High CourtsSingle Bench(2010) 09 MAD CK 0237

Allwyn Builders, Engineering Contractors vs Union of India (UOI) and K. Ravindran

Madras High Court · Decided on 30 September 2010

HON’BLE JUDGES
K.B.K. Vasuki, J
RESULT
Allowed
CASE NUMBER
Writ Petition No. 6455 of 2010

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

13 paragraphs · 634 words

K.B.K. Vasuki, J.—The learned standing counsel for the respondent 1 and 2 is present. Though the 3rd respondent is duly served with notice he does not make his appearance before this Court. On consent, writ petition is taken up for final hearing at the admission stage.

2.

The relief sought for herein is for forbearing the respondents 1 and 2 from processing and considering the 3rd respondent''s tender document along with other sealed tenders submitted in respect of item 7 of the tender notice No. MAS/09 of 09 dated 05.11.2009 issued by the first respondent.

3.

The facts remains undisputed are that the first respondent floated tender notice on 05.11.2009 inviting sealed tenders in respect of several items of works one among which related to the supply of coarse river sand. The tender notice was issued subject to terms and conditions contained in the tender schedule enclosed at pages 1 to 14 of the typed set of papers filed by the petitioner.

4.

The petitioner, the 3rd respondent and few others participated in the same by submitting their tender. The main grievance raised by the petitioner herein is that the tender submitted by the 3rd respondent does not satisfy two of the conditions, and the tender ought not to have been for non-fulfillment of the tender requirement opened and taken up for consideration along with the tenders submitted by others, which are in strict compliance with the conditions contained in the tender schedule. The two of conditions which are admittedly not complied with by the 3rd respondent are enclosed at pages 2 and 13 of the typed set of papers as follows:

PAGE - 2 ITEM No. 07 OF TENDER NOTICE No. MAS/09 OF 2009 DATED 5-11-09 DUE ON: UPTO

TO

FROM

Note: This page is to be pasted on the top of the sealed cover, used for submitting the tender, without which tenders will not be opened.

PAGE - 13

25.

Submission Tender: Tender must be enclosed in a sealed cover, super scribed "Tender Notice No. MAS/09 of 2009"/" Item No. 07" name of work - As per the schedule" and must be sent by registered post to the address of the Divisional Railway Manager/Works/MAS/Southern Railway so as to reach his office not later than 11.00 hours on 11.12.09. Or deposited in the special box allotted for the purpose in the office of the Divisional Manager/Works/MAS, Southern Railway. This special box will be sealed at 11.00 hours on 11.12.09. The tender will be opened at 11.30 hours on the same day. The tender papers will not be sold after 15.00 hours on 09.12.09.

5.

It is fairly conceded by the learned standing counsel for the respondents 1 and 2, that the II respondent has not pasted page 2 on the top of the sealed cover used for submitting the tender and instead of super scribing as "tender notice MAS/09 of 09 item 7" the same is written as "Item 6" on the top of the sealed cover. The same certainly amounts to failure to strictly comply with the tender conditions.

6.

That being so, the tender submitted by the 3rd respondent is as per the instructions No. 2 enclosed at Page 1 of the typed set of papers in violation which renders the tender submitted by the 3rd respondent not to be opened but to be rejected. However, the respondents 1 and 2 have opened it and allowed the same to be considered along with other tenders submitted by the petitioner and others. Such action on the part of the respondents is illegal and without jurisdiction and against tender conditions and the same entitles the petitioner to get the relief as sought for herein.

7.

In the result, writ petition is allowed as prayed for. No costs. Consequently, connected miscellaneous petition are closed.