The Environment Impact Assessment regime rests on one sequencing rule: appraisal before construction. The 2017 notification and a 2021 OM created a path for projects that had started without clearance to seek it afterwards — on payment and conditions — and environmental groups led by Vanashakti challenged that as a licence for fait accompli development.
The Key Question Before the Court
Can environmental clearance ever be granted after a project has commenced — and do the 2017 notification and 2021 OM survive?
Act I — May 2025: The Ban
Justice Oka's judgment for the bench declared the 2017 notification and the 2021 OM illegal and struck them down, restraining the Centre from issuing similar measures: ex post facto clearance is alien to a regime whose whole point is prior appraisal, and development that begins in violation cannot buy legitimacy later.
Act II — November 2025: The Recall
On review by the Confederation of Real Estate Developers' Associations of India, the majority (Chief Justice Gavai and Justice Chandran) recalled the May judgment as per incuriam — it had overlooked co-equal benches taking a different view — and invoked the public interest against demolishing completed projects housing lakhs of people. Justice Bhuyan's dissent held the line of the original ruling: retrospective clearances, he maintained, have no place in environmental law. The recall restored the matters for fresh hearing.
Act III — July 2026: The Settlement
The re-heard matters were decided in July 2026 by a bench led by Chief Justice Surya Kant. The outcome holds the regime's core while sparing its past: prior environmental clearance remains mandatory, and projects commenced without it generally cannot be regularised; at the same time, the 2017 notification — as a measure of delegated legislation — was upheld as valid. The sequencing rule stands for the future, with the notification's one-time regularisation window treated as lawfully made.
What the Courts Actually Held
- May 2025: the 2017 notification and 2021 OM permitting ex post facto ECs were struck down; the Centre restrained from similar measures.
- November 2025: that judgment was recalled on review, 2:1, as per incuriam, with completed projects' fate weighing in the public interest; Bhuyan J dissented.
- July 2026: prior EC reaffirmed as mandatory — violators generally cannot be regularised — while the 2017 notification was upheld as valid delegated legislation.
Why This Trilogy Matters
- It is the defining environmental-law contest of 2025–26, pitting the polluter-pays logic of prior appraisal against the human cost of demolition.
- The final position gives project proponents no comfort for the future: starting without clearance remains unregularisable as a rule.
- The review round is a study in per incuriam doctrine — and in how finality yields when co-equal precedent is overlooked.
- For the EIA bar, pending violation cases now turn on which regime — the notification's window or the general bar — covers them.
What Should Advocates Take Away From the Judgments?
For Environmental Petitioners
- The principle survives: press the mandatory-prior-EC rule against every post-commencement application outside the upheld notification's confines.
For Project Proponents
- Treat clearance as a condition precedent in fact, not just law — the 2026 ruling forecloses regularisation as a strategy, whatever the 2017 notification once allowed.
Key Takeaways
- Prior environmental clearance is mandatory; post-facto regularisation is the rare exception, not a route.
- The May 2025 strike-down was recalled 2:1 as per incuriam.
- Justice Bhuyan's dissent keeps the absolutist position alive in the law reports.
- The 2017 notification survives as valid delegated legislation.
Frequently Asked Questions
As the law stands after July 2026, prior clearance is mandatory and such projects generally cannot be regularised; only what falls within the upheld 2017 notification's own scheme ever could.
The review majority found it per incuriam for overlooking co-equal precedent, and weighed the public interest against demolishing completed projects; Justice Bhuyan dissented.
The July 2026 decision upheld it as valid delegated legislation, even while reaffirming that prior clearance is the rule — read the final judgment for how the two holdings interact in a given case.
Conclusion
Fourteen months of litigation ended close to where it began: the environment's protection lies in appraisal before the first brick — with the past, once, forgiven.
Practical takeaway: Date the project against the clearance: after this trilogy, construction first and clearance later is a plan with no legal future.
Vanashakti v. Union of India (16 May 2025) · recalled on review in CREDAI v. Vanashakti (18 November 2025) · finally decided (July 2026) Read the full judgment:
Vanashakti v. Union of India (16 May 2025)
CREDAI v. Vanashakti (18 November 2025)