₹5 Per Sq Ft for an Eight-Year Delay Is ‘Unconscionable’: Chandigarh Consumer Commission Gives 83-Year-Old ATS Buyer 9% Interest Instead

₹5 Per Sq Ft for an Eight-Year Delay Is ‘Unconscionable’: Chandigarh Consumer Commission Gives 83-Year-Old ATS Buyer 9% Interest Instead

Case at a Glance

An 83-year-old buyer and his co-allottee paid ₹57.75 lakh — over 90% — for a flat in ATS Golf Meadows Lifestyle at Derabassi, Mohali, due by 15 March 2018. Possession was offered only on 9 December 2024 on a partial completion certificate, and handed over on 29 August 2026. The District Commission gave only the agreement’s ₹5 per sq ft per month delay compensation and ₹50,000. The Chandigarh State Commission called that clause “manifestly one-sided, unreasonable and unconscionable”, held the 2024 offer invalid without occupation and completion certificates, and awarded 9% annual interest on the entire deposit from 15 March 2018 to 29 August 2026, plus ₹75,000 compensation and ₹35,000 costs.

Bachan Singh and Harmeet Singh booked Apartment No. 05152 (2,950 sq ft, 15th floor, Tower 05) in ‘ATS Golf Meadows Lifestyle’, Village Madhopur, Tehsil Derabassi, SAS Nagar, under a buyer’s agreement of 16 September 2015 for ₹65,20,000. They paid ₹57,75,950, partly through a ₹28 lakh HDFC housing loan under a tripartite agreement. Clause 14 promised possession within 24 months plus six months’ grace, i.e. by 15 March 2018; Clause 15 offered delay compensation of only ₹5 per sq ft of super area per month, while Clause 6(iii) let the developer charge 18% interest on the buyer’s defaults.

The buyers filed Consumer Complaint No. 439 of 2021 on 13 July 2021. The developer called them investors and pleaded Covid-19 as force majeure; the directors’ defence was struck off for not filing a reply within 45 days. On 20 March 2026 the District Commission directed possession, ₹5 per sq ft per month from 15 March 2018 to the 9 December 2024 offer, and ₹50,000 lump sum, dismissing the complaint against HDFC. The buyers appealed for enhancement; physical possession was handed over on 29 August 2026 while the appeal was pending.

The Key Question Before the Court

Is a builder’s contractual delay compensation of ₹5 per sq ft per month binding on a buyer, and from when to when is interest payable where possession is offered without an occupation certificate?

One-sided clauses yield to fair interest

The Commission held the ₹5 per sq ft clause “manifestly one-sided, unreasonable and unconscionable”: it gave the builder little incentive to finish on time, since paying the nominal sum was cheaper than raising funds to complete, while the buyer faced 18% for his own defaults. Relying on Pioneer Urban Land & Infrastructure Ltd. v. Govindan Raghavan, (2019) 04 SC CK 0173, Wg. Cdr. Arifur Rahman Khan v. DLF Southern Homes Pvt. Ltd., (2020) 08 SC CK 0026, Kolkata West International City Pvt. Ltd. v. Devasis Rudra, (2019) 03 SC CK 0101, Ireo Grace Realtech Pvt. Ltd. v. Abhishek Khanna, (2021) 01 SC CK 0012 and Experion Developers Pvt. Ltd. v. Sushma Ashok Shiroor, (2022) 04 SC CK 0015, it held that a delay of more than seven and a half years was substantial deficiency in service, making interest on the deposits “justified” and “necessary”.

On the period, the Commission held the 9 December 2024 offer invalid because it was based only on a partial completion certificate, while Clause 16 required the occupation and final completion certificates. Interest therefore runs from the committed date to actual possession on 29 August 2026. Following DLF Homes Panchkula Pvt. Ltd. v. Himanshu Arora, DLF Homes Panchkula (P) Ltd. v. Sushila Devi and NCDRC decisions including Shreya Kumar v. Ansal Housing & Construction Ltd. and Atul Kulshrestha v. Emaar India Ltd., it fixed the rate at 9% per annum. The ₹50,000 lump sum was found “on the lower side” and enhanced. The complaint against HDFC remained dismissed.

What the Court Actually Held

  • ATS Estates and its two directors, jointly and severally, must pay 9% per annum interest on the entire amount deposited, from 15 March 2018 to 29 August 2026, within 30 days, failing which 12% penal interest applies on the accumulated amount.
  • They must also pay ₹75,000 for mental agony, harassment and deficiency in service and ₹35,000 litigation costs within 30 days, failing which 9% interest applies.
  • The ₹5 per sq ft per month delay clause is one-sided and unconscionable, and the 9 December 2024 offer without occupation and completion certificates was not a valid offer of possession.
  • The developer may deduct the balance sale consideration from these amounts without any interest, penalty or holding charges; the complaint against HDFC stays dismissed.

Why This Judgment Matters

  • Nominal delay-compensation clauses appear in many buyer agreements; this ruling joins a long line refusing to enforce them.
  • It confirms that a possession offer without an occupation certificate does not stop the interest clock.
  • Elderly buyers who waited eight years get meaningful compensation rather than a token sum.

What Should Advocates Take Away From the Judgment?

For Homebuyers

  • A low fixed delay rate in your agreement is not the last word; consumer fora can award interest instead.
  • Do not treat a possession offer as valid unless it is backed by an occupation certificate and completion certificate as the agreement requires.
  • Claim interest up to actual possession, and ask that no holding charges be levied on the balance.

For Counsel

Key Takeaways

  • ₹5 per sq ft per month delay compensation was held unconscionable.
  • 9% interest on all deposits runs from 15 March 2018 to 29 August 2026.
  • An offer of possession on a partial completion certificate was not valid.
  • Compensation was raised to ₹75,000 with ₹35,000 costs.

Frequently Asked Questions

Is a builder’s ₹5 per sq ft delay clause binding?

The Chandigarh State Commission held the clause one-sided, unreasonable and unconscionable and replaced it with 9% annual interest on the amount deposited for the delay period.

Until when is delay interest payable?

Until actual physical possession on 29 August 2026, because the December 2024 offer was based only on a partial completion certificate, while the agreement required occupation and final completion certificates.

Was the bank liable?

No. The complaint against HDFC, the lender under the tripartite agreement, remained dismissed.

Conclusion

For an 83-year-old buyer who paid over 90% of the price in 2015 and got the keys only in 2026, the Commission has replaced a token delay rate with interest that reflects the real cost of an eight-year wait.

Practical takeaway: Buyers facing long delays should not settle for the agreement’s nominal compensation; consumer commissions regularly award interest on deposits up to valid possession.