Case at a Glance
Homebuyers in a Bengaluru project whose possession was due by 31 December 2018 had filed a consumer complaint before the NCDRC against the developer, an associated company, alleged promoters/directors and the landowners. When insolvency (CIRP) began against the developer, the NCDRC adjourned the entire complaint sine die. The Supreme Court held that the Section 14 IBC moratorium “operates against the corporate debtor alone” and gives no independent protection to the other respondents. It directed the NCDRC to hear the complaint against them, while proceedings against the developer remain stayed.
The appellants booked apartments in the project ‘Mantri Manyata Energia’ developed by Respondent No. 1. Construction agreements and agreements for sale of an undivided share in the land were executed with the developer in 2016, with possession due on or before 31 December 2018. Alleging substantial payments, repeated assurances and no delivery, the appellants and other homebuyers filed Consumer Case No. 13 of 2023 before the NCDRC against the developer (Respondent No. 1), an entity said to be associated with the development (Respondent No. 2), alleged promoters or directors (Respondents 3–5) and the landowners (Respondents 6–7), alleging deficiency in service and unfair trade practices.
On 23 August 2024, the NCLT, Bengaluru Bench admitted a Section 9 IBC application against the developer and initiated the corporate insolvency resolution process, triggering a moratorium under Section 14. The homebuyers applied (I.A. No. 14200 of 2024) to continue the complaint against Respondents 2–7, and later sought a rehearing (I.A. No. 15656 of 2024). On 20 January 2025 the NCDRC rejected both, reasoning that the alleged deficiency related only to the developer with whom the agreements were signed, and adjourned the complaint sine die.
The Key Question Before the Court
Does the IBC moratorium against a builder bar homebuyers from continuing their consumer complaint against its associates, directors, promoters and landowners?
The Moratorium Protects the Corporate Debtor — Nobody Else
The Court held that the moratorium is a statutory creation that cannot be enlarged by any adjudicating authority or court: “the moratorium operates against the corporate debtor alone.” Its purpose is limited — “The object of this moratorium is to preserve the assets of the corporate debtor” during resolution. Relying on P. Mohanraj v. Shah Brothers Ispat Pvt. Ltd., (2021) 03 SC CK 0008, Ansal Crown Heights Flat Buyers Association v. Ansal Crown Infrabuild Pvt. Ltd., (2026) 01 SC CK 1863 and Saranga Anilkumar Aggarwal v. Bhavesh Dhirajlal Sheth, (2025) 03 SC CK 0179, it held that “No independent moratorium or independent protection operates in favour of Respondent Nos. 2 to 7.”
The Court also found the NCDRC’s order internally inconsistent: having said liability was yet to be determined, it concluded that only the developer was responsible, and thereby “effectively answered the very question which was yet to be adjudicated.” The question at that stage was only whether the complaint could proceed, and “It was not open to the Commission to foreclose that inquiry at the interlocutory stage.” Objections of privity of contract, maintainability and absence of independent obligations were left open for the NCDRC to decide.
What the Court Actually Held
- The Section 14 IBC moratorium operates against the corporate debtor alone and cannot be extended to its associates, promoters, directors or landowners unless the statute so provides.
- The NCDRC erred in deciding, at an interlocutory stage, that only the developer could be liable.
- The orders rejecting I.A. Nos. 14200 and 15656 of 2024 were set aside, the applications allowed, and the NCDRC directed to hear Consumer Complaint No. 13 of 2023 against Respondents 2–7 in accordance with law.
- Proceedings against the developer (Respondent No. 1) remain governed by the Section 14 moratorium; the appeals were partly allowed, with merits objections left open.
Why This Judgment Matters
- It prevents homebuyers’ remedies from being frozen entirely just because the builder company enters insolvency.
- It reaffirms Ansal Crown Heights: promoters and directors do not get the corporate debtor’s moratorium shield in consumer cases.
- It cautions consumer fora against deciding liability questions at the interlocutory stage.
What Should Advocates Take Away From the Judgment?
For Homebuyers
- If your builder is under CIRP, your consumer case can still go on against other parties you have arrayed, such as directors, promoters or landowners.
- File your claim in the CIRP against the builder as well, since proceedings against the company itself remain stayed.
- Keep agreements and payment records showing the role of each respondent.
For Counsel
- Array all parties with a role in the project and plead their specific obligations to survive objections on privity.
- Cite Tejas J. Shah, Ansal Crown Heights and P. Mohanraj when a forum adjourns the whole complaint on account of a moratorium.
- Expect the respondents to raise privity, maintainability and independent-obligation objections on merits before the NCDRC.
Key Takeaways
- The IBC moratorium protects only the corporate debtor.
- Directors, promoters, associates and landowners get no independent moratorium.
- Consumer fora cannot decide liability at the interlocutory stage.
- The NCDRC must now hear the homebuyers’ complaint against Respondents 2–7.
Frequently Asked Questions
Can I continue my consumer case if the builder goes into insolvency?
Against the builder company itself, proceedings remain stayed by the Section 14 moratorium. But as this judgment holds, the case can proceed against other respondents such as directors, promoters or landowners.
Did the Supreme Court hold the directors liable?
No. It only held that the complaint can proceed against them; their liability and objections such as privity of contract are left to the NCDRC.
What precedents did the Court rely on?
P. Mohanraj v. Shah Brothers Ispat, Ansal Crown Heights Flat Buyers Association v. Ansal Crown Infrabuild and Saranga Anilkumar Aggarwal v. Bhavesh Dhirajlal Sheth.
Conclusion
Tejas J. Shah v. Mantri Technology Constellations keeps the doors of consumer fora open for homebuyers whose builders fall into insolvency. The moratorium is a shield for the corporate debtor’s assets, not a blanket immunity for everyone connected with a delayed project.
Practical takeaway: When a builder enters CIRP, file your claim with the resolution professional and press your consumer complaint against the other respondents — the moratorium does not cover them.
Read the full judgment on CourtKutchehry: View judgment →
For more judgments, legal opinions and case analysis, visit courtkutchehry.com

