High CourtsSingle Bench(2021) 06 CHH CK 0104

Abp Travels And Facility Management Pvt Ltd vs State Of Chhattisgarh

Chhattisgarh High Court · Decided on 28 June 2021

HON’BLE JUDGES
Goutam Bhaduri, J
RESULT
Dismissed
CASE NUMBER
Writ Petition (Civil) No. 2547 Of 2021

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

24 paragraphs · 511 words

Heard

1.

The present petition is filed for following reliefs:-

10.1 That the petitioner most humbly and respectfully prays to this Hon'ble Court to issue appropriate writ/order/direction to the respondent authorities

to consider the representation of the petitioner forthwith and after consideration of the representation the respondents shall issue work order in favour

of the petitioner.

10.2 Any other relief whatsoever, this Hon'ble Court may deem fit and proper may also be granted to the petitioner.

2.

Learned counsel for the petitioner would submit that bid was submitted by the petitioner for ""selection of service provider for Fleet Management of

102 Mahatari Express"" and according to the tender documents including the salary of driver, insurance charges and other incidental charges the

petitioner (L-3) has quoted price bid of Rs. 1,60,983/- while the other L-1 quoted the price bid of Rs. 97,104/- and L-2 quoted with price bid of Rs.

1,08,102/-. He further submits that the L-1 has been eliminated as he was not able to qualify the techno bid and now the petitioner (L3) and L2 are left

and there is 40 % difference between the quoted prices. It is stated that it would be impossible for L-2 who has quoted price bid of Rs. 1,08,102/- to

perform the contract within the said amount. Learned counsel further submits that therefore, under the circumstances, the petitioner has filed an

application before the respondents to reconsider the same which is not being decided. He would further submit that again as it has happen in past

there would be repetition of the tender process and the main purpose for which bid was floated would be defeated.

3.

Learned State counsel submits that he is unable to understand the issue that if someone has quoted low rate what problem will the petitioner is going

to face. He further submits that in respect of the repetition of tender he do not have any instructions and right of the petitioner is pre mature.

4.

Perused the documents and heard the learned counsel for the parties.

5.

Submissions of the petitioner would show that the tender is not yet finalized and if the petitioner has quoted bid of Rs. 1,60,983/- and L-2 has quoted

bid of Rs. 1,08,102/- it is for the respondents to decide the issue for the reason that both have qualified the techno bid. The claim of the petitioner to

eliminate L-2 for the reason that it is unreasonable cannot be accepted by this Court, it is for the respondents to harp upon it whether such quoted rate

is workable or not. If L-2 is unable to perform at the quoted bid, despite the acceptance of the contract, it is for him to bear the burnt and the

application of the petitioner that the quoted bid by L-2 is unreasonable cannot be accepted by this Court as a conclusive proof of fact. The petition has

no locus at this stage when the tender have not yet been finalized.

6.

In view of this, the petition sans merit is liable to be and is hereby dismissed.