Apex Court Shields Award Debtors: Section 9 Protection Granted in Rare Cases
Interim Relief under Arbitration Law Validated for Unsuccessful Parties
High Court's ₹3.5 Crore Deposit Mandate Upheld to Prevent Unjust Enrichment
By Vishwas Kumar
New Delhi: August 14, 2026:
In a ruling under Indian arbitration jurisprudence, a Division Bench of the Supreme Court of India comprising Justice K. V. Viswanathan and Justice Alok Aradhe clarified the statutory contours of interim protection for award debtors. Deciding the case of National Projects Construction Corporation Ltd. v. Ishvakoo (India) Pvt. Ltd. (Civil Appeal No. 5819 of 2025), the Bench held that an unsuccessful party in arbitration—commonly designated as an award debtor—is not automatically barred from seeking interim measures under Section 9 of the Arbitration and Conciliation Act, 1996. The Court affirmed that under rare and compelling circumstances, Section 9 can be invoked post-award to preserve the subject matter in dispute, prevent unjust enrichment, and safeguard the efficacy of pending set-aside proceedings under Section 34.
Genesis of the Commercial Dispute
The underlying conflict dates back to August 16, 2002, when National Projects Construction Corporation Ltd. (NPCC) entered into a Memorandum of Understanding (MoU) with Ishvakoo (India) Pvt. Ltd.. The agreement pertained to infrastructure development works, including bus terminals at the Taj Mahal Bus Stand, UPST Bus Stand, Idgah Bus Stand, and the broader development of the Taj Trapezium Zone (TTZ) Heritage Corridor in Agra, Uttar Pradesh.
To facilitate project execution, NPCC disbursed a sum of ₹3.5 crore to Ishvakoo as a mobilisation advance in December 2002. In return, Ishvakoo provided matching bank guarantees (Nos. 109/2002 to 124/2002) issued by Canara Bank as security.
As execution disputes erupted, the contractual relationship unravelled, leading to the invocation of arbitration. During early interlocutory proceedings in 2003, Ishvakoo sought to restrain NPCC from encashing the bank guarantees under Section 9. On December 15, 2005, the High Court disposed of the petition after recording an undertaking that Ishvakoo would keep the guarantees alive throughout the arbitral proceedings and any subsequent Section 34 challenge. Crucially, the High Court clarified that NPCC could invoke the bank guarantees only if, upon final adjudication, an executable award established that NPCC was entitled to recover funds.
Encashment and the Arbitral Award
As arbitral proceedings stretched over a decade, Ishvakoo eventually faced financial strain and became unable to renew the bank guarantees. Consequently, around September 2017—prior to the publication of the final award—NPCC encashed the bank guarantees and appropriated the ₹3.5 crore.
The sole arbitrator delivered the final award on December 5, 2017. The tribunal dismissed all monetary claims submitted by Ishvakoo. Uniquely, NPCC had filed no counter-claims before the tribunal to substantiate any independent monetary recovery or loss arising out of the unutilized mobilisation advance.
Although the tribunal considered whether Ishvakoo was entitled to discharge the bank guarantees and claim bank charges, it rendered no specific finding that Ishvakoo had misappropriated or failed to utilise the mobilisation advance. Furthermore, the tribunal's analysis failed to address the consequences of NPCC encashing the bank guarantees prior to the award being rendered.
Judicial Trajectory in the High Court
Aggrieved by the award, Ishvakoo instituted proceedings under Section 34 of the Act to challenge the arbitral decision. Alongside, Ishvakoo filed a fresh Section 9 application seeking an order directing NPCC to refund or deposit the ₹3.5 crore encashed via the bank guarantees.
On April 5, 2019, a Single Judge of the Delhi High Court allowed Ishvakoo’s Section 9 petition. The High Court noted that:
NPCC had not preferred any counter-claim before the arbitrator.
No finding existed in the award establishing non-utilisation of the mobilisation advance.
Retaining ₹3.5 crore without an affirmative arbitral decree would amount to unjust enrichment.
The High Court directed NPCC to deposit ₹3.5 crore with its Registry, to be invested in an interest-bearing fixed deposit with a nationalised bank. A Division Bench of the Delhi High Court subsequently dismissed NPCC’s appeal (FAO(OS)(COMM) No. 113/2019) on May 21, 2019, upholding the Single Judge's direction. NPCC then carried the matter to the Supreme Court.
Legal Analysis of Applicable Frameworks
The Supreme Court examined the statutory interplay between three critical provisions of the Arbitration and Conciliation Act, 1996:
| ARBITRATION AND CONCILIATION ACT, 1996 |
+-----------------------------------------------------------------------+
v v v
+--------------+ +--------------+ +--------------+
| SECTION 9 | | SECTION 34 | | SECTION 36 |
| Interim | | Setting Aside| | Enforcement |
| Protection | | Arbitral | | & Execution |
| Measures | | Award | | of Awards |
+--------------+ +--------------+ +--------------+
1. Section 9: Interim Measures by Court
Section 9 empowers a party to apply to a court for interim measures of protection before, during, or after the arbitral proceedings, but prior to the enforcement of the award under Section 36. The broad discretion conferred on courts allows them to pass orders for the preservation, interim custody, or sale of goods, or the securing of amounts in dispute. The statutory phrase granting power to order "such other interim measure of protection as may appear to the court to be just and convenient" provides necessary equitable flexibility.
2. Section 34: Setting Aside Arbitral Award
Section 34 specifies the limited statutory grounds under which an arbitral award can be challenged, such as patent illegality, conflict with the public policy of India, or procedural unfairness.
3. Section 36: Enforcement
Section 36 governs the execution of arbitral awards once the period for challenging the award under Section 34 expires or when such challenge is rejected.
Key Legal Precedents Considered
The Bench placed reliance on key precedents to define the threshold of post-award interim relief:
Home Care Retail Marts Pvt. Ltd. v. Haresh N. Sanghavi
The Supreme Court reiterated the legal principle established in Home Care Retail Marts, holding that an award debtor is not strictly disentitled from seeking Section 9 relief post-award. However, the court emphasized that the threshold for granting relief to an unsuccessful party is substantially higher. Such relief must be restricted to "rare and compelling cases" where the denial of interim protection would cause irreparable injury and render the Section 34 remedy illusory.
Essar House Private Limited v. Arcellor Mittal Nippon Steel India Limited
Referencing Essar House, the Court highlighted that while exercising Section 9 powers, courts must apply fundamental principles governing civil interim relief under the Code of Civil Procedure, 1908 (CPC)—such as prima facie case, balance of convenience, and irreparable loss—without being rigidly bound by every technical requirement of Order XXXVIII Rule 5 of the CPC.
Adhunik Steels Ltd. v. Orissa Manganese and Minerals (P) Ltd.
The Bench cited Adhunik Steels to affirm that Section 9 relief cannot be granted in a vacuum. The court must evaluate well-settled principles of equity, ensuring that any grant of interim measures promotes the overall efficacy of arbitration.
Findings and Final Supreme Court Directions
The Supreme Court concluded that Ishvakoo successfully met the heightened burden required of an award debtor. The Court highlighted four core factors:
Breach of Initial High Court Order: The 2005 High Court order expressly required an executable finding of recovery before NPCC could encash the bank guarantees. Encashing the guarantees prior to the award without an affirmative award violated the intent of that judicial arrangement.
Absence of Counter-Claim: NPCC never filed a counter-claim to establish its entitlement to retain the ₹3.5 crore mobilisation advance.
Unjust Enrichment: Retaining ₹3.5 crore while no tribunal had awarded NPCC those funds created an inequitable situation of unjust enrichment pending Section 34 adjudication.
Preservation of Section 34 Efficacy: Requiring NPCC to deposit the funds into court preserved the subject matter without determining the ultimate merits of the award challenge.
Dismissing NPCC's appeal, the Supreme Court granted NPCC four weeks to deposit ₹3.5 crore with the Registry of the Delhi High Court. The Registry was directed to keep the funds in an auto-renewing fixed deposit with a nationalised bank until the Section 34 petition is finally decided. The Apex Court clarified that its observations are strictly limited to the Section 9 proceedings and will not influence the independent determination of the Section 34 challenge on its merits.
Searchable Index & Comprehensive FAQ
================================================================================
QUICK REFERENCE SEARCH INDEX
================================================================================
[1.0] SECTION 9 SCOPE & APPLICABILITY
└─ [1.1] Can an award debtor file a Section 9 petition post-award?
└─ [1.2] What is the legal threshold for an award debtor to get relief?
└─ [1.3] What key factors guide the Court’s discretion under Section 9?
[2.0] BANK GUARANTEES & UNJUST ENRICHMENT
└─ [2.1] Why was NPCC ordered to deposit ₹3.5 crore despite winning?
└─ [2.2] How does the absence of a counter-claim affect retention of funds?
└─ [2.3] What constitutes "unjust enrichment" in post-award scenarios?
[3.0] PROCEDURAL & INTER-SECTIONAL INTERPLAY
└─ [3.1] How do Sections 9, 34, and 36 interact under the 1996 Act?
└─ [3.2] Are CPC rules strictly applicable to Section 9 proceedings?
└─ [3.3] Does a Section 9 order impact the outcome of a Section 34 challenge?
================================================================================
Detailed Frequently Asked Questions (FAQ)
[1.1] Can an award debtor or losing party file a petition under Section 9 of the Arbitration Act after the award is passed?
Yes. An award debtor or losing party in an arbitration is legally entitled to file a post-award petition under Section 9 of the Arbitration and Conciliation Act, 1996. The Supreme Court confirmed in National Projects Construction Corporation Ltd. v. Ishvakoo (India) Pvt. Ltd. that access to Section 9 is not restricted solely to the winning party (award holder).
[1.2] What is the threshold for an award debtor to successfully obtain Section 9 interim relief?
The legal threshold for an award debtor is substantially higher than that for an award holder. Courts will grant interim relief to an award debtor only in "rare and compelling cases" where withholding protection would cause irreparable injury, lead to unjust enrichment, or destroy the efficacy of the pending challenge under Section 34.
[1.3] What essential judicial parameters must a court evaluate under Section 9?
Courts must evaluate standard equitable principles applicable to interim injunctions:
Establishment of a prima facie case.
Balance of convenience favouring the applicant.
Risk of irreparable harm or injury if relief is denied.
Whether the party approached the court with reasonable expedition.
Whether the measure is necessary to preserve the subject matter in dispute.
[2.1] Why was NPCC required to deposit ₹3.5 crore even though Ishvakoo’s arbitral claims were dismissed?
Even though Ishvakoo’s claims were dismissed, NPCC had filed no counter-claim seeking recovery or forfeit of the mobilisation advance. Because NPCC encashed the bank guarantees before the award without an affirmative award decree in its favor, permitting NPCC to retain the funds during the Section 34 challenge would amount to unjust enrichment.
[2.2] What role does the absence of a counter-claim play in post-award interim relief?
The absence of a counter-claim means that the arbitral tribunal made no judicial determination authorizing the respondent to recover or retain the funds in question. When a party encashes a bank guarantee without a counter-claim or tribunal finding validating the retention, it holds the money without an executable decree, making court intervention under Section 9 justified.
[2.3] What is "unjust enrichment" in the context of arbitration guarantees?
Unjust enrichment occurs when one party retains money or benefits at the expense of another without a lawful legal basis or judicial authorization. In this case, NPCC held ₹3.5 crore from encashed bank guarantees despite having no arbitral award directing Ishvakoo to pay that sum, thereby creating an inequitable financial advantage during pending appeals.
[3.1] How do Sections 9, 34, and 36 function together in the scheme of the 1996 Act?
Section 9 provides interim protective measures to safeguard property, funds, or rights before, during, or after arbitration until enforcement.
Section 34 provides the procedural mechanism to challenge and set aside an arbitral award on specific statutory grounds.
Section 36 governs the execution and enforcement of the arbitral award as a decree of the court once challenges are resolved or elapsed.
[3.2] Are courts strictly bound by the Code of Civil Procedure (CPC) when deciding Section 9 applications?
No. While the fundamental equitable principles underlying the CPC (such as Order XXXVIII Rule 5) guide the court’s discretion, courts exercising Section 9 jurisdiction are not bound by rigid procedural formalities. The court maintains broad discretion to pass orders that are "just and convenient" to uphold the integrity of arbitration.
[3.3] Will the findings or observations made in a Section 9 order impact the final outcome of a Section 34 petition?
No. Observations made while deciding a Section 9 interim petition are strictly confined to evaluating interim protection. The Supreme Court explicitly clarified that Section 34 proceedings must be adjudicated independently on their own legal merits, completely uninfluenced by interlocutory Section 9 orders.

