This is an application seeking review and modification of the final Order passed by this Commission in CC No. 1121 of 2018 on 27.1.2025.
The Applicant/original Opposite Party seeks modification/ clarification in the aforesaid Order in the following manner –
(i)A clarification in the final order dated 27-01-2025 to the extent that while computing the decretal amount, the amount of Rs. 5,12,241/- already paid/credited towards delay compensation to the complainant be adjusted; and
(ii)Consider the subsequent clarification by the Hon’ble Supreme Court in DLF Home Developers Limited and Another Vs. Capital Greens Flat Buyers Association and Others, (2021) 5 Supreme Court Cases 537, whereby Hon’ble Supreme Court has clarified that in Wg Cdr. Arifur Rahman Khan Vs. DLF Southern Homes Pvt. Ltd., 2020 SCC OnLine SC 66, compensation at 6% was ordered to be paid in addition to the contractual rate since the amenities agreed to be provided by the developer has not been set up; and accordingly modify the final order restricting the award to only one compensation.”
Considered; The prayer to have the amount of Rs. 5,12,241/- already paid/credited towards delay compensation by the Opposite Party in the final entitlement of the compensation payable to the Complainant does appear to be in order.
However, the second prayer to modify the Order regarding award of compensation @ 6% p.a. apart from the contractual rate as fixed between the parties, on the basis of the decision of the Hon’ble Supreme Court, which was subsequent to the earlier decision in “Wg Cdr. Arifur Rahman Khan Vs. DLF Southern Homes Pvt. Ltd. 2020 SCC OnLine SC 66,” is not tenable. A Review Application cannot be used as a disguise to make this Forum sit in Appeal over its own Order passed earlier on merits.
Consequently, the instant Application is allowed in part qua the first prayer made by the Applicant as re-produced above. Resultantly, the following line shall be added at the end of Para No. 15 of the Order under review –
“Any amount already paid/credited towards delay compensation by the Opposite Party in calculating final entitlement of the compensation payable to the Complainant is to be adjusted accordingly”.
This Order shall form a part of the final Order dated 27.1.2025.