A Big Bill Is Not a Reason to Cut an Arbitral Award: Supreme Court Restores Dredging Contractor’s Award Against Kolkata Port

A Big Bill Is Not a Reason to Cut an Arbitral Award: Supreme Court Restores Dredging Contractor’s Award Against Kolkata Port

Case at a Glance

A contractor dredged a channel and basin at Sagar Island for the Kolkata Port Trust and was awarded its claims for additional work by an arbitrator in 2003; the award was upheld under Section 34. In a Section 37 appeal, a Division Bench of the Calcutta High Court cut the award to 50% and reduced interest to 6%, saying it shocked the conscience that the extra-work claim exceeded 70% of the original contract value, even though it found the award was not perverse or patently illegal. The Supreme Court held that the size of a claim alone is no ground to interfere, that a completion certificate is not a precondition for payment for work actually done, and that the award could not be partly set aside because its parts were not separable. The award was restored.

The contract was for dredging the river bed and shores at Sagar Island to create a channel and basin, to be completed in 18 months; the original contract value was Rs. 2,86,56,200, of which Rs. 2,79,32,865 had admittedly been paid. By a letter of 19 July 2000 the Port Trust entrusted additional work arising from 100% siltation. The contractor attributed the extra work to adverse weather and to soil conditions that did not match the data supplied by the Port Trust. The pilot station was inaugurated on 17 April 2001 by the Port Trust Chairman using the dredged channel, but no completion certificate was ever issued under the General Conditions of Contract.

The arbitrator, by award dated 3 November 2003, allowed the contractor’s claims for additional work on the basis of pre-work and post-work levels and joint measurements. A single judge upheld the award under Section 34 of the Arbitration and Conciliation Act, 1996. In the Port Trust’s Section 37 appeal, the Division Bench recorded that the award was not based on ‘no evidence’ and was not perverse or patently illegal, but reduced it to 50% of the arbitrator’s quantification with 6% interest from 8 February 2002, because the additional-work claim exceeded 70% of the original contract value. Both sides appealed: the contractor against the reduction, and the Port Trust seeking to set aside the award entirely.

The Key Question Before the Court

Can a court hearing a Section 37 appeal reduce an arbitral award to half on the ground that the claim for additional work is too large compared with the original contract value, when it finds the award is neither perverse nor patently illegal?

Conscience must have a reason

The Court held that reliance on the 70% figure did not engage any ground available under Section 37. The arbitrator had relied on measurements and pre-work and post-work levels, and the Division Bench had not examined the nature of the additional work at all. Following Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India, (2019) 05 SC CK 0037, the ‘most basic notions of morality or justice’ test needs a substantive reason, and “the words are not to be applied on a mere lip service.” The Division Bench itself had found that no completion certificate was issued, and its absence did not by itself defeat the contractor’s entitlement to be paid for work actually done.

The Port Trust relied on Gayatri Balasamy v. M/s ISG Novasoft Technologies Limited, (2025) 04 SC CK 0302 to argue for partial setting aside. The Court explained that under that Constitution Bench ruling an award can be set aside in part only where the valid and invalid portions are separable; here the measurements and invoices were of one character and could not be split. Following Pam Developments Private Ltd. v. State of West Bengal, (2019) 07 SC CK 0036, a government entity is to be treated like any other party, and its status cannot justify cutting a claim without substantive grounds. Batliboi Environmental Engineers Ltd. v. Hindustan Petroleum Corporation Ltd., (2023) 09 SC CK 0050 was distinguished as a case about damages, not invoices raised for additional work.

What the Court Actually Held

  • The size of an additional-work claim relative to the original contract value is not, by itself, a ground under Section 37 to reduce an arbitral award.
  • Refusal to issue a completion certificate does not by itself defeat a contractor’s entitlement to payment for work actually done.
  • An award can be partly set aside only where valid and invalid portions are separable, as explained in Gayatri Balasamy; a uniform measurement-based claim cannot be arbitrarily halved.
  • The Division Bench judgment was set aside, the contractor’s appeal allowed and the arbitral award restored; the Port Trust’s appeal was disposed of.

Why This Judgment Matters

  • It stops appellate courts from trimming awards by a rough percentage simply because the numbers seem large.
  • It applies Gayatri Balasamy on partial setting aside in a practical way: severability, not discretion, decides.
  • It reminds public bodies that their status does not earn them more lenient review in arbitration.

What Should Advocates Take Away From the Judgment?

For Contractors

  • Keep joint measurements and pre-work and post-work level records; they carried the award here.
  • Lack of a completion certificate does not by itself bar payment for work actually done.
  • A Section 37 court must give a real legal reason before reducing an award.

For Counsel

Key Takeaways

  • A large claim is not, on its own, a ground to cut an arbitral award.
  • Section 37 review is narrow and needs a recognised ground.
  • No completion certificate does not mean no payment for work done.
  • The 2003 award in favour of the contractor stands restored.

Frequently Asked Questions

Can a High Court reduce an arbitral award because the claim seems too high?

Not on that basis alone. In this case the Supreme Court held that the Division Bench’s reduction by 50%, based only on the claim exceeding 70% of the contract value, did not engage any Section 37 ground.

Does the absence of a completion certificate bar a contractor’s claim?

The Court held that refusal to issue a completion certificate does not by itself defeat the entitlement to bills for work actually done.

What was the final order in Marino Dredgeco v. Port of Kolkata?

The Supreme Court set aside the Calcutta High Court Division Bench judgment, allowed the contractor’s appeal and restored the arbitral award; the Port Trust’s appeal was disposed of.

Conclusion

The judgment protects the finality of arbitration against intuitive trimming. Once a court accepts that an award is based on evidence and is not perverse, it cannot reduce it because the figure feels disproportionate; it must point to a legal ground and, for partial interference, a separable portion.

Practical takeaway: In Section 37 appeals, ask whether the court has identified a recognised ground and a severable part; if not, a percentage cut is vulnerable.

Read the full judgment on CourtKutchehry: View judgment →