Case at a Glance
Two buyers from Kinnaur paid about Rs. 1.12 crore for a 3 BHK independent floor in Omaxe’s ‘Celestia Royal’ project at New Chandigarh, with possession promised by 31 July 2023. The developer offered possession by email in January 2025 without a completion certificate and pleaded Covid-19 force majeure and the buyers’ payment delays. The Punjab State Commission held that an offer without a completion certificate and the promised amenities is not valid possession, rejected the Covid plea because the relief period ended before the 2021 agreement, allowed only 129 days’ extension, and directed the developer and its Managing Directors to obtain the completion certificate, hand over possession and pay 9% interest from the revised due date of 7 December 2023.
The complainants booked Independent Floor No. IRTC/II/CROYAL/FF/700, a first-floor 3 BHK unit with a super area of 2,550 sq. ft., in the ‘Celestia Royal Chandigarh’ project of Omaxe New Chandigarh Developers Pvt. Ltd. The price was Rs. 1,07,45,259, and an application of 31 March 2021 was followed by allotment and an agreement in July 2021. They took a home loan of Rs. 71,19,604 from SBI under a tripartite agreement and paid Rs. 1,11,79,644.90 in all. Possession was due by 31 July 2023. The developer says it obtained an occupancy certificate on 30 November 2024 and offered possession by email on 29 January 2025, without a completion certificate. The buyers called this “paper possession” and filed a complaint under Section 47 of the Consumer Protection Act, 2019, seeking possession with amenities, 18% interest and compensation.
The developer pleaded force majeure on account of Covid-19, relying on the Government of India advisory of 13 May 2020 and RERA Punjab extensions, and the second Covid wave in 2021. It said the buyers had delayed payments by 337 days in total, entitling it to extend the possession date under Clause 7.3, that the buyers were investors who lived in Kinnaur, that 6% interest was the appropriate rate, and that its Managing Directors had been wrongly impleaded.
The Key Question Before the Court
Is an offer of possession made without a completion certificate and promised amenities a valid offer, and can a developer rely on Covid-19 force majeure for a project agreement signed in 2021?
Why the Commission rejected the developer’s defences
On consumer status, the Commission held that the developer had not proved any investment purpose and that a “mere bald statement is insufficient.” On force majeure, it noted that the Covid-related extension “had already elapsed” before the agreement was executed in July 2021, and that Clause 7.1 covered only events affecting the regular development of the project. Relying on Faqir Chand Gulati v. Uppal Agencies Pvt. Ltd., which holds a builder liable to compensate if it fails to obtain a completion certificate, and the National Commission’s decision in Inderjit Singh Bakshi v. S.M.V. Agencies Private Limited that “An allottee is not obliged to take possession of a flat unless it is complete in every respect”, it held that an offer without a completion certificate and the brochure amenities “does not constitute a valid and lawful possession.” It also referred to Wing Commander Arifur Rahman Khan and Aleya Sultana v. DLF Southern Homes Pvt. Ltd. on failure to provide promised amenities.
On the payment delays, the Commission accepted only 129 of the 337 days claimed as a valid extension, because the remaining period was linked to the invalid offer of possession; the revised due date therefore became 7 December 2023. Since time was of the essence under Clause 5 and “primary liability lies upon the OPs to complete the project as promised in the Agreement”, deficiency in service and unfair trade practice were established. The Managing Directors were held jointly and severally liable. The Commission fixed interest at 9% per annum, rejecting both the 18% sought by the buyers and the 6% offered by the developer, and distinguished the High Court’s RERA appeal decision in Signature Global (India) Limited v. Praveen Kumar Gupta, on which the developer relied.
What the Court Actually Held
- The complaint is partly allowed; the developer and its Managing Directors are jointly and severally liable.
- An offer of possession made without a completion certificate and the promised amenities is not valid and lawful possession.
- Covid-19 force majeure was rejected because the relief period had elapsed before the 2021 agreement; only 129 days of payment delay extend the due date, to 7 December 2023.
- The developer must obtain the completion certificate, then hand over physical possession with brochure amenities, pay 9% per annum interest on amounts paid (excluding taxes) from 7 December 2023, and on later payments from their dates, until the certificates are delivered, and pay Rs. 22,000 as litigation expenses.
Why This Judgment Matters
- It confirms that homebuyers can refuse an offer of possession that comes without a completion certificate, and still claim delay interest.
- It limits the Covid-19 defence for projects whose agreements were signed after the pandemic relief periods ended.
- It shows how consumer commissions apportion the buyer’s own payment delays instead of letting a developer extend the date by the full period claimed.
What Should Advocates Take Away From the Judgment?
For Homebuyers
- Before accepting possession, ask for the completion certificate and check that brochure amenities are in place.
- Keep your payment record; only proved delays can extend the developer’s deadline.
- A developer’s claim that you are an investor must be proved, not merely stated.
For Counsel
- Rely on Faqir Chand Gulati v. Uppal Agencies Pvt. Ltd. and Inderjit Singh Bakshi v. S.M.V. Agencies Private Limited against ‘paper possession’.
- Compare the dates of Covid extensions with the date of the agreement to defeat force majeure.
- Implead the Managing Directors where the facts support joint and several liability.
Key Takeaways
- Possession without a completion certificate is not valid possession.
- Covid-19 force majeure does not help where the agreement was signed after the relief period ended.
- Only 129 days of buyer payment delay were allowed, fixing the due date at 7 December 2023.
- 9% delay interest runs until the completion and occupancy certificates are delivered.
Frequently Asked Questions
Can I refuse possession if the builder has no completion certificate?
In this case the Punjab State Commission held that an offer without a completion certificate and promised amenities does not constitute valid and lawful possession.
Does Covid-19 excuse delay in every housing project?
No. The Commission rejected the plea because the Covid-related extension had elapsed before the agreement was signed in July 2021.
What interest did the Commission award for the delay?
Interest at 9% per annum on the amounts paid, excluding taxes, from the revised due date of 7 December 2023 until the certificates are delivered.
Conclusion
The order puts the burden squarely on the developer to deliver a complete, certified unit. A possession letter sent before the completion certificate does not stop delay interest, and a pandemic that ended before the agreement was signed cannot be pleaded as force majeure.
Practical takeaway: Homebuyers offered possession without a completion certificate should record their objection in writing and claim delay interest until a valid, certified offer is made.