← All articles

Landmark Judgements

Ex Post Facto Environmental Clearances: From Ban to Recall to the 2026 Settlement — The Vanashakti Trilogy

Updated 19 October 2026
Ex Post Facto Environmental Clearances: From Ban to Recall to the 2026 Settlement — The Vanashakti Trilogy
Case at a glance: One question — can a project that began without environmental clearance be regularised afterwards? — produced three rulings in fourteen months. In May 2025, Vanashakti struck down the 2017 MoEFCC notification and the 2021 Office Memorandum that permitted ex post facto clearances, restraining the Centre from similar measures. In November 2025, a 2:1 review in CREDAI recalled that judgment as per incuriam, Justice Bhuyan dissenting that retrospective clearances have no place in environmental law. In July 2026, a three-judge bench settled the field: prior environmental clearance is mandatory and violators generally cannot be regularised — while the 2017 notification itself was upheld as valid delegated legislation.
3 RoundsOne question
2017Notification in issue
2:1Review split, Bhuyan J dissenting
MandatoryPrior EC (2026)

The Environment Impact Assessment regime rests on one sequencing rule: appraisal before construction. The 2017 notification and a 2021 OM created a path for projects that had started without clearance to seek it afterwards — on payment and conditions — and environmental groups led by Vanashakti challenged that as a licence for fait accompli development.

The Key Question Before the Court

Can environmental clearance ever be granted after a project has commenced — and do the 2017 notification and 2021 OM survive?

Act I — May 2025: The Ban

Justice Oka's judgment for the bench declared the 2017 notification and the 2021 OM illegal and struck them down, restraining the Centre from issuing similar measures: ex post facto clearance is alien to a regime whose whole point is prior appraisal, and development that begins in violation cannot buy legitimacy later.

Act II — November 2025: The Recall

On review by the Confederation of Real Estate Developers' Associations of India, the majority (Chief Justice Gavai and Justice Chandran) recalled the May judgment as per incuriam — it had overlooked co-equal benches taking a different view — and invoked the public interest against demolishing completed projects housing lakhs of people. Justice Bhuyan's dissent held the line of the original ruling: retrospective clearances, he maintained, have no place in environmental law. The recall restored the matters for fresh hearing.

Act III — July 2026: The Settlement

The re-heard matters were decided in July 2026 by a bench led by Chief Justice Surya Kant. The outcome holds the regime's core while sparing its past: prior environmental clearance remains mandatory, and projects commenced without it generally cannot be regularised; at the same time, the 2017 notification — as a measure of delegated legislation — was upheld as valid. The sequencing rule stands for the future, with the notification's one-time regularisation window treated as lawfully made.

What the Courts Actually Held

  • May 2025: the 2017 notification and 2021 OM permitting ex post facto ECs were struck down; the Centre restrained from similar measures.
  • November 2025: that judgment was recalled on review, 2:1, as per incuriam, with completed projects' fate weighing in the public interest; Bhuyan J dissented.
  • July 2026: prior EC reaffirmed as mandatory — violators generally cannot be regularised — while the 2017 notification was upheld as valid delegated legislation.

Why This Trilogy Matters

  • It is the defining environmental-law contest of 2025–26, pitting the polluter-pays logic of prior appraisal against the human cost of demolition.
  • The final position gives project proponents no comfort for the future: starting without clearance remains unregularisable as a rule.
  • The review round is a study in per incuriam doctrine — and in how finality yields when co-equal precedent is overlooked.
  • For the EIA bar, pending violation cases now turn on which regime — the notification's window or the general bar — covers them.

What Should Advocates Take Away From the Judgments?

For Environmental Petitioners

  • The principle survives: press the mandatory-prior-EC rule against every post-commencement application outside the upheld notification's confines.

For Project Proponents

  • Treat clearance as a condition precedent in fact, not just law — the 2026 ruling forecloses regularisation as a strategy, whatever the 2017 notification once allowed.

Key Takeaways

  • Prior environmental clearance is mandatory; post-facto regularisation is the rare exception, not a route.
  • The May 2025 strike-down was recalled 2:1 as per incuriam.
  • Justice Bhuyan's dissent keeps the absolutist position alive in the law reports.
  • The 2017 notification survives as valid delegated legislation.

Frequently Asked Questions

Can a project that started without EC get one now?

As the law stands after July 2026, prior clearance is mandatory and such projects generally cannot be regularised; only what falls within the upheld 2017 notification's own scheme ever could.

Why was the May 2025 judgment recalled?

The review majority found it per incuriam for overlooking co-equal precedent, and weighed the public interest against demolishing completed projects; Justice Bhuyan dissented.

Is the 2017 notification valid or not?

The July 2026 decision upheld it as valid delegated legislation, even while reaffirming that prior clearance is the rule — read the final judgment for how the two holdings interact in a given case.

Conclusion

Fourteen months of litigation ended close to where it began: the environment's protection lies in appraisal before the first brick — with the past, once, forgiven.

Practical takeaway: Date the project against the clearance: after this trilogy, construction first and clearance later is a plan with no legal future.

Vanashakti v. Union of India (16 May 2025) · recalled on review in CREDAI v. Vanashakti (18 November 2025) · finally decided (July 2026) Read the full judgment:

Vanashakti v. Union of India (16 May 2025)

CREDAI v. Vanashakti (18 November 2025)

For more judgments, legal opinions and case analysis, visit
courtkutchehry.com

Visit CourtKutchehry →