the matter of petition bearing CP No.175/241/242/(ND)/2018.

14.

The Company has mainly launched Phase-I of the Project, in which 470 units, out of 542 units, have been sold out. In Phase-II, the Company has booked only 79 units, out of which 57 units have been booked and allotted to related parties, and only 22 units are sold to end-users/customers.

15.

The existing Promoter/Suspended Directors of the Company justifying the purported settlement plan submits that "the Company requests to all the Stakeholders of the Company and the Project, to approve the aforesaid revival plan and allow the Management/Promoter to restart the construction. There are the following major reasons to approve the Revival Plan in the best interest of the Project and the Company:

a) The existing management is fully aware of the Project; in case

there is a change in the management, the new management will take time to understand the various aspects of the Project.

b) The CIRP process will only delay and proposed revival plan. However, the existing management will complete the Project within 15 months.

c) The  CIRP  process  will  additionally  burden  the  Project  with

additional costs.

d) There is no clarity on who will bid for the Project and what will be offered.

e) The management has agreed to hand over the Project in a time-bound manner and without any additional cost burden to the Buyer.

f) The existing management will provide an approach road before completion of the Project.

g) The Promoters has agreed to provide Personal and Corporate Guarantee for taking finance for the Project and made the provision and back up to start immediately without wasting any time."

16.

It is important to mention that no settlement plan encompassing all the allottees has been filed to date. The allottees of different groups have filed IA 183 of 2020, 184 of 2020 dated 10th January 2020, IA 205 of 2020 dated 13th January 2020, IA 330 of 2020 dated 22nd January 2020, IA 366 of 2020 dated 31st January 2020, IA 560 of 2020 dated 03rd February 2020, IA 738 of 2020 dated 13th February 2020, IA 739 of 2020 dated 13th February 2020 and 756 of 2020 dated 14th February 2020 for Impleadment. Only some of them favour the purported settlement plan, and others oppose the scheme. However, it is undisputed to date there is no consensus among the allottees for the said settlement plan.

17.

In its latest status report, Interim Resolution Professional submitted that some homebuyers want that reverse CIRP as a better option because the Promoter offered to deliver flats at Builder Buyer Agreement prices. The Promoter is ready with money for immediate construction activities, and the Promoter has agreed to buy land for road connectivity after completion of construction. It is also reported that some homebuyers want that Project to be completed through the CIRP process, as they cannot trust the Promoter under any circumstances.

18.

It is important to mention that by our order dated 26th February 2020, we have directed the Interim Resolution Professional to go ahead with the constitution of the Committee of Creditors and carry forward the Corporate Resolution Process. This order was challenged before the Hon'ble Supreme Court in Civil No. 1928 of 2020 but was not entertained. However, Hon'ble Supreme Court directed the Appellant to approach this Tribunal and file the Application for modification of the order dated 26th February 2020 based on the settlement plan filed on 13th February 2020, which covers all the allottees.

19.

It appears that the Appellant made a misleading statement before the Hon'ble Supreme Court that the settlement plan dated 13th February 2020 covers all the allottees. In fact, to date, there is no settlement plan covering all the allottees. There is no consensus among the allottees. Some of the Allottees favour the Settlement Plan, and others oppose the same. There is nothing on record to show that there is consensus for the purported Settlement plan. There is a trust deficit among the homebuyers. The proposed Reverse Insolvency appears to be a device for buying time. Based on the settlement plan and lack of consensus among allottees of flats and the present Promoters, there is no hope of success in arriving at a settlement. Thus, we are of the considered opinion not to delay the CIRP proceeding on the pretext of the so-called reverse CIRP.

20.

In the circumstances, we observe that the Settlement Plan dated 12th February 2020 and the further Revised Settlement Plan dated 12th March 2021 deserves to be rejected. We do not think it proper to provide any further time for getting consensus for arriving at a settlement for completion of the Project. However, the settlement process is provided under Section 12A of the Insolvency and Bankruptcy Code, 2016. Therefore, if settlement takes place, the same can be filed U/S 12 A of the Code before the Adjudicating Authority.

21.

We further direct IRP/RP to hold the meeting of the Committee of Creditors within ten days from the date of order and decide a future course of action about a resolution for completion of the CIRP of the Corporate Debtor. The Appeal is listed for hearing on 25th November 2021. Parties may file their notes of submission not only in soft copy but also in hard copy with a copy in advance to opposite parties before the next date of hearing.