Case at a Glance
Power Grid Corporation, the Central Transmission Utility, built two LILO (loop-in loop-out) arrangements at the Tuticorin Pooling Station that served as the interim evacuation route for Coastal Energen’s power plant, because the generator’s own dedicated transmission line was not ready until October 2016. CERC accepted the LILOs’ commercial operation dates of January 2015 and held the generator liable for the transmission charges until its line was commissioned. APTEL reversed this, saying the LILOs were not used and their COD should be reconsidered. The Supreme Court set aside APTEL’s orders and restored CERC’s, holding that the LILO elements are includable in tariff and that the generator, which delayed its line, must bear the charges for the interim period.
The Tuticorin Pooling Station was planned to collect power from three generators, including Coastal Energen (now Moxie Power Generation Ltd.). Under the original plan the generator was to build a dedicated transmission line (DTL) to the pooling station; as an interim arrangement, Standing Committee decisions provided for LILOs of the Tuticorin JV–Madurai line at the pooling station. The Bulk Power Transmission Agreement was signed on 24 February 2010, investment approval came on 12 December 2011, and the scheduled COD of the transmission system was 11 April 2014. Generation began on 23 December 2014. The first LILO circuit achieved COD on 4 January 2015 and the second on 8 January 2015, after time overruns of about nine months.
The generator’s DTL was commissioned only on 27 October 2016, and its long-term open access became operational on 1 December 2016. Power Grid claimed non-PoC transmission charges of Rs. 15,43,26,909 for 4 January 2015 to 27 October 2016. By its tariff order of 29 July 2016, CERC accepted the CODs on the basis of RLDC and CEA certificates, refused to condone the time overrun (with liberty to Power Grid at truing-up) and held that the generator must pay transmission charges until its DTL was commissioned. APTEL held that the LILOs were permanent, not temporary, assets, that no power flowed through them, that the upstream line delay made the DTL delay irrelevant, and that the COD should be revisited.
The Key Question Before the Court
Is Power Grid entitled to transmission tariff for LILOs built under statutory planning as the interim evacuation route, and must the generating company whose dedicated transmission line was delayed bear those charges until the line is commissioned?
The dedicated line is the generator’s obligation
Walking through the Electricity Act scheme, the Court divided transmission into three stages: the dedicated transmission line, the CTU network and the distribution system, and said, “The DTL, hence, is the obligation of the generating station.” The generator argued that electricity took the path of least resistance through the Tuticorin JV–Madurai line, so the LILOs were never put to beneficial use; the Court rejected this, observing that “There cannot be two opinions on this, and the contention raised is rejected,” and that “generation, transmission, supply and consumption are clearly admitted.” It also held that “the delay in implementation of the upstream transmission to Salem does not affect the evacuation arrangement at all.”
On COD, the Court held that Regulation 4(3)(ii) of the Tariff Regulations applies only where the delay is attributable to the generator or to upstream or downstream parties, and CERC’s approach in accepting the CODs was correct. Paragraph 72 of CERC’s order, on which TANGEDCO relied, was only a record of TANGEDCO’s contentions and “cannot be termed as a finding of the CERC.” The Standing Committee decision on the LILOs under Section 29(4) bound all stakeholders, and the generator had not objected at that stage. The Court drew on Power Grid Corporation of India Ltd. v. Madhya Pradesh Power Transmission Co. Ltd., (2025) 05 SC CK 0219, PTC India Ltd. v. Central Electricity Regulatory Commission, (2010) 03 SC CK 0014 and Energy Watchdog v. Central Electricity Regulatory Commission on CERC’s powers under Sections 79 and 178.
What the Court Actually Held
- The LILO elements are includable in the transmission tariff from 4 January 2015 until the generator’s DTL was established on 27 October 2016, as non-PoC charges.
- APTEL’s interpretation of the commercial operation date was erroneous; CERC rightly accepted the CODs on the basis of the RLDC and CEA certificates.
- The generating company that delayed its dedicated transmission line is liable for the transmission charges for that period, in line with the Court’s precedents.
- Both APTEL orders were set aside, the CERC order was restored and the appeals were allowed.
Why This Judgment Matters
- It places the cost of interim transmission arrangements on the party whose delay made them necessary, rather than on consumers through pooled charges.
- It rejects the ‘path of least resistance’ argument as a way to avoid paying for assets built under statutory planning.
- It clarifies how Regulation 4(3)(ii) on commercial operation dates is to be applied.
What Should Advocates Take Away From the Judgment?
For Generators and Utilities
- Delay in building your dedicated transmission line can make you liable for interim transmission charges.
- Object to transmission planning at the Standing Committee stage; silence there is held against you later.
- Open access charges paid separately do not cancel liability for capital-cost tariff.
For Counsel
- Distinguish what CERC actually found from what it merely recorded as a party’s contention.
- Use the three-stage view of transmission (DTL, CTU network, distribution) to allocate obligations.
- Regulation 4(3)(ii) turns on who caused the delay; build the factual record on that.
Key Takeaways
- The dedicated transmission line is the generator’s obligation.
- LILOs built as the interim evacuation route are includable in tariff until the DTL is ready.
- The generator that delayed its line pays the non-PoC charges for that period.
- CERC’s order is restored; APTEL’s orders are set aside.
Frequently Asked Questions
Who pays for a temporary transmission arrangement when a generator’s own line is late?
In this case the Supreme Court held that the generating company that delayed its dedicated transmission line must bear the transmission charges for the interim LILO arrangement until its line was commissioned.
Does it matter that power may have physically flowed through another line?
The Court rejected the argument that the LILOs were not used because electricity took the path of least resistance, noting that generation, transmission, supply and consumption were admitted.
What did the Supreme Court decide in Power Grid v. TANGEDCO?
It set aside both APTEL orders, restored CERC’s order accepting the LILO CODs of 4 and 8 January 2015, and allowed Power Grid’s appeals.
Conclusion
The judgment allocates risk in transmission planning in a commonsense way: the party that does not finish its own part of the evacuation system on time pays for the stop-gap that keeps its power flowing.
Practical takeaway: Generators should treat their dedicated line timelines as cost-bearing obligations; delay can translate directly into transmission charges.